Type 1 thin epoxy overlay (epoxy-urethane) unit price, Tennessee
Low bidders on TDOT contracts carried a median of $42.50 per SY for item 617-04.01, type 1 thin epoxy overlay (epoxy-urethane), over the 24 months to 02 OCT 2026, across 91 low bids. Half of all 220 bids fell between $36.70 and $60.00.
- Owner
- Tennessee DOT
- Item
- 617-04.01
- Unit
- SY
- Latest letting
- 02 OCT 2026
By year of letting
| Year | Contracts | Low bids | Low-bid median | All bids | Median, all bids |
|---|---|---|---|---|---|
| 2018 | 3 | 3 | $31.00 | 6 | $31.66 |
| 2020 | 11 | 11 | $35.00 | 27 | $38.00 |
| 2023 | 1 | 1 | $56.19 | 3 | $56.19 |
| 2024 | 27 | 27 | $41.80 | 75 | $42.00 |
| 2025 | 47 | 47 | $43.95 | 117 | $45.00 |
| 2026 | 37 | 37 | $39.85 | 88 | $40.73 |
Bid prices as published, not adjusted for inflation.
By county
| County | Low bids | Low-bid median | All bids | Median, all bids |
|---|---|---|---|---|
| Davidson County | 7 | $37.80 | 20 | $36.00 |
| Shelby County | 6 | $38.25 | 16 | $37.45 |
| Hardin County | 3 | $40.00 | 14 | $36.77 |
| Maury County | 3 | $42.00 | 9 | $37.75 |
| Haywood County | 4 | $42.50 | 8 | $43.95 |
| Fayette County | 3 | $34.25 | 7 | $34.25 |
| Sullivan County | 3 | $68.00 | 7 | $77.74 |
Countys with at least three low bids, over the last 24 months.
By quantity
| Quantity (SY) | Low bids | Low-bid median |
|---|---|---|
| 13 to 1,050 | 22 | $81.46 |
| 1,132 to 2,624 | 23 | $48.00 |
| 2,659 to 5,722 | 23 | $39.25 |
| 6,559 to 39,249 | 23 | $35.00 |
The low bids split into four bands of equal count by the quantity on the contract. Larger quantities usually carry lower unit prices.
Latest contracts with this item
| Let | Contract | County | Quantity | Low bidder's price | Median | Bids | Low bidder | Source |
|---|---|---|---|---|---|---|---|---|
| 02 OCT 2026 | CN264061 | Henry And Stewart Counties | 3,917 | $29.29 | $33.75 | 3 | Delta Contracting Company, LLC | TDOT |
| 14 AUG 2026 | CN262060 | Meigs County | 73 | $155.63 | $155.63 | 5 | Mid-State Construction Company, Inc. | TDOT |
| 14 AUG 2026 | CN263061 | Humphreys County | 9,000 | $30.40 | $30.40 | 1 | Dement Construction Group, LLC | TDOT |
| 26 JUN 2026 | CN264043 | Dyer County | 4,294 | $43.00 | $43.00 | 1 | Ford Construction Company | TDOT |
| 26 JUN 2026 | CN262048 | Grundy County | 100 | $215.00 | $215.00 | 1 | Rogers Group, Inc. | TDOT |
| 26 JUN 2026 | CN264044 | Hardin County | 15,692 | $35.23 | $35.91 | 8 | Louis-Company, LLC | TDOT |
| 26 JUN 2026 | CN264045 | Haywood County | 360 | $80.00 | $78.00 | 2 | Delta Contracting Company, LLC | TDOT |
| 26 JUN 2026 | CN264047 | Henderson County | 2,466 | $37.21 | $41.11 | 2 | Delta Contracting Company, LLC | TDOT |
| 26 JUN 2026 | CN264050 | Henry County | 822 | $58.45 | $63.30 | 2 | Delta Contracting Company, LLC | TDOT |
| 26 JUN 2026 | CN262050 | Mcminn County | 2,193 | $48.00 | $48.00 | 1 | Rogers Group, Inc. | TDOT |
| 26 JUN 2026 | CN261902 | Roane County | 3,360 | $38.77 | $39.39 | 4 | Mid-State Construction Company, Inc. | TDOT |
| 26 JUN 2026 | CN261049 | Sullivan County | 898 | $68.00 | $77.25 | 2 | Summers-Taylor, Inc. | TDOT |
| 08 MAY 2026 | CN262040 | Cumberland County | 1,865 | $39.85 | $40.65 | 2 | Rogers Group, Inc. | TDOT |
| 08 MAY 2026 | CN261045 | Grainger County | 2,494 | $42.50 | $42.00 | 3 | APAC-Atlantic, Inc. | TDOT |
| 08 MAY 2026 | CN261039 | Knox County | 18,841 | $35.00 | $43.53 | 5 | The Truesdell Corporation | TDOT |
Filter this item by your own quantity, county and period, or check your price against it, in the TDOT explorer.
How these prices were read
TDOT Summary of Bids PDFs: every letting posted for February 2024 to October 2026, and nine lettings of 2018 to 2023 recovered from archived copies of the tn.gov files. Cost-plus-time bids, and bids that did not match their published total, are left out.
- Statistics leave out bids over three times the low bid, zero or negative prices and token prices under 5% of the median.
- Item codes and units are TDOT's own: this item is compared with TDOT contracts only.
- Prices are bid prices, not paid prices, and are not adjusted for inflation. Use them as a reference range, never as a quote.
Your own bid history, read the same way
Mirage deploys AI agents for heavy civil estimating teams: quantities from the plan set, specs and addenda read, and bid tabs compared, inside your systems and your rules.