Portable barrier, 50", as per plan unit price, Ohio

Low bidders on ODOT contracts carried a median of $30.12 per FT for item 622E41011, portable barrier, 50", as per plan, over the 24 months to 12 NOV 2026, across 15 low bids. Half of all 43 bids fell between $22.00 and $34.00.

Owner
Ohio DOT
Item
622E41011
Unit
FT
Latest letting
08 OCT 2026
$30.12Low bidder's median, per FT
$29.96Median of all bids, per FT
15Contracts in the window

By year of letting

Portable barrier, 50", as per plan, ODOT: unit prices by year
YearContractsLow bidsLow-bid medianAll bidsMedian, all bids
202066$13.5023$13.00
202144$13.0029$22.00
202266$19.5921$20.00
20231010$17.5033$19.89
202466$18.7713$25.00
202577$30.0024$28.69
202677$34.0017$30.12
Portable barrier, 50", as per plan, ODOT: unit prices by year

Bid prices as published, not adjusted for inflation.

By quantity

Portable barrier, 50", as per plan, ODOT: low bidder's median by quantity band
Quantity (FT)Low bidsLow-bid median
732 to 1,7553$40.00
2,819 to 11,9894$32.75
14,832 to 29,4904$28.95
36,440 to 63,6454$20.79
Portable barrier, 50", as per plan, ODOT: low bidder's median by quantity band

The low bids split into four bands of equal count by the quantity on the contract. Larger quantities usually carry lower unit prices.

Latest contracts with this item

Latest ODOT contracts carrying Portable barrier, 50", as per plan
LetContractCountyQuantityLow bidder's priceMedianBidsLow bidderSource
08 OCT 2026260398HAM26,590$49.51$49.511JOHN R JURGENSEN COMPANYODOT
07 MAY 2026260227AUG4,610$34.00$32.963HELMS AND SONS EXCAVATINGODOT
07 MAY 2026260251MOT36,440$30.12$30.882JOHN R JURGENSEN COMPANYODOT
26 MAR 2026260152HAS29,490$22.00$24.502SHELLY & SANDS INCODOT
19 FEB 2026260096SUM2,819$50.00$28.004KENMORE CONSTRUCTION CO INCODOT
29 JAN 2026260002HEN63,645$15.50$20.003E S WAGNER - VERNON NAGEL JOINT VENTUREODOT
29 JAN 2026260058LAW732$40.00$53.002AXIS CIVIL CONSTRUCTION LLCODOT
23 OCT 2025250459CRA11,989$24.00$24.974SHELLY & SANDS INCODOT
25 SEP 2025250439MIA1,755$50.13$50.676R B JERGENS CONTRACTORS INCODOT
15 MAY 2025250238HAM14,832$35.91$32.642JOHN R JURGENSEN COMPANYODOT
27 MAR 2025250150UNI38,396$24.57$21.504MILLER BROS CONST INCODOT
27 FEB 2025250076FRA1,510$30.00$30.001SHELLY & SANDS INCODOT
27 FEB 2025250130MOT5,328$31.50$31.503BARRETT PAVING MATERIALS INCODOT
30 JAN 2025250001FRA62,797$17.00$16.754SHELLY & SANDS INCODOT
19 DEC 2024240548CUY19,699$15.00$18.502RUHLIN COMPANYODOT
Latest ODOT contracts carrying Portable barrier, 50", as per plan

Filter this item by your own quantity, county and period, or check your price against it, in the ODOT explorer.

How these prices were read

ODOT Official Bid Tabulation PDFs from its public DigitalPaper bid tab cabinet, January 2020 to November 2026 (the source links open after DigitalPaper starts a guest session). ODOT prints unit prices to two decimals but computes line amounts from the full price, so a few bids miss their total and are left out. Descriptions are cut at about 50 characters, as ODOT prints them.

  • Statistics leave out bids over three times the low bid, zero or negative prices and token prices under 5% of the median.
  • Item codes and units are ODOT's own: this item is compared with ODOT contracts only.
  • Prices are bid prices, not paid prices, and are not adjusted for inflation. Use them as a reference range, never as a quote.

Your own bid history, read the same way

Mirage deploys AI agents for heavy civil estimating teams: quantities from the plan set, specs and addenda read, and bid tabs compared, inside your systems and your rules.

We use your email to reply to you and, now and then, to tell you about Mirage. You can opt out at any time. Privacy policy