Special - retaining wall, precast concrete lagging unit price, Ohio
Low bidders on ODOT contracts carried a median of $28.00 per SF for item 530E51010, special - retaining wall, precast concrete lagging, over the 24 months to 12 NOV 2026, across 11 low bids. Half of all 39 bids fell between $30.00 and $50.00.
- Owner
- Ohio DOT
- Item
- 530E51010
- Unit
- SF
- Latest letting
- 12 NOV 2026
By year of letting
| Year | Contracts | Low bids | Low-bid median | All bids | Median, all bids |
|---|---|---|---|---|---|
| 2022 | 12 | 16 | $20.00 | 66 | $23.25 |
| 2023 | 8 | 8 | $21.50 | 33 | $26.78 |
| 2024 | 10 | 10 | $24.50 | 42 | $25.50 |
| 2025 | 7 | 7 | $25.00 | 21 | $31.00 |
| 2026 | 4 | 4 | $41.50 | 18 | $40.00 |
Bid prices as published, not adjusted for inflation.
Latest contracts with this item
| Let | Contract | County | Quantity | Low bidder's price | Median | Bids | Low bidder | Source |
|---|---|---|---|---|---|---|---|---|
| 12 NOV 2026 | 260521 | GUE | 7,000 | $38.00 | $39.50 | 8 | SHELLY & SANDS INC | ODOT |
| 29 OCT 2026 | 260465 | HOL | 1,950 | $26.00 | $30.00 | 5 | DENNISON BRIDGE INC | ODOT |
| 07 MAY 2026 | 260242 | JEF | 2,856 | $70.00 | $75.00 | 3 | MARUCCI & GAFFNEY EXCAVATING CO | ODOT |
| 23 APR 2026 | 260221 | FRA | 2,695 | $45.00 | $51.00 | 2 | COMPLETE GENERAL CONSTRUCTION COMPANY | ODOT |
| 09 OCT 2025 | 250404 | HAM | 288 | $50.00 | $108.42 | 3 | GREAT LAKES CONSTRUCTION CO | ODOT |
| 24 APR 2025 | 254015 | MRG | 2,024 | $30.00 | $36.00 | 2 | ALAN STONE CO INC | ODOT |
| 27 FEB 2025 | 250137 | WAS | 1,716 | $24.00 | $31.00 | 3 | ALAN STONE CO INC | ODOT |
| 27 FEB 2025 | 254010 | MEG | 1,804 | $24.60 | $24.60 | 1 | ALAN STONE CO INC | ODOT |
| 13 FEB 2025 | 250096 | MOE | 2,977 | $20.00 | $30.00 | 3 | ALAN STONE CO INC | ODOT |
| 16 JAN 2025 | 250012 | GAL | 1,320 | $25.00 | $30.00 | 4 | ALAN STONE CO INC | ODOT |
| 16 JAN 2025 | 250037 | HOL | 2,016 | $28.00 | $35.00 | 5 | SHELLY & SANDS INC | ODOT |
| 26 SEP 2024 | 240451 | BEL | 1,403 | $25.00 | $26.00 | 5 | ALAN STONE CO INC | ODOT |
| 23 MAY 2024 | 240300 | ATH | 2,433 | $23.25 | $25.00 | 3 | OHIO-WEST VIRGINIA EXCAVATING CO | ODOT |
| 23 MAY 2024 | 240314 | ATH | 1,628 | $25.00 | $25.00 | 5 | ALAN STONE CO INC | ODOT |
| 09 MAY 2024 | 240279 | MRG | 1,458 | $22.57 | $25.79 | 4 | OHIO-WEST VIRGINIA EXCAVATING CO | ODOT |
Filter this item by your own quantity, county and period, or check your price against it, in the ODOT explorer.
How these prices were read
ODOT Official Bid Tabulation PDFs from its public DigitalPaper bid tab cabinet, January 2020 to November 2026 (the source links open after DigitalPaper starts a guest session). ODOT prints unit prices to two decimals but computes line amounts from the full price, so a few bids miss their total and are left out. Descriptions are cut at about 50 characters, as ODOT prints them.
- Statistics leave out bids over three times the low bid, zero or negative prices and token prices under 5% of the median.
- Item codes and units are ODOT's own: this item is compared with ODOT contracts only.
- Prices are bid prices, not paid prices, and are not adjusted for inflation. Use them as a reference range, never as a quote.
Your own bid history, read the same way
Mirage deploys AI agents for heavy civil estimating teams: quantities from the plan set, specs and addenda read, and bid tabs compared, inside your systems and your rules.