Acs mix(PG76-22) grading d unit price, Tennessee
Low bidders on TDOT contracts carried a median of $153.25 per TON for item 411-03.10, acs mix(pg76-22) grading d, over the 24 months to 02 OCT 2026, across 64 low bids. Half of all 178 bids fell between $139.00 and $199.00.
- Owner
- Tennessee DOT
- Item
- 411-03.10
- Unit
- TON
- Latest letting
- 02 OCT 2026
By year of letting
| Year | Contracts | Low bids | Low-bid median | All bids | Median, all bids |
|---|---|---|---|---|---|
| 2018 | 8 | 8 | $108.48 | 15 | $109.00 |
| 2020 | 7 | 7 | $170.00 | 19 | $187.00 |
| 2023 | 9 | 9 | $158.78 | 20 | $164.39 |
| 2024 | 27 | 27 | $170.00 | 75 | $172.00 |
| 2025 | 34 | 34 | $146.51 | 89 | $148.50 |
| 2026 | 13 | 13 | $186.50 | 44 | $192.50 |
Bid prices as published, not adjusted for inflation.
By county
| County | Low bids | Low-bid median | All bids | Median, all bids |
|---|---|---|---|---|
| Shelby County | 8 | $150.80 | 26 | $162.00 |
| Davidson County | 7 | $128.00 | 23 | $135.00 |
| Williamson County | 4 | $120.31 | 16 | $148.50 |
| Knox County | 3 | $235.00 | 10 | $299.38 |
| Cumberland County | 3 | $134.35 | 8 | $144.50 |
| Marion County | 3 | $210.00 | 7 | $210.00 |
| Sullivan County | 3 | $180.00 | 6 | $180.00 |
Countys with at least three low bids, over the last 24 months.
By quantity
| Quantity (TON) | Low bids | Low-bid median |
|---|---|---|
| 67 to 788 | 16 | $211.50 |
| 868 to 3,269 | 16 | $186.78 |
| 3,494 to 12,875 | 16 | $140.00 |
| 14,932 to 44,335 | 16 | $125.25 |
The low bids split into four bands of equal count by the quantity on the contract. Larger quantities usually carry lower unit prices.
Latest contracts with this item
| Let | Contract | County | Quantity | Low bidder's price | Median | Bids | Low bidder | Source |
|---|---|---|---|---|---|---|---|---|
| 02 OCT 2026 | CN261073 | Knox County | 164 | $360.00 | $378.00 | 4 | Bluegrass Contracting Corporation | TDOT |
| 14 AUG 2026 | CN262056 | Grundy County | 1,300 | $210.00 | $210.00 | 5 | Mack Construction, LLC | TDOT |
| 26 JUN 2026 | CN263059 | Dickson And Hickman Counties | 1,451 | $195.00 | $195.00 | 3 | Jones Bros. Contractors, LLC | TDOT |
| 26 JUN 2026 | CN263054 | Williamson County | 20,843 | $120.61 | $139.50 | 4 | Volunteer Paving, LLC | TDOT |
| 08 MAY 2026 | CN264039 | Henderson County | 1,582 | $142.00 | $168.00 | 3 | Jones Bros. Contractors, LLC | TDOT |
| 20 MAR 2026 | CN264025 | Fayette And Shelby Counties | 1,990 | $186.50 | $208.73 | 3 | APAC-Tennessee, Inc. | TDOT |
| 20 MAR 2026 | CN264027 | Shelby County | 14,932 | $156.00 | $152.87 | 3 | APAC-Tennessee, Inc. | TDOT |
| 20 MAR 2026 | CN264026 | Shelby County | 252 | $478.00 | $590.88 | 6 | Thomson & Thomson, Inc. | TDOT |
| 20 MAR 2026 | CN261025 | Sullivan County | 2,366 | $187.10 | $183.55 | 2 | W-L Construction & Paving, Inc. | TDOT |
| 20 MAR 2026 | CN261027 | Unicoi County | 3,269 | $176.00 | $176.00 | 1 | Summers-Taylor, Inc. | TDOT |
| 20 MAR 2026 | CN263036 | Williamson County | 25,801 | $120.00 | $127.60 | 3 | Vulcan Construction Materials, LLC | TDOT |
| 20 MAR 2026 | CN263025 | Davidson County | 23,351 | $120.00 | $125.00 | 3 | Vulcan Construction Materials, LLC | TDOT |
| 09 JAN 2026 | CN262018 | Marion County | 900 | $227.00 | $204.00 | 4 | Summers-Taylor, Inc. | TDOT |
| 05 DEC 2025 | CNZ327 | Cumberland County | 12,875 | $134.35 | $140.68 | 2 | Rogers Group, Inc. | TDOT |
| 05 DEC 2025 | CNZ290 | Cumberland County | 7,041 | $132.00 | $144.92 | 4 | Rogers Group, Inc. | TDOT |
Filter this item by your own quantity, county and period, or check your price against it, in the TDOT explorer.
How these prices were read
TDOT Summary of Bids PDFs: every letting posted for February 2024 to October 2026, and nine lettings of 2018 to 2023 recovered from archived copies of the tn.gov files. Cost-plus-time bids, and bids that did not match their published total, are left out.
- Statistics leave out bids over three times the low bid, zero or negative prices and token prices under 5% of the median.
- Item codes and units are TDOT's own: this item is compared with TDOT contracts only.
- Prices are bid prices, not paid prices, and are not adjusted for inflation. Use them as a reference range, never as a quote.
Your own bid history, read the same way
Mirage deploys AI agents for heavy civil estimating teams: quantities from the plan set, specs and addenda read, and bid tabs compared, inside your systems and your rules.