Sign hanger assembly, mast arm unit price, Ohio

Low bidders on ODOT contracts carried a median of $449.10 per EACH for item 630E79100, sign hanger assembly, mast arm, over the 24 months to 12 NOV 2026, across 23 low bids. Half of all 70 bids fell between $367.50 and $500.00.

Owner
Ohio DOT
Item
630E79100
Unit
EACH
Latest letting
12 NOV 2026
$449.10Low bidder's median, per EACH
$445.23Median of all bids, per EACH
22Contracts in the window

By year of letting

Sign hanger assembly, mast arm, ODOT: unit prices by year
YearContractsLow bidsLow-bid medianAll bidsMedian, all bids
202055$365.0018$307.50
20212223$360.50105$350.00
20221818$385.0057$385.00
20231718$397.5052$395.00
202488$428.0223$416.24
20251415$441.3650$436.26
202677$449.1018$438.50
Sign hanger assembly, mast arm, ODOT: unit prices by year

Bid prices as published, not adjusted for inflation.

By quantity

Sign hanger assembly, mast arm, ODOT: low bidder's median by quantity band
Quantity (EACH)Low bidsLow-bid median
1 to 25$450.00
2 to 66$450.00
6 to 106$433.18
14 to 1106$422.05
Sign hanger assembly, mast arm, ODOT: low bidder's median by quantity band

The low bids split into four bands of equal count by the quantity on the contract. Larger quantities usually carry lower unit prices.

Latest contracts with this item

Latest ODOT contracts carrying Sign hanger assembly, mast arm
LetContractCountyQuantityLow bidder's priceMedianBidsLow bidderSource
12 NOV 2026260495COL2$500.00$500.003CORNERSTONE ELECTRIC INCODOT
15 OCT 2026260478District 410$425.00$425.001LAKE ERIE CONSTRUCTION COMPANYODOT
30 JUL 2026260354MAH110$580.00$577.504MARUCCI & GAFFNEY EXCAVATING COODOT
11 JUN 2026260297District 710$630.36$630.361CAPITAL ELECTRIC LINE BUILDERS INCODOT
07 MAY 2026260258District 126$285.00$390.003PERRAM ELECTRIC INCODOT
23 APR 2026260218District 21$250.00$338.952PERRAM ELECTRIC INCODOT
26 MAR 2026260149HAM18$449.10$225.754SUNESIS CONSTRUCTION COODOT
18 DEC 2025250557HAM6$355.00$355.004EAGLE BRIDGE COODOT
23 OCT 2025250514MAH50$320.00$367.502LAKE ERIE CONSTRUCTION COMPANYODOT
25 SEP 2025250439MIA10$441.36$392.506R B JERGENS CONTRACTORS INCODOT
11 SEP 2025250411HAM2$242.00$560.005FORD DEVELOPMENT CORPODOT
28 AUG 2025250398TRU5$825.00$427.126KIRILA CONTRACTORS INCODOT
17 JUL 2025250343CUY5$287.00$358.004PERRAM ELECTRIC INCODOT
17 JUL 2025250352District 732$516.78$516.781CAPITAL ELECTRIC LINE BUILDERS INCODOT
22 MAY 2025250272COL2$450.00$405.002M P DORY COODOT
Latest ODOT contracts carrying Sign hanger assembly, mast arm

Filter this item by your own quantity, county and period, or check your price against it, in the ODOT explorer.

How these prices were read

ODOT Official Bid Tabulation PDFs from its public DigitalPaper bid tab cabinet, January 2020 to November 2026 (the source links open after DigitalPaper starts a guest session). ODOT prints unit prices to two decimals but computes line amounts from the full price, so a few bids miss their total and are left out. Descriptions are cut at about 50 characters, as ODOT prints them.

  • Statistics leave out bids over three times the low bid, zero or negative prices and token prices under 5% of the median.
  • Item codes and units are ODOT's own: this item is compared with ODOT contracts only.
  • Prices are bid prices, not paid prices, and are not adjusted for inflation. Use them as a reference range, never as a quote.

Your own bid history, read the same way

Mirage deploys AI agents for heavy civil estimating teams: quantities from the plan set, specs and addenda read, and bid tabs compared, inside your systems and your rules.

We use your email to reply to you and, now and then, to tell you about Mirage. You can opt out at any time. Privacy policy