Railing (twin steel tube) unit price, Ohio
Low bidders on ODOT contracts carried a median of $250.00 per FT for item 517E70000, railing (twin steel tube), over the 24 months to 12 NOV 2026, across 19 low bids. Half of all 72 bids fell between $220.00 and $270.00.
- Owner
- Ohio DOT
- Item
- 517E70000
- Unit
- FT
- Latest letting
- 17 SEP 2026
By year of letting
| Year | Contracts | Low bids | Low-bid median | All bids | Median, all bids |
|---|---|---|---|---|---|
| 2020 | 44 | 48 | $150.00 | 233 | $150.00 |
| 2021 | 32 | 34 | $178.50 | 178 | $170.00 |
| 2022 | 14 | 16 | $267.50 | 48 | $250.00 |
| 2023 | 16 | 16 | $229.00 | 62 | $228.88 |
| 2024 | 5 | 5 | $255.00 | 19 | $249.75 |
| 2025 | 9 | 10 | $254.00 | 39 | $248.00 |
| 2026 | 8 | 8 | $244.00 | 26 | $247.00 |
Bid prices as published, not adjusted for inflation.
By quantity
| Quantity (FT) | Low bids | Low-bid median |
|---|---|---|
| 25 to 50 | 4 | $195.00 |
| 85 to 139 | 5 | $238.00 |
| 176 to 191 | 5 | $260.00 |
| 210 to 358 | 5 | $265.00 |
The low bids split into four bands of equal count by the quantity on the contract. Larger quantities usually carry lower unit prices.
Latest contracts with this item
| Let | Contract | County | Quantity | Low bidder's price | Median | Bids | Low bidder | Source |
|---|---|---|---|---|---|---|---|---|
| 17 SEP 2026 | 260415 | District 3 | 50 | $198.00 | $249.00 | 2 | LAKE ERIE CONSTRUCTION COMPANY | ODOT |
| 16 JUL 2026 | 260336 | District 5 | 25 | $195.00 | $215.00 | 2 | LAKE ERIE CONSTRUCTION COMPANY | ODOT |
| 07 MAY 2026 | 260228 | CAR | 101 | $238.00 | $239.00 | 2 | SUNESIS CONSTRUCTION CO | ODOT |
| 23 APR 2026 | 260206 | MAR | 358 | $260.00 | $246.00 | 3 | DOUBLE Z CONSTRUCTION COMPANY | ODOT |
| 12 MAR 2026 | 260130 | NOB | 91 | $250.00 | $235.00 | 5 | J & J BRIDGE COMPANY INC | ODOT |
| 19 FEB 2026 | 260077 | BRO | 270 | $270.00 | $270.00 | 4 | COMPLETE GENERAL CONSTRUCTION COMPANY | ODOT |
| 19 FEB 2026 | 260092 | PAU | 284.32 | $204.50 | $204.50 | 3 | R G ZACHRICH CONSTRUCTION INC | ODOT |
| 29 JAN 2026 | 260060 | MOE | 210 | $265.00 | $250.00 | 5 | SHELLY & SANDS INC | ODOT |
| 18 DEC 2025 | 250580 | BEL | 182 | $300.00 | $287.50 | 4 | STANLEY MILLER CONSTRUCTION COMPANY | ODOT |
| 18 DEC 2025 | 250593 | MOE | 252 | $280.00 | $262.50 | 6 | ALAN STONE CO INC | ODOT |
| 18 DEC 2025 | 250602 | District 3 | 50 | $192.00 | $208.50 | 2 | LAKE ERIE CONSTRUCTION COMPANY | ODOT |
| 26 JUN 2025 | 250329 | District 5 | 25 | $195.00 | $195.00 | 3 | LAKE ERIE CONSTRUCTION COMPANY | ODOT |
| 08 MAY 2025 | 250240 | BEL | 178 | $258.00 | $275.00 | 3 | SHELLY & SANDS INC | ODOT |
| 10 APR 2025 | 250196 | NOB | 134 | $213.00 | $217.50 | 6 | J & J BRIDGE COMPANY INC | ODOT |
| 27 MAR 2025 | 258003 | GAL | 191 | $270.00 | $270.00 | 1 | COMPLETE GENERAL CONSTRUCTION COMPANY | ODOT |
Filter this item by your own quantity, county and period, or check your price against it, in the ODOT explorer.
How these prices were read
ODOT Official Bid Tabulation PDFs from its public DigitalPaper bid tab cabinet, January 2020 to November 2026 (the source links open after DigitalPaper starts a guest session). ODOT prints unit prices to two decimals but computes line amounts from the full price, so a few bids miss their total and are left out. Descriptions are cut at about 50 characters, as ODOT prints them.
- Statistics leave out bids over three times the low bid, zero or negative prices and token prices under 5% of the median.
- Item codes and units are ODOT's own: this item is compared with ODOT contracts only.
- Prices are bid prices, not paid prices, and are not adjusted for inflation. Use them as a reference range, never as a quote.
Your own bid history, read the same way