Welded stud shear connectors unit price, Ohio

Low bidders on ODOT contracts carried a median of $5.00 per EACH for item 513E20000, welded stud shear connectors, over the 24 months to 12 NOV 2026, across 63 low bids. Half of all 210 bids fell between $4.50 and $6.00.

Owner
Ohio DOT
Item
513E20000
Unit
EACH
Latest letting
29 OCT 2026
$5.00Low bidder's median, per EACH
$5.00Median of all bids, per EACH
46Contracts in the window

By year of letting

Welded stud shear connectors, ODOT: unit prices by year
YearContractsLow bidsLow-bid medianAll bidsMedian, all bids
20202737$3.50201$3.55
20212642$4.22207$4.35
20222024$5.25109$5.25
20233047$5.25161$5.52
20242331$4.7095$5.00
20252536$5.00132$5.20
20261824$4.9968$4.55
Welded stud shear connectors, ODOT: unit prices by year

Bid prices as published, not adjusted for inflation.

By county

Welded stud shear connectors, ODOT: unit prices by county, last 24 months
CountyLow bidsLow-bid medianAll bidsMedian, all bids
UNI7$5.5028$6.00
CUY8$4.6127$4.55
FRA6$5.0016$5.50
SUM3$4.6016$4.55
DEL3$4.4013$4.80
LAK3$4.4511$4.75
HAM5$4.8710$4.79
HAS5$5.0010$5.20
Welded stud shear connectors, ODOT: unit prices by county, last 24 months

Countys with at least three low bids, over the last 24 months.

By quantity

Welded stud shear connectors, ODOT: low bidder's median by quantity band
Quantity (EACH)Low bidsLow-bid median
15 to 2,66415$5.00
2,700 to 3,63616$4.50
3,660 to 6,69616$5.39
7,326 to 18,48016$4.64
Welded stud shear connectors, ODOT: low bidder's median by quantity band

The low bids split into four bands of equal count by the quantity on the contract. Larger quantities usually carry lower unit prices.

Latest contracts with this item

Latest ODOT contracts carrying Welded stud shear connectors
LetContractCountyQuantityLow bidder's priceMedianBidsLow bidderSource
29 OCT 2026260475WOO3,465$3.70$3.703EAGLE BRIDGE COODOT
08 OCT 2026260398HAM5,436$4.99$4.991JOHN R JURGENSEN COMPANYODOT
08 OCT 2026260398HAM6,696$5.29$5.291JOHN R JURGENSEN COMPANYODOT
08 OCT 2026260398HAM7,383$4.87$4.871JOHN R JURGENSEN COMPANYODOT
01 OCT 2026260405DEL3,045$3.70$3.703SHELLY & SANDS INCODOT
13 AUG 2026260345CUY5,220$4.15$4.154GREAT LAKES CONSTRUCTION COODOT
13 AUG 2026260353LOR3,036$4.10$4.102GREAT LAKES CONSTRUCTION COODOT
13 AUG 2026260371SUM3,190$4.50$4.509J D WILLIAMSON CONSTRUCTION CO INCODOT
30 JUL 2026260342ALL3,255$4.50$4.184EAGLE BRIDGE COODOT
07 MAY 2026260237FRA3,240$5.00$4.882SHELLY & SANDS INCODOT
07 MAY 2026260243MIA3,960$6.50$6.504EAGLE BRIDGE COODOT
23 APR 2026260206MAR15$53.25$53.253DOUBLE Z CONSTRUCTION COMPANYODOT
23 APR 2026260216VAN3,636$4.00$4.222VERNON NAGEL INCODOT
09 APR 2026260147DEL2,652$4.40$4.403COMPLETE GENERAL CONSTRUCTION COMPANYODOT
26 MAR 2026260152HAS2,772$5.00$5.202SHELLY & SANDS INCODOT
Latest ODOT contracts carrying Welded stud shear connectors

Filter this item by your own quantity, county and period, or check your price against it, in the ODOT explorer.

How these prices were read

ODOT Official Bid Tabulation PDFs from its public DigitalPaper bid tab cabinet, January 2020 to November 2026 (the source links open after DigitalPaper starts a guest session). ODOT prints unit prices to two decimals but computes line amounts from the full price, so a few bids miss their total and are left out. Descriptions are cut at about 50 characters, as ODOT prints them.

  • Statistics leave out bids over three times the low bid, zero or negative prices and token prices under 5% of the median.
  • Item codes and units are ODOT's own: this item is compared with ODOT contracts only.
  • Prices are bid prices, not paid prices, and are not adjusted for inflation. Use them as a reference range, never as a quote.

Your own bid history, read the same way

Mirage deploys AI agents for heavy civil estimating teams: quantities from the plan set, specs and addenda read, and bid tabs compared, inside your systems and your rules.

We use your email to reply to you and, now and then, to tell you about Mirage. You can opt out at any time. Privacy policy