Cold planing bituminous pavement unit price, Tennessee
Low bidders on TDOT contracts carried a median of $21.30 per SY for item 415-01.02, cold planing bituminous pavement, over the 24 months to 02 OCT 2026, across 85 low bids. Half of all 221 bids fell between $8.00 and $42.54.
- Owner
- Tennessee DOT
- Item
- 415-01.02
- Unit
- SY
- Latest letting
- 02 OCT 2026
By year of letting
| Year | Contracts | Low bids | Low-bid median | All bids | Median, all bids |
|---|---|---|---|---|---|
| 2018 | 44 | 44 | $4.62 | 105 | $8.29 |
| 2020 | 27 | 28 | $5.06 | 77 | $6.47 |
| 2023 | 4 | 4 | $10.72 | 13 | $13.62 |
| 2024 | 43 | 42 | $24.85 | 116 | $21.50 |
| 2025 | 39 | 39 | $29.00 | 85 | $29.41 |
| 2026 | 34 | 33 | $15.00 | 102 | $15.50 |
Bid prices as published, not adjusted for inflation.
By county
| County | Low bids | Low-bid median | All bids | Median, all bids |
|---|---|---|---|---|
| Shelby County | 4 | $15.54 | 15 | $16.00 |
| Hardin County | 3 | $4.00 | 15 | $28.00 |
| Sullivan County | 5 | $12.00 | 12 | $22.61 |
| Grainger County | 5 | $13.85 | 11 | $16.50 |
| Knox County | 3 | $13.70 | 10 | $16.10 |
| Hawkins County | 3 | $141.33 | 7 | $125.00 |
| Washington County | 5 | $35.00 | 7 | $75.00 |
| Greene County | 3 | $47.98 | 7 | $42.54 |
| Hancock County | 3 | $45.00 | 6 | $58.50 |
| Morgan County | 3 | $35.00 | 6 | $35.90 |
| Claiborne County | 3 | $47.25 | 5 | $49.00 |
| Carter County | 3 | $65.00 | 4 | $74.50 |
Countys with at least three low bids, over the last 24 months.
By quantity
| Quantity (SY) | Low bids | Low-bid median |
|---|---|---|
| 20 to 240 | 21 | $79.00 |
| 247 to 977 | 21 | $32.00 |
| 1,045 to 3,735 | 21 | $12.00 |
| 3,754 to 70,336 | 22 | $6.32 |
The low bids split into four bands of equal count by the quantity on the contract. Larger quantities usually carry lower unit prices.
Latest contracts with this item
| Let | Contract | County | Quantity | Low bidder's price | Median | Bids | Low bidder | Source |
|---|---|---|---|---|---|---|---|---|
| 02 OCT 2026 | CN264057 | Hardin County | 3,735 | $4.00 | $4.50 | 5 | Delta Contracting Company, LLC | TDOT |
| 02 OCT 2026 | CN263066 | Smith County | 10,186 | $5.00 | $6.42 | 4 | Rock Supremacy, LLC | TDOT |
| 02 OCT 2026 | CN261064 | Sullivan County | 6,000 | $12.00 | $12.00 | 1 | Summers-Taylor, Inc. | TDOT |
| 14 AUG 2026 | CN262059 | Coffee County | 5,133 | $7.45 | $6.50 | 5 | Jones Bros. Contractors, LLC | TDOT |
| 14 AUG 2026 | CN262056 | Grundy County | 13,385 | $6.00 | $6.00 | 5 | Mack Construction, LLC | TDOT |
| 14 AUG 2026 | CN262060 | Meigs County | 1,350 | $16.14 | $16.00 | 5 | Mid-State Construction Company, Inc. | TDOT |
| 14 AUG 2026 | CN264054 | Shelby County | 1,596 | $12.00 | $12.50 | 2 | Dement Construction Group, LLC | TDOT |
| 26 JUN 2026 | CN261054 | Greene County | 1,685 | $22.00 | $22.00 | 1 | Summers-Taylor, Inc. | TDOT |
| 26 JUN 2026 | CN264044 | Hardin County | 600 | $31.59 | $31.30 | 8 | Louis-Company, LLC | TDOT |
| 26 JUN 2026 | CN261055 | Hawkins County | 225 | $48.00 | $74.00 | 2 | Summers-Taylor, Inc. | TDOT |
| 26 JUN 2026 | CN264037 | Lake County | 175 | $91.00 | $91.00 | 1 | Ford Construction Company | TDOT |
| 26 JUN 2026 | CN261902 | Roane County | 240 | $70.20 | $82.04 | 4 | Mid-State Construction Company, Inc. | TDOT |
| 26 JUN 2026 | CN263057 | Rutherford County | 11,856 | $6.30 | $6.25 | 4 | Civil Constructors, LLC | TDOT |
| 08 MAY 2026 | CN261051 | Anderson County | 1,045 | $18.65 | $15.32 | 4 | J. Hill Excavating, LLC | TDOT |
| 08 MAY 2026 | CN261035 | Grainger County | 36 | $150.00 | $85.00 | 2 | APAC-Atlantic, Inc. | TDOT |
Filter this item by your own quantity, county and period, or check your price against it, in the TDOT explorer.
How these prices were read
TDOT Summary of Bids PDFs: every letting posted for February 2024 to October 2026, and nine lettings of 2018 to 2023 recovered from archived copies of the tn.gov files. Cost-plus-time bids, and bids that did not match their published total, are left out.
- Statistics leave out bids over three times the low bid, zero or negative prices and token prices under 5% of the median.
- Item codes and units are TDOT's own: this item is compared with TDOT contracts only.
- Prices are bid prices, not paid prices, and are not adjusted for inflation. Use them as a reference range, never as a quote.
Your own bid history, read the same way
Mirage deploys AI agents for heavy civil estimating teams: quantities from the plan set, specs and addenda read, and bid tabs compared, inside your systems and your rules.