Work zone edge line, class i, 6", 642 paint unit price, Ohio
Low bidders on ODOT contracts carried a median of $1,175.00 per MI for item 614E22110, work zone edge line, class i, 6", 642 paint, over the 24 months to 12 NOV 2026, across 113 low bids. Half of all 363 bids fell between $858.50 and $2,687.50.
- Owner
- Ohio DOT
- Item
- 614E22110
- Unit
- MI
- Latest letting
- 12 NOV 2026
By year of letting
| Year | Contracts | Low bids | Low-bid median | All bids | Median, all bids |
|---|---|---|---|---|---|
| 2020 | 66 | 68 | $1,157.00 | 293 | $2,210.51 |
| 2021 | 57 | 56 | $1,000.00 | 216 | $1,220.00 |
| 2022 | 55 | 55 | $1,210.00 | 176 | $1,726.50 |
| 2023 | 49 | 49 | $1,415.00 | 135 | $1,500.00 |
| 2024 | 51 | 52 | $1,502.50 | 141 | $1,550.00 |
| 2025 | 57 | 57 | $1,175.00 | 197 | $1,267.00 |
| 2026 | 44 | 45 | $1,225.00 | 139 | $1,335.00 |
Bid prices as published, not adjusted for inflation.
By county
| County | Low bids | Low-bid median | All bids | Median, all bids |
|---|---|---|---|---|
| CUY | 10 | $785.00 | 36 | $800.00 |
| GEA | 6 | $675.00 | 27 | $675.00 |
| HAM | 8 | $1,670.00 | 20 | $2,797.50 |
| JEF | 4 | $2,562.50 | 15 | $3,325.00 |
| BUT | 5 | $1,145.00 | 14 | $1,145.00 |
| BEL | 3 | $2,600.00 | 14 | $3,100.00 |
| HAS | 3 | $4,200.00 | 13 | $4,000.00 |
| CLI | 4 | $1,510.00 | 12 | $1,695.00 |
| LAK | 3 | $900.00 | 11 | $900.00 |
| FRA | 3 | $910.00 | 10 | $965.00 |
| District 7 | 3 | $805.00 | 10 | $805.00 |
| ATH | 4 | $1,125.00 | 10 | $8,950.00 |
Countys with at least three low bids, over the last 24 months.
By quantity
| Quantity (MI) | Low bids | Low-bid median |
|---|---|---|
| 0.03 to 0.60 | 28 | $3,412.50 |
| 0.64 to 5 | 28 | $1,329.74 |
| 5.29 to 24 | 28 | $882.50 |
| 24.14 to 144.57 | 29 | $880.00 |
The low bids split into four bands of equal count by the quantity on the contract. Larger quantities usually carry lower unit prices.
Latest contracts with this item
| Let | Contract | County | Quantity | Low bidder's price | Median | Bids | Low bidder | Source |
|---|---|---|---|---|---|---|---|---|
| 12 NOV 2026 | 260490 | ATH | 36.40 | $1,075.00 | $1,075.00 | 1 | SHELLY & SANDS INC | ODOT |
| 12 NOV 2026 | 260502 | HAM | 0.26 | $5,300.00 | $4,995.00 | 4 | ALAN STONE CO INC | ODOT |
| 29 OCT 2026 | 260461 | HAM | 1.15 | $815.00 | $815.00 | 5 | SUNESIS CONSTRUCTION CO | ODOT |
| 29 OCT 2026 | 268021 | JEF | 0.81 | $1,800.00 | $3,000.00 | 3 | BUDS INC | ODOT |
| 15 OCT 2026 | 260464 | WOO | 16 | $900.00 | $900.00 | 2 | GERKEN PAVING INC | ODOT |
| 01 OCT 2026 | 260424 | FAI | 40.33 | $2,295.00 | $1,797.50 | 2 | SHELLY COMPANY | ODOT |
| 17 SEP 2026 | 260401 | CHP | 112.92 | $680.00 | $1,158.00 | 3 | SHELLY COMPANY | ODOT |
| 17 SEP 2026 | 260403 | CUY | 23.62 | $650.00 | $650.00 | 4 | KARVO COMPANIES INC | ODOT |
| 17 SEP 2026 | 260414 | WAR | 2.58 | $2,000.00 | $4,335.75 | 2 | AAD CONTRACTING INC | ODOT |
| 17 SEP 2026 | 264023 | BEL | 0.64 | $1,225.00 | $1,312.50 | 2 | J & J BRIDGE COMPANY INC | ODOT |
| 27 AUG 2026 | 264020 | CAR | 0.11 | $15,000 | $21,576 | 2 | BOG CONSTRUCTION INC | ODOT |
| 13 AUG 2026 | 260362 | HAS | 0.26 | $5,000.00 | $3,522.50 | 6 | DENNISON BRIDGE INC | ODOT |
| 30 JUL 2026 | 260327 | CUY | 33.52 | $850.00 | $850.00 | 3 | RUHLIN COMPANY | ODOT |
| 30 JUL 2026 | 260347 | FAY | 4.39 | $2,500.00 | $2,500.00 | 2 | JOHN R JURGENSEN COMPANY | ODOT |
| 16 JUL 2026 | 264017 | CRA | 0.05 | $25,000 | $16,678 | 4 | GREAT LAKES DEMOLITION COMPANY | ODOT |
Filter this item by your own quantity, county and period, or check your price against it, in the ODOT explorer.
How these prices were read
ODOT Official Bid Tabulation PDFs from its public DigitalPaper bid tab cabinet, January 2020 to November 2026 (the source links open after DigitalPaper starts a guest session). ODOT prints unit prices to two decimals but computes line amounts from the full price, so a few bids miss their total and are left out. Descriptions are cut at about 50 characters, as ODOT prints them.
- Statistics leave out bids over three times the low bid, zero or negative prices and token prices under 5% of the median.
- Item codes and units are ODOT's own: this item is compared with ODOT contracts only.
- Prices are bid prices, not paid prices, and are not adjusted for inflation. Use them as a reference range, never as a quote.
Your own bid history, read the same way
Mirage deploys AI agents for heavy civil estimating teams: quantities from the plan set, specs and addenda read, and bid tabs compared, inside your systems and your rules.