Pavement removed, as per plan unit price, Ohio

Low bidders on ODOT contracts carried a median of $23.00 per SY for item 202E23001, pavement removed, as per plan, over the 24 months to 12 NOV 2026, across 41 low bids. Half of all 145 bids fell between $15.69 and $40.00.

Owner
Ohio DOT
Item
202E23001
Unit
SY
Latest letting
12 NOV 2026
$23.00Low bidder's median, per SY
$24.00Median of all bids, per SY
41Contracts in the window

By year of letting

Pavement removed, as per plan, ODOT: unit prices by year
YearContractsLow bidsLow-bid medianAll bidsMedian, all bids
20201616$16.6272$16.05
20212929$12.50129$16.00
20222123$18.0070$15.75
20232524$19.2584$19.75
20241919$23.5056$27.40
20252222$22.0076$21.25
20261515$20.0061$25.00
Pavement removed, as per plan, ODOT: unit prices by year

Bid prices as published, not adjusted for inflation.

By county

Pavement removed, as per plan, ODOT: unit prices by county, last 24 months
CountyLow bidsLow-bid medianAll bidsMedian, all bids
FRA3$7.5016$9.00
CUY4$25.5015$28.00
LAK4$19.0014$21.75
KNO3$42.0010$41.00
Pavement removed, as per plan, ODOT: unit prices by county, last 24 months

Countys with at least three low bids, over the last 24 months.

By quantity

Pavement removed, as per plan, ODOT: low bidder's median by quantity band
Quantity (SY)Low bidsLow-bid median
4 to 11910$45.00
123 to 48610$31.00
555 to 1,92710$20.50
1,977 to 305,32511$14.00
Pavement removed, as per plan, ODOT: low bidder's median by quantity band

The low bids split into four bands of equal count by the quantity on the contract. Larger quantities usually carry lower unit prices.

Latest contracts with this item

Latest ODOT contracts carrying Pavement removed, as per plan
LetContractCountyQuantityLow bidder's priceMedianBidsLow bidderSource
12 NOV 2026260506LUC37.60$110.00$112.502SHELLY COMPANYODOT
12 NOV 2026260521GUE10,852$14.00$14.508SHELLY & SANDS INCODOT
15 OCT 2026260426LAK1,927$18.00$24.005GEAUGA HIGHWAY COODOT
15 OCT 2026260472ROS119$50.00$86.753FILLMORE CONSTRUCTIONODOT
08 OCT 2026260398HAM114,234$16.64$16.641JOHN R JURGENSEN COMPANYODOT
01 OCT 2026260418ADA555$27.00$27.005ALLARD EXCAVATION LLCODOT
17 SEP 2026260402CUY1,977$21.00$29.845CATTS CONSTRUCTION INCODOT
17 SEP 2026260408JAC579$15.00$22.507ALAN STONE CO INCODOT
17 SEP 2026260410MAR4$40.00$40.002SHELLY & SANDS INCODOT
13 AUG 2026260364KNO20,325$15.00$13.624COMPLETE GENERAL CONSTRUCTION COMPANYODOT
13 AUG 2026260370SEN123$75.00$78.005M & B ASPHALT CO INCODOT
07 MAY 2026260235CUY1,420$12.70$22.506R M H CONCRETE & FOUNDATIONS INCODOT
23 APR 2026260222ROS34$20.00$65.005FILLMORE CONSTRUCTIONODOT
26 MAR 2026260158WOO840$23.00$23.002GERKEN PAVING INCODOT
15 JAN 2026260028UNI40$13.75$13.751SHELLY COMPANYODOT
Latest ODOT contracts carrying Pavement removed, as per plan

Filter this item by your own quantity, county and period, or check your price against it, in the ODOT explorer.

How these prices were read

ODOT Official Bid Tabulation PDFs from its public DigitalPaper bid tab cabinet, January 2020 to November 2026 (the source links open after DigitalPaper starts a guest session). ODOT prints unit prices to two decimals but computes line amounts from the full price, so a few bids miss their total and are left out. Descriptions are cut at about 50 characters, as ODOT prints them.

  • Statistics leave out bids over three times the low bid, zero or negative prices and token prices under 5% of the median.
  • Item codes and units are ODOT's own: this item is compared with ODOT contracts only.
  • Prices are bid prices, not paid prices, and are not adjusted for inflation. Use them as a reference range, never as a quote.

Your own bid history, read the same way

Mirage deploys AI agents for heavy civil estimating teams: quantities from the plan set, specs and addenda read, and bid tabs compared, inside your systems and your rules.

We use your email to reply to you and, now and then, to tell you about Mirage. You can opt out at any time. Privacy policy