Guardrail terminals, non-flared unit price, Oregon

Low bidders on ODOT contracts carried a median of $3,910.00 per EACH for item 0810-0129000E, guardrail terminals, non-flared, over the 24 months to 13 AUG 2026, across 31 low bids. Half of all 168 bids fell between $3,500.00 and $4,281.25.

Owner
Oregon DOT
Item
0810-0129000E
Unit
EACH
Latest letting
23 JUL 2026
$3,910.00Low bidder's median, per EACH
$3,875.00Median of all bids, per EACH
31Contracts in the window

By year of letting

Guardrail terminals, non-flared, ODOT: unit prices by year
YearContractsLow bidsLow-bid medianAll bidsMedian, all bids
20212424$3,775.0089$4,000.00
20222121$4,100.0068$4,187.50
20232121$4,100.0070$4,500.00
20243030$4,050.00124$4,140.00
20251313$3,816.0069$3,850.00
202699$3,910.0057$3,800.00
Guardrail terminals, non-flared, ODOT: unit prices by year

Bid prices as published, not adjusted for inflation.

By region

Guardrail terminals, non-flared, ODOT: unit prices by region, last 24 months
RegionLow bidsLow-bid medianAll bidsMedian, all bids
Region 510$3,755.0064$3,687.50
Region 29$4,000.0046$3,900.00
Region 37$3,875.0033$3,875.00
Region 13$4,000.0016$4,000.00
Guardrail terminals, non-flared, ODOT: unit prices by region, last 24 months

Regions with at least three low bids, over the last 24 months.

By quantity

Guardrail terminals, non-flared, ODOT: low bidder's median by quantity band
Quantity (EACH)Low bidsLow-bid median
1 to 27$3,600.00
2 to 38$4,150.00
3 to 98$4,050.00
10 to 668$3,833.00
Guardrail terminals, non-flared, ODOT: low bidder's median by quantity band

The low bids split into four bands of equal count by the quantity on the contract. Larger quantities usually carry lower unit prices.

Latest contracts with this item

Latest ODOT contracts carrying Guardrail terminals, non-flared
LetContractRegionQuantityLow bidder's priceMedianBidsSource
23 JUL 202615677Region 24$4,100.00$4,000.005ODOT
11 JUN 202615670Region 510$4,000.00$3,500.006ODOT
04 JUN 202615669Region 53$3,910.00$3,614.276ODOT
23 APR 202615660Region 22$4,200.00$4,150.008ODOT
09 APR 202615657Region 52$4,000.00$3,965.006ODOT
02 APR 202615654Region 366$3,850.00$3,437.504ODOT
02 APR 202615650Region 49$3,895.00$4,150.006ODOT
05 FEB 202615586Region 32$3,400.00$3,400.0010ODOT
08 JAN 202615638Region 12$3,200.00$3,200.006ODOT
11 DEC 202515628Region 23$3,200.00$3,200.009ODOT
11 DEC 202515630Region 22$3,600.00$3,600.005ODOT
11 DEC 202515632Region 52$3,600.00$3,540.007ODOT
30 OCT 202515621Region 221$3,000.00$3,000.005ODOT
30 OCT 202515616Region 517$3,500.00$3,550.006ODOT
11 SEP 202515611Region 11$4,000.00$4,650.005ODOT
Latest ODOT contracts carrying Guardrail terminals, non-flared

Filter this item by your own quantity, region and period, or check your price against it, in the ODOT explorer.

How these prices were read

ODOT Bid Data Program yearly workbooks. ODOT publishes rank and unit price only: no bidder names and no bid totals, so these bids cannot be checked against a total and Oregon is left out of the competitor views.

  • Statistics leave out bids over three times the low bid, zero or negative prices and token prices under 5% of the median.
  • Item codes and units are ODOT's own: this item is compared with ODOT contracts only.
  • Prices are bid prices, not paid prices, and are not adjusted for inflation. Use them as a reference range, never as a quote.

Your own bid history, read the same way

Mirage deploys AI agents for heavy civil estimating teams: quantities from the plan set, specs and addenda read, and bid tabs compared, inside your systems and your rules.

We use your email to reply to you and, now and then, to tell you about Mirage. You can opt out at any time. Privacy policy