18" pipe culvert (side drain) unit price, Tennessee
Low bidders on TDOT contracts carried a median of $98.00 per LF for item 607-39.02, 18" pipe culvert (side drain), over the 24 months to 02 OCT 2026, across 39 low bids. Half of all 143 bids fell between $82.00 and $140.00.
- Owner
- Tennessee DOT
- Item
- 607-39.02
- Unit
- LF
- Latest letting
- 02 OCT 2026
By year of letting
| Year | Contracts | Low bids | Low-bid median | All bids | Median, all bids |
|---|---|---|---|---|---|
| 2018 | 11 | 11 | $50.00 | 28 | $50.00 |
| 2020 | 6 | 6 | $59.62 | 23 | $54.00 |
| 2023 | 1 | 1 | $112.00 | 2 | $525.21 |
| 2024 | 21 | 21 | $85.29 | 76 | $94.00 |
| 2025 | 15 | 15 | $85.00 | 55 | $100.00 |
| 2026 | 17 | 17 | $110.00 | 63 | $104.84 |
Bid prices as published, not adjusted for inflation.
By quantity
| Quantity (LF) | Low bids | Low-bid median |
|---|---|---|
| 24 to 92 | 9 | $100.00 |
| 94 to 136 | 10 | $93.04 |
| 153 to 301 | 10 | $105.55 |
| 394 to 3,760 | 10 | $77.43 |
The low bids split into four bands of equal count by the quantity on the contract. Larger quantities usually carry lower unit prices.
Latest contracts with this item
| Let | Contract | County | Quantity | Low bidder's price | Median | Bids | Low bidder | Source |
|---|---|---|---|---|---|---|---|---|
| 02 OCT 2026 | CN261074 | Claiborne County | 163 | $140.00 | $140.00 | 5 | Southern Constructors, Inc. | TDOT |
| 02 OCT 2026 | CN261079 | Hawkins County | 114 | $300.00 | $171.49 | 3 | Southern Constructors, Inc. | TDOT |
| 14 AUG 2026 | CN261063 | Campbell County | 33 | $125.00 | $100.00 | 5 | Rogers Group, Inc. | TDOT |
| 14 AUG 2026 | CN262059 | Coffee County | 24 | $80.00 | $80.00 | 5 | Jones Bros. Contractors, LLC | TDOT |
| 14 AUG 2026 | CN262058 | Cumberland County | 3,760 | $101.79 | $97.09 | 6 | Charles Blalock & Sons, Inc. | TDOT |
| 14 AUG 2026 | CN264048 | Dyer County | 301 | $145.50 | $145.50 | 1 | Ford Construction Company | TDOT |
| 26 JUN 2026 | CN264041 | Chester County | 74 | $50.00 | $87.50 | 2 | Delta Contracting Company, LLC | TDOT |
| 26 JUN 2026 | CN261057 | Hawkins County | 495 | $63.00 | $143.23 | 4 | Whaley Construction, LLC | TDOT |
| 26 JUN 2026 | CN261901 | Johnson County | 103 | $230.00 | $210.29 | 2 | Southern Constructors, Inc. | TDOT |
| 26 JUN 2026 | CN264037 | Lake County | 116 | $110.00 | $110.00 | 1 | Ford Construction Company | TDOT |
| 26 JUN 2026 | CN261044 | Monroe County | 1,010 | $76.45 | $88.67 | 6 | Charles Blalock & Sons, Inc. | TDOT |
| 26 JUN 2026 | CN263057 | Rutherford County | 548 | $106.00 | $109.50 | 4 | Civil Constructors, LLC | TDOT |
| 08 MAY 2026 | CN264036 | Henry County | 242 | $35.00 | $55.00 | 4 | Delta Contracting Company, LLC | TDOT |
| 20 MAR 2026 | CN261015 | Anderson County | 80 | $98.00 | $101.10 | 5 | Whaley Construction, LLC | TDOT |
| 20 MAR 2026 | CN261026 | Sullivan County | 250 | $150.00 | $159.50 | 4 | Southern Constructors, Inc. | TDOT |
Filter this item by your own quantity, county and period, or check your price against it, in the TDOT explorer.
How these prices were read
TDOT Summary of Bids PDFs: every letting posted for February 2024 to October 2026, and nine lettings of 2018 to 2023 recovered from archived copies of the tn.gov files. Cost-plus-time bids, and bids that did not match their published total, are left out.
- Statistics leave out bids over three times the low bid, zero or negative prices and token prices under 5% of the median.
- Item codes and units are TDOT's own: this item is compared with TDOT contracts only.
- Prices are bid prices, not paid prices, and are not adjusted for inflation. Use them as a reference range, never as a quote.