Work zone transverse/diagonal line, class i unit price, Ohio
Low bidders on ODOT contracts carried a median of $3.00 per FT for item 614E25000, work zone transverse/diagonal line, class i, over the 24 months to 12 NOV 2026, across 20 low bids. Half of all 70 bids fell between $2.06 and $4.83.
- Owner
- Ohio DOT
- Item
- 614E25000
- Unit
- FT
- Latest letting
- 29 OCT 2026
By year of letting
| Year | Contracts | Low bids | Low-bid median | All bids | Median, all bids |
|---|---|---|---|---|---|
| 2020 | 4 | 4 | $2.25 | 18 | $2.00 |
| 2021 | 7 | 6 | $2.33 | 42 | $2.45 |
| 2022 | 3 | 3 | $4.00 | 13 | $4.00 |
| 2023 | 8 | 8 | $3.30 | 25 | $3.40 |
| 2025 | 6 | 6 | $3.55 | 24 | $3.50 |
| 2026 | 13 | 14 | $2.83 | 46 | $3.00 |
Bid prices as published, not adjusted for inflation.
By county
| County | Low bids | Low-bid median | All bids | Median, all bids |
|---|---|---|---|---|
| HAM | 4 | $3.05 | 13 | $3.50 |
| CUY | 3 | $3.25 | 12 | $3.25 |
Countys with at least three low bids, over the last 24 months.
By quantity
| Quantity (FT) | Low bids | Low-bid median |
|---|---|---|
| 53 to 128 | 5 | $3.85 |
| 143 to 268 | 5 | $1.85 |
| 337 to 1,176 | 5 | $3.00 |
| 1,212 to 4,718 | 5 | $2.25 |
The low bids split into four bands of equal count by the quantity on the contract. Larger quantities usually carry lower unit prices.
Latest contracts with this item
| Let | Contract | County | Quantity | Low bidder's price | Median | Bids | Low bidder | Source |
|---|---|---|---|---|---|---|---|---|
| 29 OCT 2026 | 260399 | CUY | 337 | $4.00 | $3.00 | 4 | TRI-MOR CORP | ODOT |
| 01 OCT 2026 | 260439 | WAR | 169 | $1.85 | $1.85 | 3 | FILLMORE CONSTRUCTION | ODOT |
| 13 AUG 2026 | 260368 | PIK | 201 | $1.20 | $1.25 | 9 | ALLARD EXCAVATION LLC | ODOT |
| 30 JUL 2026 | 260354 | MAH | 4,718 | $2.00 | $2.00 | 4 | MARUCCI & GAFFNEY EXCAVATING CO | ODOT |
| 11 JUN 2026 | 260287 | FUL | 128 | $8.55 | $8.55 | 3 | MILLER BROS CONST INC | ODOT |
| 07 MAY 2026 | 260167 | ERI | 3,618 | $3.00 | $3.00 | 3 | GREAT LAKES DEMOLITION COMPANY | ODOT |
| 07 MAY 2026 | 260227 | AUG | 100 | $3.00 | $7.00 | 3 | HELMS AND SONS EXCAVATING | ODOT |
| 07 MAY 2026 | 260232 | CUY | 684 | $3.00 | $3.00 | 3 | PERK COMPANY INC | ODOT |
| 07 MAY 2026 | 260237 | FRA | 1,212 | $1.30 | $2.40 | 2 | SHELLY & SANDS INC | ODOT |
| 07 MAY 2026 | 260239 | HAR | 143 | $8.00 | $4.30 | 3 | EAGLE BRIDGE CO | ODOT |
| 23 APR 2026 | 260221 | FRA | 268 | $12.00 | $6.67 | 2 | COMPLETE GENERAL CONSTRUCTION COMPANY | ODOT |
| 29 JAN 2026 | 260043 | BUT | 174 | $1.00 | $1.00 | 3 | FILLMORE CONSTRUCTION | ODOT |
| 29 JAN 2026 | 260064 | POR | 1,154 | $2.65 | $2.65 | 2 | KARVO COMPANIES INC | ODOT |
| 29 JAN 2026 | 260064 | POR | 53 | $2.65 | $2.65 | 2 | KARVO COMPANIES INC | ODOT |
| 18 DEC 2025 | 250557 | HAM | 1,176 | $1.50 | $2.38 | 4 | EAGLE BRIDGE CO | ODOT |
Filter this item by your own quantity, county and period, or check your price against it, in the ODOT explorer.
How these prices were read
ODOT Official Bid Tabulation PDFs from its public DigitalPaper bid tab cabinet, January 2020 to November 2026 (the source links open after DigitalPaper starts a guest session). ODOT prints unit prices to two decimals but computes line amounts from the full price, so a few bids miss their total and are left out. Descriptions are cut at about 50 characters, as ODOT prints them.
- Statistics leave out bids over three times the low bid, zero or negative prices and token prices under 5% of the median.
- Item codes and units are ODOT's own: this item is compared with ODOT contracts only.
- Prices are bid prices, not paid prices, and are not adjusted for inflation. Use them as a reference range, never as a quote.