Work zone lane line, class i, 4" unit price, Ohio

Low bidders on ODOT contracts carried a median of $900.00 per MI for item 614E20000, work zone lane line, class i, 4", over the 24 months to 12 NOV 2026, across 15 low bids. Half of all 53 bids fell between $620.00 and $1,650.00.

Owner
Ohio DOT
Item
614E20000
Unit
MI
Latest letting
29 OCT 2026
$900.00Low bidder's median, per MI
$790.00Median of all bids, per MI
14Contracts in the window

By year of letting

Work zone lane line, class i, 4", ODOT: unit prices by year
YearContractsLow bidsLow-bid medianAll bidsMedian, all bids
202077$1,930.0031$2,255.10
20211111$698.0049$600.00
20221111$675.0036$682.50
20231112$800.0040$750.00
202444$1,029.0016$900.00
202566$717.5022$625.00
202678$1,200.0028$848.00
Work zone lane line, class i, 4", ODOT: unit prices by year

Bid prices as published, not adjusted for inflation.

By quantity

Work zone lane line, class i, 4", ODOT: low bidder's median by quantity band
Quantity (MI)Low bidsLow-bid median
0.03 to 0.093$1,500.00
0.12 to 0.394$2,210.00
0.48 to 0.604$842.50
0.69 to 164$752.50
Work zone lane line, class i, 4", ODOT: low bidder's median by quantity band

The low bids split into four bands of equal count by the quantity on the contract. Larger quantities usually carry lower unit prices.

Latest contracts with this item

Latest ODOT contracts carrying Work zone lane line, class i, 4"
LetContractCountyQuantityLow bidder's priceMedianBidsLow bidderSource
29 OCT 2026260399CUY0.48$900.00$838.004TRI-MOR CORPODOT
13 AUG 2026260364KNO0.09$650.00$650.004COMPLETE GENERAL CONSTRUCTION COMPANYODOT
13 AUG 2026260368PIK1.45$620.00$700.009ALLARD EXCAVATION LLCODOT
07 MAY 2026260232CUY0.56$2,500.00$2,500.003PERK COMPANY INCODOT
09 APR 2026260168ATB0.14$2,000.00$2,000.001UNION INDUSTRIAL CONTRACTORS INCODOT
29 JAN 2026260043BUT0.04$1,500.00$1,500.003FILLMORE CONSTRUCTIONODOT
29 JAN 2026260064POR1.15$885.00$885.002KARVO COMPANIES INCODOT
29 JAN 2026260064POR0.12$2,900.00$2,900.002KARVO COMPANIES INCODOT
18 DEC 2025250557HAM0.30$340.00$307.504EAGLE BRIDGE COODOT
18 DEC 2025250601WOO0.60$650.00$650.003GERKEN PAVING INCODOT
13 NOV 2025250505WAR0.39$2,420.00$925.003FILLMORE CONSTRUCTIONODOT
09 OCT 2025250472WOO16$550.00$540.004SHELLY COMPANYODOT
22 MAY 2025250263UNI0.48$785.00$680.006SHELLY COMPANYODOT
20 MAR 2025250078CUY0.03$4,100.00$4,100.002GREAT LAKES CONSTRUCTION COODOT
14 NOV 2024240529LAW0.69$1,895.00$1,895.003SHELLY COMPANYODOT
Latest ODOT contracts carrying Work zone lane line, class i, 4"

Filter this item by your own quantity, county and period, or check your price against it, in the ODOT explorer.

How these prices were read

ODOT Official Bid Tabulation PDFs from its public DigitalPaper bid tab cabinet, January 2020 to November 2026 (the source links open after DigitalPaper starts a guest session). ODOT prints unit prices to two decimals but computes line amounts from the full price, so a few bids miss their total and are left out. Descriptions are cut at about 50 characters, as ODOT prints them.

  • Statistics leave out bids over three times the low bid, zero or negative prices and token prices under 5% of the median.
  • Item codes and units are ODOT's own: this item is compared with ODOT contracts only.
  • Prices are bid prices, not paid prices, and are not adjusted for inflation. Use them as a reference range, never as a quote.

Your own bid history, read the same way

Mirage deploys AI agents for heavy civil estimating teams: quantities from the plan set, specs and addenda read, and bid tabs compared, inside your systems and your rules.

We use your email to reply to you and, now and then, to tell you about Mirage. You can opt out at any time. Privacy policy