Extra for hand dug guardrail post holes unit price, Oregon

Low bidders on ODOT contracts carried a median of $200.00 per EACH for item 0810-0145000E, extra for hand dug guardrail post holes, over the 24 months to 13 AUG 2026, across 15 low bids. Half of all 78 bids fell between $185.00 and $350.00.

Owner
Oregon DOT
Item
0810-0145000E
Unit
EACH
Latest letting
23 JUL 2026
$200.00Low bidder's median, per EACH
$250.00Median of all bids, per EACH
15Contracts in the window

By year of letting

Extra for hand dug guardrail post holes, ODOT: unit prices by year
YearContractsLow bidsLow-bid medianAll bidsMedian, all bids
20211414$175.0054$200.00
20221111$200.0030$200.00
202344$202.5015$215.00
20241111$250.0041$250.00
202599$220.0043$315.00
202644$212.5025$250.00
Extra for hand dug guardrail post holes, ODOT: unit prices by year

Bid prices as published, not adjusted for inflation.

By region

Extra for hand dug guardrail post holes, ODOT: unit prices by region, last 24 months
RegionLow bidsLow-bid medianAll bidsMedian, all bids
Region 25$220.0024$235.00
Region 54$250.0023$315.00
Region 34$225.0020$250.00
Extra for hand dug guardrail post holes, ODOT: unit prices by region, last 24 months

Regions with at least three low bids, over the last 24 months.

By quantity

Extra for hand dug guardrail post holes, ODOT: low bidder's median by quantity band
Quantity (EACH)Low bidsLow-bid median
2 to 33$400.00
4 to 104$235.00
12 to 504$200.00
56 to 1004$136.00
Extra for hand dug guardrail post holes, ODOT: low bidder's median by quantity band

The low bids split into four bands of equal count by the quantity on the contract. Larger quantities usually carry lower unit prices.

Latest contracts with this item

Latest ODOT contracts carrying Extra for hand dug guardrail post holes
LetContractRegionQuantityLow bidder's priceMedianBidsSource
23 JUL 202615677Region 250$280.00$270.005ODOT
02 APR 202615654Region 3100$175.00$187.504ODOT
02 APR 202615650Region 412$165.00$165.006ODOT
05 FEB 202615586Region 310$250.00$250.0010ODOT
11 DEC 202515630Region 24$400.00$385.005ODOT
11 DEC 202515632Region 53$400.00$377.007ODOT
30 OCT 202515616Region 52$450.00$450.006ODOT
18 SEP 202515613Region 2100$100.00$100.005ODOT
22 MAY 202515601Region 32$350.00$350.003ODOT
27 MAR 202515592Region 256$172.00$238.504ODOT
20 FEB 202515581Region 332$200.00$200.003ODOT
30 JAN 202515580Region 24$220.00$200.005ODOT
09 JAN 202515571Region 120$200.00$250.005ODOT
07 NOV 202415564Region 54$100.00$250.007ODOT
24 OCT 202415566Region 560$96.00$100.003ODOT
Latest ODOT contracts carrying Extra for hand dug guardrail post holes

Filter this item by your own quantity, region and period, or check your price against it, in the ODOT explorer.

How these prices were read

ODOT Bid Data Program yearly workbooks. ODOT publishes rank and unit price only: no bidder names and no bid totals, so these bids cannot be checked against a total and Oregon is left out of the competitor views.

  • Statistics leave out bids over three times the low bid, zero or negative prices and token prices under 5% of the median.
  • Item codes and units are ODOT's own: this item is compared with ODOT contracts only.
  • Prices are bid prices, not paid prices, and are not adjusted for inflation. Use them as a reference range, never as a quote.

Your own bid history, read the same way

Mirage deploys AI agents for heavy civil estimating teams: quantities from the plan set, specs and addenda read, and bid tabs compared, inside your systems and your rules.

We use your email to reply to you and, now and then, to tell you about Mirage. You can opt out at any time. Privacy policy