Tether wire, with accessories unit price, Ohio

Low bidders on ODOT contracts carried a median of $22.25 per FT for item 632E30600, tether wire, with accessories, over the 24 months to 12 NOV 2026, across 20 low bids. Half of all 64 bids fell between $18.06 and $26.75.

Owner
Ohio DOT
Item
632E30600
Unit
FT
Latest letting
01 OCT 2026
$22.25Low bidder's median, per FT
$22.00Median of all bids, per FT
20Contracts in the window

By year of letting

Tether wire, with accessories, ODOT: unit prices by year
YearContractsLow bidsLow-bid medianAll bidsMedian, all bids
20201010$15.0049$18.64
20212019$15.6594$16.50
20221111$16.0041$16.00
20231010$18.7526$19.88
202477$24.0022$20.02
20251212$22.7543$22.50
202666$20.4813$22.00
Tether wire, with accessories, ODOT: unit prices by year

Bid prices as published, not adjusted for inflation.

By county

Tether wire, with accessories, ODOT: unit prices by county, last 24 months
CountyLow bidsLow-bid medianAll bidsMedian, all bids
FRA4$23.0011$22.00
District 33$18.086$18.09
Tether wire, with accessories, ODOT: unit prices by county, last 24 months

Countys with at least three low bids, over the last 24 months.

By quantity

Tether wire, with accessories, ODOT: low bidder's median by quantity band
Quantity (FT)Low bidsLow-bid median
106 to 3475$20.00
390 to 4395$30.00
465 to 6345$19.85
769 to 2,5435$23.00
Tether wire, with accessories, ODOT: low bidder's median by quantity band

The low bids split into four bands of equal count by the quantity on the contract. Larger quantities usually carry lower unit prices.

Latest contracts with this item

Latest ODOT contracts carrying Tether wire, with accessories
LetContractCountyQuantityLow bidder's priceMedianBidsLow bidderSource
01 OCT 2026260442District 3500$18.08$18.081PERRAM ELECTRIC INCODOT
01 OCT 2026260445District 6500$16.20$18.104PERRAM ELECTRIC INCODOT
07 MAY 2026260237FRA634$22.00$22.002SHELLY & SANDS INCODOT
23 APR 2026260218District 2950$18.95$18.052PERRAM ELECTRIC INCODOT
23 APR 2026260221FRA435$26.00$26.002COMPLETE GENERAL CONSTRUCTION COMPANYODOT
26 MAR 2026260154LAW439$30.00$30.002SHELLY COMPANYODOT
04 DEC 2025250530MAR1,518$23.00$23.005SHELLY & SANDS INCODOT
04 DEC 2025250571ROS390$32.00$48.007COMPLETE GENERAL CONSTRUCTION COMPANYODOT
22 MAY 2025250263UNI415$22.50$17.956SHELLY COMPANYODOT
15 MAY 2025250153FAI465$20.00$22.504SHELLY & SANDS INCODOT
08 MAY 2025250244District 3342$15.00$18.103CORNERSTONE ELECTRIC INCODOT
24 APR 2025250216District 81,000$20.00$22.002MILLER CABLE COMPANYODOT
24 APR 2025250221MUS347$20.00$20.003MILLER CABLE COMPANYODOT
24 APR 2025250228STA769$29.25$20.122WENGER EXCAVATING INCODOT
27 MAR 2025250166TUS127$16.00$16.003STANLEY MILLER CONSTRUCTION COMPANYODOT
Latest ODOT contracts carrying Tether wire, with accessories

Filter this item by your own quantity, county and period, or check your price against it, in the ODOT explorer.

How these prices were read

ODOT Official Bid Tabulation PDFs from its public DigitalPaper bid tab cabinet, January 2020 to November 2026 (the source links open after DigitalPaper starts a guest session). ODOT prints unit prices to two decimals but computes line amounts from the full price, so a few bids miss their total and are left out. Descriptions are cut at about 50 characters, as ODOT prints them.

  • Statistics leave out bids over three times the low bid, zero or negative prices and token prices under 5% of the median.
  • Item codes and units are ODOT's own: this item is compared with ODOT contracts only.
  • Prices are bid prices, not paid prices, and are not adjusted for inflation. Use them as a reference range, never as a quote.

Your own bid history, read the same way

Mirage deploys AI agents for heavy civil estimating teams: quantities from the plan set, specs and addenda read, and bid tabs compared, inside your systems and your rules.

We use your email to reply to you and, now and then, to tell you about Mirage. You can opt out at any time. Privacy policy