Underground warning/marking tape unit price, Ohio
Low bidders on ODOT contracts carried a median of $2.00 per FT for item 625E36010, underground warning/marking tape, over the 24 months to 12 NOV 2026, across 66 low bids. Half of all 223 bids fell between $1.50 and $3.00.
- Owner
- Ohio DOT
- Item
- 625E36010
- Unit
- FT
- Latest letting
- 09 OCT 2025
By year of letting
| Year | Contracts | Low bids | Low-bid median | All bids | Median, all bids |
|---|---|---|---|---|---|
| 2020 | 7 | 7 | $1.00 | 57 | $0.50 |
| 2021 | 71 | 77 | $0.50 | 391 | $0.60 |
| 2022 | 56 | 61 | $1.50 | 217 | $1.50 |
| 2023 | 58 | 63 | $1.68 | 189 | $2.00 |
| 2024 | 52 | 57 | $2.00 | 201 | $2.00 |
| 2025 | 52 | 59 | $2.00 | 200 | $2.00 |
Bid prices as published, not adjusted for inflation.
By county
| County | Low bids | Low-bid median | All bids | Median, all bids |
|---|---|---|---|---|
| HAM | 8 | $2.00 | 23 | $2.00 |
| CUY | 8 | $3.00 | 21 | $2.00 |
| FRA | 3 | $3.00 | 14 | $2.00 |
| District 3 | 4 | $1.40 | 13 | $2.00 |
| FAI | 3 | $3.00 | 12 | $1.79 |
| LIC | 3 | $3.00 | 7 | $1.20 |
| ATH | 3 | $1.90 | 5 | $3.00 |
Countys with at least three low bids, over the last 24 months.
By quantity
| Quantity (FT) | Low bids | Low-bid median |
|---|---|---|
| 4 to 104 | 16 | $2.00 |
| 104 to 536 | 17 | $2.20 |
| 557 to 1,883 | 16 | $2.00 |
| 2,021 to 19,090 | 17 | $1.90 |
The low bids split into four bands of equal count by the quantity on the contract. Larger quantities usually carry lower unit prices.
Latest contracts with this item
| Let | Contract | County | Quantity | Low bidder's price | Median | Bids | Low bidder | Source |
|---|---|---|---|---|---|---|---|---|
| 09 OCT 2025 | 250467 | MAH | 115 | $3.00 | $3.00 | 4 | A P O'HORO COMPANY | ODOT |
| 09 OCT 2025 | 250467 | MAH | 4 | $3.00 | $2.85 | 4 | A P O'HORO COMPANY | ODOT |
| 25 SEP 2025 | 250428 | BRO | 115 | $1.50 | $1.50 | 1 | COMPLETE GENERAL CONSTRUCTION COMPANY | ODOT |
| 25 SEP 2025 | 250446 | District 3 | 42 | $1.30 | $2.00 | 6 | PERRAM ELECTRIC INC | ODOT |
| 11 SEP 2025 | 250399 | WOO | 107 | $2.09 | $2.09 | 3 | VERNON NAGEL INC | ODOT |
| 11 SEP 2025 | 250407 | CUY | 182 | $1.25 | $2.60 | 3 | PERRAM ELECTRIC INC | ODOT |
| 11 SEP 2025 | 250411 | HAM | 118 | $2.20 | $3.00 | 5 | FORD DEVELOPMENT CORP | ODOT |
| 14 AUG 2025 | 250377 | CUY | 277 | $2.50 | $2.25 | 6 | CATTS CONSTRUCTION INC | ODOT |
| 17 JUL 2025 | 250343 | CUY | 1,038 | $1.45 | $1.73 | 4 | PERRAM ELECTRIC INC | ODOT |
| 17 JUL 2025 | 250351 | District 6 | 4,475 | $1.40 | $1.95 | 7 | ASPLUNDH CONSTRUCTION LLC | ODOT |
| 17 JUL 2025 | 250353 | District 8 | 4,730 | $1.65 | $1.49 | 2 | BANSAL CONSTRUCTION INC | ODOT |
| 29 MAY 2025 | 258014 | CUY | 3,170 | $3.00 | $2.25 | 2 | MILLER CABLE COMPANY | ODOT |
| 22 MAY 2025 | 250263 | UNI | 24 | $1.00 | $0.23 | 6 | SHELLY COMPANY | ODOT |
| 22 MAY 2025 | 250278 | HAM | 938 | $2.00 | $2.00 | 2 | COMPLETE GENERAL CONSTRUCTION COMPANY | ODOT |
| 22 MAY 2025 | 250296 | District 12 | 50 | $1.25 | $2.75 | 3 | PERRAM ELECTRIC INC | ODOT |
Filter this item by your own quantity, county and period, or check your price against it, in the ODOT explorer.
How these prices were read
ODOT Official Bid Tabulation PDFs from its public DigitalPaper bid tab cabinet, January 2020 to November 2026 (the source links open after DigitalPaper starts a guest session). ODOT prints unit prices to two decimals but computes line amounts from the full price, so a few bids miss their total and are left out. Descriptions are cut at about 50 characters, as ODOT prints them.
- Statistics leave out bids over three times the low bid, zero or negative prices and token prices under 5% of the median.
- Item codes and units are ODOT's own: this item is compared with ODOT contracts only.
- Prices are bid prices, not paid prices, and are not adjusted for inflation. Use them as a reference range, never as a quote.
Your own bid history, read the same way
Mirage deploys AI agents for heavy civil estimating teams: quantities from the plan set, specs and addenda read, and bid tabs compared, inside your systems and your rules.