Shoulder preparation unit price, Ohio

Low bidders on ODOT contracts carried a median of $1.53 per SY for item 617E20000, shoulder preparation, over the 24 months to 12 NOV 2026, across 51 low bids. Half of all 120 bids fell between $0.60 and $2.79.

Owner
Ohio DOT
Item
617E20000
Unit
SY
Latest letting
29 OCT 2026
$1.53Low bidder's median, per SY
$1.63Median of all bids, per SY
52Contracts in the window

By year of letting

Shoulder preparation, ODOT: unit prices by year
YearContractsLow bidsLow-bid medianAll bidsMedian, all bids
20202626$0.25105$0.40
20213333$0.50123$0.50
20223231$1.2796$1.26
20232525$1.0062$1.00
20242221$0.5052$1.07
20252525$1.6161$1.57
20262323$2.0052$2.13
Shoulder preparation, ODOT: unit prices by year

Bid prices as published, not adjusted for inflation.

By county

Shoulder preparation, ODOT: unit prices by county, last 24 months
CountyLow bidsLow-bid medianAll bidsMedian, all bids
HAM8$2.3815$2.24
MAD3$1.4014$1.32
DEL3$1.009$2.00
CLI3$1.536$1.58
BUT3$2.706$2.54
Shoulder preparation, ODOT: unit prices by county, last 24 months

Countys with at least three low bids, over the last 24 months.

By quantity

Shoulder preparation, ODOT: low bidder's median by quantity band
Quantity (SY)Low bidsLow-bid median
106 to 3,03612$5.00
3,547 to 6,65313$1.45
6,665 to 10,00313$1.40
10,278 to 34,71013$1.00
Shoulder preparation, ODOT: low bidder's median by quantity band

The low bids split into four bands of equal count by the quantity on the contract. Larger quantities usually carry lower unit prices.

Latest contracts with this item

Latest ODOT contracts carrying Shoulder preparation
LetContractCountyQuantityLow bidder's priceMedianBidsLow bidderSource
29 OCT 2026260399CUY1,284$8.00$6.004TRI-MOR CORPODOT
29 OCT 2026260453DEL27,423$1.00$1.003SHELLY & SANDS INCODOT
29 OCT 2026260455ASD362$1.00$5.502KOKOSING CONSTRUCTION COMPANY INCODOT
29 OCT 2026260474WAR5,564$2.00$2.042BARRETT PAVING MATERIALS INCODOT
01 OCT 2026260434RIC7,089$0.10$0.172KOKOSING CONSTRUCTION COMPANY INCODOT
17 SEP 2026260400ASD17,024$0.25$0.172SHELLY & SANDS INCODOT
17 SEP 2026260410MAR10,003$2.50$1.382SHELLY & SANDS INCODOT
30 JUL 2026260347FAY23,043$3.07$2.542JOHN R JURGENSEN COMPANYODOT
11 JUN 2026260282ATB106$6.00$25.004A P O'HORO COMPANYODOT
11 JUN 2026260283COL869$2.00$2.382SHELLY & SANDS INCODOT
07 MAY 2026260237FRA3,036$1.50$2.002SHELLY & SANDS INCODOT
09 APR 2026260133PIC148$24.00$14.002SHELLY COMPANYODOT
09 APR 2026260179MED6,306$1.25$0.802KARVO COMPANIES INCODOT
09 APR 2026260191POR593$5.00$5.001KARVO COMPANIES INCODOT
26 MAR 2026260124HAM10,278$1.00$1.672BARRETT PAVING MATERIALS INCODOT
Latest ODOT contracts carrying Shoulder preparation

Filter this item by your own quantity, county and period, or check your price against it, in the ODOT explorer.

How these prices were read

ODOT Official Bid Tabulation PDFs from its public DigitalPaper bid tab cabinet, January 2020 to November 2026 (the source links open after DigitalPaper starts a guest session). ODOT prints unit prices to two decimals but computes line amounts from the full price, so a few bids miss their total and are left out. Descriptions are cut at about 50 characters, as ODOT prints them.

  • Statistics leave out bids over three times the low bid, zero or negative prices and token prices under 5% of the median.
  • Item codes and units are ODOT's own: this item is compared with ODOT contracts only.
  • Prices are bid prices, not paid prices, and are not adjusted for inflation. Use them as a reference range, never as a quote.

Your own bid history, read the same way