Trench, as per plan unit price, Ohio

Low bidders on ODOT contracts carried a median of $13.41 per FT for item 625E29001, trench, as per plan, over the 24 months to 12 NOV 2026, across 8 low bids. Half of all 19 bids fell between $9.00 and $16.88.

Owner
Ohio DOT
Item
625E29001
Unit
FT
Latest letting
01 OCT 2026
$13.41Low bidder's median, per FT
$12.00Median of all bids, per FT
7Contracts in the window

By year of letting

Trench, as per plan, ODOT: unit prices by year
YearContractsLow bidsLow-bid medianAll bidsMedian, all bids
202066$7.5425$8.08
20211111$5.8334$7.10
202266$6.0016$7.28
2023811$12.0027$11.00
202455$10.0018$10.75
202523$15.007$12.00
202633$10.006$14.00
Trench, as per plan, ODOT: unit prices by year

Bid prices as published, not adjusted for inflation.

Latest contracts with this item

Latest ODOT contracts carrying Trench, as per plan
LetContractCountyQuantityLow bidder's priceMedianBidsLow bidderSource
01 OCT 2026260442District 3200$22.15$22.151PERRAM ELECTRIC INCODOT
13 AUG 2026260332STA131$9.00$13.504KENMORE CONSTRUCTION CO INCODOT
16 JUL 2026260338District 111,000$10.00$10.001CORNERSTONE ELECTRIC INCODOT
18 DEC 2025250594NOB2,901$12.00$9.505SHELLY & SANDS INCODOT
27 FEB 2025250076FRA2,055$27.00$27.001SHELLY & SANDS INCODOT
27 FEB 2025250076FRA1,757$15.00$15.001SHELLY & SANDS INCODOT
05 DEC 2024240555HOC2,341$7.36$7.934AXIS CIVIL CONSTRUCTION LLCODOT
14 NOV 2024240536District 3200$14.82$16.912ASPLUNDH CONSTRUCTION LLCODOT
12 SEP 2024240420MEG2,208$10.00$10.007AXIS CIVIL CONSTRUCTION LLCODOT
22 AUG 2024240411District 111,000$12.00$12.402CORNERSTONE ELECTRIC INCODOT
09 MAY 2024240278MRG794$7.50$15.003SHELLY & SANDS INCODOT
30 NOV 2023230585LOR1,478$15.00$10.006CORNERSTONE ELECTRIC INCODOT
27 JUL 2023230409District 111,000$10.00$10.001CORNERSTONE ELECTRIC INCODOT
25 MAY 2023230343LIC25$27.00$27.003SHELLY & SANDS INCODOT
11 MAY 2023230245FRA6,911$12.00$12.002SHELLY & SANDS INCODOT
Latest ODOT contracts carrying Trench, as per plan

Filter this item by your own quantity, county and period, or check your price against it, in the ODOT explorer.

How these prices were read

ODOT Official Bid Tabulation PDFs from its public DigitalPaper bid tab cabinet, January 2020 to November 2026 (the source links open after DigitalPaper starts a guest session). ODOT prints unit prices to two decimals but computes line amounts from the full price, so a few bids miss their total and are left out. Descriptions are cut at about 50 characters, as ODOT prints them.

  • Statistics leave out bids over three times the low bid, zero or negative prices and token prices under 5% of the median.
  • Item codes and units are ODOT's own: this item is compared with ODOT contracts only.
  • Prices are bid prices, not paid prices, and are not adjusted for inflation. Use them as a reference range, never as a quote.

Your own bid history, read the same way

Mirage deploys AI agents for heavy civil estimating teams: quantities from the plan set, specs and addenda read, and bid tabs compared, inside your systems and your rules.

We use your email to reply to you and, now and then, to tell you about Mirage. You can opt out at any time. Privacy policy