18IN endwall (side drain) unit price, Tennessee
Low bidders on TDOT contracts carried a median of $4,500.00 per EACH for item 611-07.31, 18in endwall (side drain), over the 24 months to 02 OCT 2026, across 34 low bids. Half of all 123 bids fell between $4,200.00 and $6,000.00.
- Owner
- Tennessee DOT
- Item
- 611-07.31
- Unit
- EACH
- Latest letting
- 02 OCT 2026
By year of letting
| Year | Contracts | Low bids | Low-bid median | All bids | Median, all bids |
|---|---|---|---|---|---|
| 2018 | 3 | 3 | $3,000.00 | 14 | $2,500.00 |
| 2020 | 2 | 2 | $2,625.00 | 7 | $3,739.90 |
| 2024 | 18 | 18 | $4,825.00 | 60 | $4,825.00 |
| 2025 | 14 | 14 | $4,152.67 | 58 | $5,000.00 |
| 2026 | 14 | 14 | $4,448.28 | 46 | $4,900.00 |
Bid prices as published, not adjusted for inflation.
By quantity
| Quantity (EACH) | Low bids | Low-bid median |
|---|---|---|
| 1 to 2 | 8 | $4,900.00 |
| 2 to 6 | 9 | $6,104.75 |
| 6 to 8 | 8 | $4,052.06 |
| 10 to 232 | 9 | $4,060.00 |
The low bids split into four bands of equal count by the quantity on the contract. Larger quantities usually carry lower unit prices.
Latest contracts with this item
| Let | Contract | County | Quantity | Low bidder's price | Median | Bids | Low bidder | Source |
|---|---|---|---|---|---|---|---|---|
| 02 OCT 2026 | CN261079 | Hawkins County | 5 | $4,000.00 | $5,200.00 | 3 | Southern Constructors, Inc. | TDOT |
| 14 AUG 2026 | CN262059 | Coffee County | 2 | $5,000.00 | $7,100.00 | 5 | Jones Bros. Contractors, LLC | TDOT |
| 14 AUG 2026 | CN262058 | Cumberland County | 232 | $3,626.02 | $3,934.44 | 6 | Charles Blalock & Sons, Inc. | TDOT |
| 14 AUG 2026 | CN264048 | Dyer County | 2 | $5,000.00 | $5,000.00 | 1 | Ford Construction Company | TDOT |
| 26 JUN 2026 | CN264041 | Chester County | 8 | $4,396.56 | $4,548.28 | 2 | Delta Contracting Company, LLC | TDOT |
| 26 JUN 2026 | CN264903 | Dyer County | 3 | $4,300.00 | $4,100.00 | 2 | Ford Construction Company | TDOT |
| 26 JUN 2026 | CN261057 | Hawkins County | 10 | $8,147.00 | $5,793.72 | 4 | Whaley Construction, LLC | TDOT |
| 26 JUN 2026 | CN264037 | Lake County | 8 | $4,500.00 | $4,500.00 | 1 | Ford Construction Company | TDOT |
| 26 JUN 2026 | CN263057 | Rutherford County | 32 | $4,060.00 | $4,280.00 | 4 | Civil Constructors, LLC | TDOT |
| 08 MAY 2026 | CN264036 | Henry County | 16 | $5,000.00 | $4,525.00 | 4 | Delta Contracting Company, LLC | TDOT |
| 20 MAR 2026 | CN261015 | Anderson County | 3 | $7,120.00 | $7,120.00 | 5 | Whaley Construction, LLC | TDOT |
| 20 MAR 2026 | CN261026 | Sullivan County | 6 | $4,500.00 | $6,110.08 | 4 | Southern Constructors, Inc. | TDOT |
| 06 FEB 2026 | CN262019 | Bradley County | 1 | $4,000.00 | $5,624.27 | 4 | Wright Brothers Civil Construction, LLC | TDOT |
| 06 FEB 2026 | CN261011 | Sevier County | 7 | $3,332.81 | $3,332.81 | 1 | Charles Blalock & Sons, Inc. | TDOT |
| 05 DEC 2025 | CNZ307 | Gibson County | 2 | $4,300.00 | $4,300.00 | 5 | Dement Construction Group, LLC | TDOT |
Filter this item by your own quantity, county and period, or check your price against it, in the TDOT explorer.
How these prices were read
TDOT Summary of Bids PDFs: every letting posted for February 2024 to October 2026, and nine lettings of 2018 to 2023 recovered from archived copies of the tn.gov files. Cost-plus-time bids, and bids that did not match their published total, are left out.
- Statistics leave out bids over three times the low bid, zero or negative prices and token prices under 5% of the median.
- Item codes and units are TDOT's own: this item is compared with TDOT contracts only.
- Prices are bid prices, not paid prices, and are not adjusted for inflation. Use them as a reference range, never as a quote.
Your own bid history, read the same way