Reinforced concrete approach slabs (t=15") unit price, Ohio

Low bidders on ODOT contracts carried a median of $360.00 per SY for item 526E25000, reinforced concrete approach slabs (t=15"), over the 24 months to 12 NOV 2026, across 37 low bids. Half of all 117 bids fell between $360.00 and $450.00.

Owner
Ohio DOT
Item
526E25000
Unit
SY
Latest letting
01 OCT 2026
$360.00Low bidder's median, per SY
$400.00Median of all bids, per SY
18Contracts in the window

By year of letting

Reinforced concrete approach slabs (t=15"), ODOT: unit prices by year
YearContractsLow bidsLow-bid medianAll bidsMedian, all bids
20201414$255.0058$260.00
2021910$252.5051$275.00
2022710$400.0026$387.50
202388$320.0019$320.00
202469$322.0025$400.00
2025813$345.2549$375.00
2026819$425.0056$430.00
Reinforced concrete approach slabs (t=15"), ODOT: unit prices by year

Bid prices as published, not adjusted for inflation.

By county

Reinforced concrete approach slabs (t=15"), ODOT: unit prices by county, last 24 months
CountyLow bidsLow-bid medianAll bidsMedian, all bids
HEN7$360.0021$375.72
FRA4$325.0016$356.50
HAS5$430.0010$447.50
ROS4$317.008$391.00
Reinforced concrete approach slabs (t=15"), ODOT: unit prices by county, last 24 months

Countys with at least three low bids, over the last 24 months.

By quantity

Reinforced concrete approach slabs (t=15"), ODOT: low bidder's median by quantity band
Quantity (SY)Low bidsLow-bid median
133 to 2229$365.00
223 to 2369$420.00
245 to 2899$345.25
297 to 33610$357.50
Reinforced concrete approach slabs (t=15"), ODOT: low bidder's median by quantity band

The low bids split into four bands of equal count by the quantity on the contract. Larger quantities usually carry lower unit prices.

Latest contracts with this item

Latest ODOT contracts carrying Reinforced concrete approach slabs (t=15")
LetContractCountyQuantityLow bidder's priceMedianBidsLow bidderSource
01 OCT 2026260405DEL245$525.00$508.523SHELLY & SANDS INCODOT
01 OCT 2026260432POR224$505.00$505.004SHELLY & SANDS INCODOT
16 JUL 2026260328CUY328$498.00$500.004FECHKO EXCAVATING LLCODOT
16 JUL 2026260328CUY214$529.00$514.504FECHKO EXCAVATING LLCODOT
26 MAR 2026260152HAS234$430.00$452.502SHELLY & SANDS INCODOT
26 MAR 2026260152HAS234$430.00$452.502SHELLY & SANDS INCODOT
26 MAR 2026260152HAS299$430.00$445.002SHELLY & SANDS INCODOT
26 MAR 2026260152HAS299$425.00$437.502SHELLY & SANDS INCODOT
26 MAR 2026260152HAS289$445.00$455.002SHELLY & SANDS INCODOT
19 FEB 2026260103District 1133$452.39$451.194BCC OHIO INCODOT
29 JAN 2026260002HEN152$360.00$393.193E S WAGNER - VERNON NAGEL JOINT VENTUREODOT
29 JAN 2026260002HEN223$360.00$374.083E S WAGNER - VERNON NAGEL JOINT VENTUREODOT
29 JAN 2026260002HEN223$360.00$374.083E S WAGNER - VERNON NAGEL JOINT VENTUREODOT
29 JAN 2026260002HEN230$360.00$381.773E S WAGNER - VERNON NAGEL JOINT VENTUREODOT
29 JAN 2026260002HEN326$360.00$381.383E S WAGNER - VERNON NAGEL JOINT VENTUREODOT
Latest ODOT contracts carrying Reinforced concrete approach slabs (t=15")

Filter this item by your own quantity, county and period, or check your price against it, in the ODOT explorer.

How these prices were read

ODOT Official Bid Tabulation PDFs from its public DigitalPaper bid tab cabinet, January 2020 to November 2026 (the source links open after DigitalPaper starts a guest session). ODOT prints unit prices to two decimals but computes line amounts from the full price, so a few bids miss their total and are left out. Descriptions are cut at about 50 characters, as ODOT prints them.

  • Statistics leave out bids over three times the low bid, zero or negative prices and token prices under 5% of the median.
  • Item codes and units are ODOT's own: this item is compared with ODOT contracts only.
  • Prices are bid prices, not paid prices, and are not adjusted for inflation. Use them as a reference range, never as a quote.

Your own bid history, read the same way