Strain pole foundation unit price, Ohio
Low bidders on ODOT contracts carried a median of $7,350.00 per EACH for item 632E64000, strain pole foundation, over the 24 months to 12 NOV 2026, across 12 low bids. Half of all 42 bids fell between $7,175.00 and $9,780.00.
- Owner
- Ohio DOT
- Item
- 632E64000
- Unit
- EACH
- Latest letting
- 19 FEB 2026
By year of letting
| Year | Contracts | Low bids | Low-bid median | All bids | Median, all bids |
|---|---|---|---|---|---|
| 2020 | 11 | 11 | $3,605.00 | 47 | $4,500.00 |
| 2021 | 14 | 14 | $5,088.13 | 65 | $5,200.00 |
| 2022 | 10 | 10 | $6,100.00 | 41 | $6,000.00 |
| 2023 | 8 | 8 | $7,300.00 | 29 | $7,250.00 |
| 2024 | 5 | 5 | $6,525.00 | 17 | $8,070.00 |
| 2025 | 11 | 11 | $7,600.00 | 37 | $8,251.72 |
| 2026 | 1 | 1 | $2,362.55 | 5 | $7,773.00 |
Bid prices as published, not adjusted for inflation.
By quantity
| Quantity (EACH) | Low bids | Low-bid median |
|---|---|---|
| 1 to 2 | 3 | $7,050.00 |
| 2 to 4 | 3 | $2,464.00 |
| 4 to 4 | 3 | $9,200.00 |
| 8 to 13 | 3 | $7,100.00 |
The low bids split into four bands of equal count by the quantity on the contract. Larger quantities usually carry lower unit prices.
Latest contracts with this item
| Let | Contract | County | Quantity | Low bidder's price | Median | Bids | Low bidder | Source |
|---|---|---|---|---|---|---|---|---|
| 19 FEB 2026 | 260090 | MOT | 3 | $2,362.55 | $7,773.00 | 5 | Performance Site Development | ODOT |
| 17 JUL 2025 | 250351 | District 6 | 2 | $2,464.00 | $9,720.00 | 7 | ASPLUNDH CONSTRUCTION LLC | ODOT |
| 17 JUL 2025 | 250353 | District 8 | 1 | $9,850.00 | $12,934 | 2 | BANSAL CONSTRUCTION INC | ODOT |
| 22 MAY 2025 | 250263 | UNI | 4 | $9,200.00 | $7,412.50 | 6 | SHELLY COMPANY | ODOT |
| 15 MAY 2025 | 250153 | FAI | 4 | $9,400.00 | $10,200 | 4 | SHELLY & SANDS INC | ODOT |
| 24 APR 2025 | 250216 | District 8 | 8 | $7,100.00 | $8,550.00 | 2 | MILLER CABLE COMPANY | ODOT |
| 24 APR 2025 | 250221 | MUS | 4 | $7,600.00 | $7,600.00 | 3 | MILLER CABLE COMPANY | ODOT |
| 24 APR 2025 | 250228 | STA | 8 | $5,220.00 | $6,360.00 | 2 | WENGER EXCAVATING INC | ODOT |
| 27 MAR 2025 | 250166 | TUS | 2 | $4,925.00 | $4,925.00 | 3 | STANLEY MILLER CONSTRUCTION COMPANY | ODOT |
| 20 MAR 2025 | 250078 | CUY | 1 | $7,050.00 | $7,275.00 | 2 | GREAT LAKES CONSTRUCTION CO | ODOT |
| 27 FEB 2025 | 250076 | FRA | 13 | $11,000 | $11,000 | 1 | SHELLY & SANDS INC | ODOT |
| 30 JAN 2025 | 250047 | FAI | 4 | $8,000.00 | $8,240.00 | 5 | SHELLY COMPANY | ODOT |
| 31 OCT 2024 | 240491 | District 6 | 9 | $6,525.00 | $7,059.50 | 6 | RUHLIN COMPANY | ODOT |
| 09 MAY 2024 | 240265 | District 4 | 2 | $6,500.00 | $8,070.00 | 3 | CORNERSTONE ELECTRIC INC | ODOT |
| 18 APR 2024 | 240258 | MIA | 4 | $13,000 | $15,043 | 3 | MILLER CABLE COMPANY | ODOT |
Filter this item by your own quantity, county and period, or check your price against it, in the ODOT explorer.
How these prices were read
ODOT Official Bid Tabulation PDFs from its public DigitalPaper bid tab cabinet, January 2020 to November 2026 (the source links open after DigitalPaper starts a guest session). ODOT prints unit prices to two decimals but computes line amounts from the full price, so a few bids miss their total and are left out. Descriptions are cut at about 50 characters, as ODOT prints them.
- Statistics leave out bids over three times the low bid, zero or negative prices and token prices under 5% of the median.
- Item codes and units are ODOT's own: this item is compared with ODOT contracts only.
- Prices are bid prices, not paid prices, and are not adjusted for inflation. Use them as a reference range, never as a quote.
Your own bid history, read the same way