Scoring for rumble stripe (non-continuous) (8IN width) unit price, Tennessee
Low bidders on TDOT contracts carried a median of $796.00 per LM for item 411-12.03, scoring for rumble stripe (non-continuous) (8in width), over the 24 months to 02 OCT 2026, across 114 low bids. Half of all 304 bids fell between $680.62 and $1,795.50.
- Owner
- Tennessee DOT
- Item
- 411-12.03
- Unit
- LM
- Latest letting
- 02 OCT 2026
By year of letting
| Year | Contracts | Low bids | Low-bid median | All bids | Median, all bids |
|---|---|---|---|---|---|
| 2018 | 37 | 37 | $565.00 | 75 | $600.00 |
| 2020 | 20 | 20 | $631.33 | 51 | $750.00 |
| 2023 | 2 | 2 | $6,808.50 | 3 | $9,762.50 |
| 2024 | 46 | 46 | $800.00 | 113 | $800.00 |
| 2025 | 51 | 51 | $739.50 | 132 | $950.00 |
| 2026 | 48 | 48 | $789.75 | 134 | $950.00 |
Bid prices as published, not adjusted for inflation.
By county
| County | Low bids | Low-bid median | All bids | Median, all bids |
|---|---|---|---|---|
| Maury County | 4 | $2,000.00 | 19 | $2,205.00 |
| Cumberland County | 7 | $725.00 | 15 | $1,020.00 |
| Hardin County | 3 | $1,325.00 | 14 | $6,500.00 |
| Knox County | 4 | $707.50 | 13 | $860.00 |
| Montgomery County | 4 | $675.00 | 12 | $1,505.00 |
| Rutherford County | 3 | $996.23 | 12 | $1,050.91 |
| Smith County | 3 | $1,689.00 | 9 | $1,545.00 |
| Polk County | 3 | $725.00 | 4 | $742.00 |
Countys with at least three low bids, over the last 24 months.
By quantity
| Quantity (LM) | Low bids | Low-bid median |
|---|---|---|
| 0.05 to 1 | 28 | $2,200.00 |
| 1.20 to 5.10 | 29 | $787.50 |
| 5.40 to 9.40 | 28 | $732.08 |
| 9.50 to 27.90 | 29 | $600.00 |
The low bids split into four bands of equal count by the quantity on the contract. Larger quantities usually carry lower unit prices.
Latest contracts with this item
| Let | Contract | County | Quantity | Low bidder's price | Median | Bids | Low bidder | Source |
|---|---|---|---|---|---|---|---|---|
| 02 OCT 2026 | CN261074 | Claiborne County | 0.20 | $2,200.00 | $2,200.00 | 5 | Southern Constructors, Inc. | TDOT |
| 02 OCT 2026 | CN263066 | Smith County | 1.20 | $10,000 | $6,155.08 | 4 | Rock Supremacy, LLC | TDOT |
| 14 AUG 2026 | CN261063 | Campbell County | 0.20 | $2,115.00 | $15,000 | 5 | Rogers Group, Inc. | TDOT |
| 14 AUG 2026 | CN264048 | Dyer County | 0.34 | $12,500 | $12,500 | 1 | Ford Construction Company | TDOT |
| 14 AUG 2026 | CN264054 | Shelby County | 1 | $9,600.00 | $9,900.00 | 2 | Dement Construction Group, LLC | TDOT |
| 26 JUN 2026 | CN264041 | Chester County | 0.45 | $13,500 | $16,625 | 2 | Delta Contracting Company, LLC | TDOT |
| 26 JUN 2026 | CN261054 | Greene County | 24 | $1,200.00 | $1,200.00 | 1 | Summers-Taylor, Inc. | TDOT |
| 26 JUN 2026 | CN264044 | Hardin County | 0.05 | $203,095 | $193,500 | 8 | Louis-Company, LLC | TDOT |
| 26 JUN 2026 | CN264045 | Haywood County | 11 | $530.00 | $530.00 | 2 | Delta Contracting Company, LLC | TDOT |
| 26 JUN 2026 | CN263051 | Marshall And Williamson Counties | 9.40 | $1,233.75 | $1,116.88 | 4 | Asphalt Paving Systems, Inc. | TDOT |
| 26 JUN 2026 | CN263052 | Maury County | 0.17 | $10,000 | $28,750 | 8 | Eubank Asphalt Paving & Sealing, LLC | TDOT |
| 26 JUN 2026 | CN263046 | Rutherford County | 9.60 | $580.00 | $580.00 | 3 | Hawkins Asphalt Paving, LLC | TDOT |
| 26 JUN 2026 | CN263053 | Rutherford County | 4.20 | $1,200.00 | $1,775.00 | 4 | Hawkins Asphalt Paving, LLC | TDOT |
| 08 MAY 2026 | CN261031 | Blount County | 3 | $4,880.00 | $2,000.00 | 3 | APAC-Atlantic, Inc. | TDOT |
| 08 MAY 2026 | CN262040 | Cumberland County | 5.40 | $739.15 | $719.58 | 2 | Rogers Group, Inc. | TDOT |
Filter this item by your own quantity, county and period, or check your price against it, in the TDOT explorer.
How these prices were read
TDOT Summary of Bids PDFs: every letting posted for February 2024 to October 2026, and nine lettings of 2018 to 2023 recovered from archived copies of the tn.gov files. Cost-plus-time bids, and bids that did not match their published total, are left out.
- Statistics leave out bids over three times the low bid, zero or negative prices and token prices under 5% of the median.
- Item codes and units are TDOT's own: this item is compared with TDOT contracts only.
- Prices are bid prices, not paid prices, and are not adjusted for inflation. Use them as a reference range, never as a quote.
Your own bid history, read the same way
Mirage deploys AI agents for heavy civil estimating teams: quantities from the plan set, specs and addenda read, and bid tabs compared, inside your systems and your rules.