Acs mix(PG64-22) grading d unit price, Tennessee
Low bidders on TDOT contracts carried a median of $167.50 per TON for item 411-01.10, acs mix(pg64-22) grading d, over the 24 months to 02 OCT 2026, across 198 low bids. Half of all 559 bids fell between $135.00 and $248.50.
- Owner
- Tennessee DOT
- Item
- 411-01.10
- Unit
- TON
- Latest letting
- 02 OCT 2026
By year of letting
| Year | Contracts | Low bids | Low-bid median | All bids | Median, all bids |
|---|---|---|---|---|---|
| 2018 | 42 | 42 | $93.08 | 108 | $106.48 |
| 2020 | 22 | 23 | $111.09 | 64 | $124.50 |
| 2023 | 8 | 8 | $312.98 | 27 | $306.00 |
| 2024 | 89 | 90 | $166.50 | 252 | $180.00 |
| 2025 | 85 | 85 | $167.00 | 234 | $171.38 |
| 2026 | 81 | 80 | $159.00 | 234 | $176.72 |
Bid prices as published, not adjusted for inflation.
By county
| County | Low bids | Low-bid median | All bids | Median, all bids |
|---|---|---|---|---|
| Williamson County | 4 | $189.75 | 21 | $155.00 |
| Maury County | 4 | $135.00 | 21 | $175.00 |
| Cumberland County | 6 | $176.22 | 19 | $187.00 |
| Rutherford County | 4 | $154.62 | 18 | $169.50 |
| Anderson County | 4 | $205.00 | 16 | $221.76 |
| Humphreys County | 4 | $177.35 | 15 | $220.00 |
| Sumner County | 4 | $162.50 | 14 | $170.64 |
| Hardin County | 4 | $117.88 | 14 | $245.00 |
| Bradley County | 4 | $161.32 | 13 | $270.16 |
| Bedford County | 3 | $122.50 | 13 | $135.00 |
| Shelby County | 5 | $212.00 | 12 | $209.00 |
| Carter County | 5 | $361.75 | 12 | $373.38 |
Countys with at least three low bids, over the last 24 months.
By quantity
| Quantity (TON) | Low bids | Low-bid median |
|---|---|---|
| 6 to 266 | 49 | $300.00 |
| 278 to 1,935 | 50 | $200.00 |
| 2,062 to 6,323 | 49 | $155.00 |
| 6,432 to 26,796 | 50 | $122.50 |
The low bids split into four bands of equal count by the quantity on the contract. Larger quantities usually carry lower unit prices.
Latest contracts with this item
| Let | Contract | County | Quantity | Low bidder's price | Median | Bids | Low bidder | Source |
|---|---|---|---|---|---|---|---|---|
| 02 OCT 2026 | CN261076 | Anderson County | 188 | $210.00 | $230.50 | 4 | Rogers Group, Inc. | TDOT |
| 02 OCT 2026 | CN263064 | Bedford County | 33 | $425.00 | $461.00 | 6 | Jones Bros. Contractors, LLC | TDOT |
| 02 OCT 2026 | CN261070 | Carter County | 34 | $732.18 | $700.00 | 3 | Baker's Construction Services, Inc. | TDOT |
| 02 OCT 2026 | CN261067 | Carter County | 69 | $361.75 | $348.38 | 4 | Eclipse Companies,LLC | TDOT |
| 02 OCT 2026 | CN261074 | Claiborne County | 120 | $300.00 | $286.00 | 5 | Southern Constructors, Inc. | TDOT |
| 02 OCT 2026 | CN264061 | Henry And Stewart Counties | 2,062 | $132.00 | $164.99 | 3 | Delta Contracting Company, LLC | TDOT |
| 02 OCT 2026 | CN263065 | Humphreys County | 81 | $300.00 | $384.50 | 6 | Dement Construction Group, LLC | TDOT |
| 02 OCT 2026 | CN263066 | Smith County | 675 | $200.00 | $201.75 | 4 | Rock Supremacy, LLC | TDOT |
| 02 OCT 2026 | CN261064 | Sullivan County | 2,700 | $199.50 | $199.50 | 1 | Summers-Taylor, Inc. | TDOT |
| 14 AUG 2026 | CN261063 | Campbell County | 219 | $198.00 | $205.00 | 5 | Rogers Group, Inc. | TDOT |
| 14 AUG 2026 | CN262059 | Coffee County | 431 | $203.00 | $230.00 | 5 | Jones Bros. Contractors, LLC | TDOT |
| 14 AUG 2026 | CN262058 | Cumberland County | 5,513 | $177.45 | $180.72 | 6 | Charles Blalock & Sons, Inc. | TDOT |
| 14 AUG 2026 | CN264048 | Dyer County | 1,100 | $215.00 | $215.00 | 1 | Ford Construction Company | TDOT |
| 14 AUG 2026 | CN261061 | Knox County | 741 | $210.00 | $230.00 | 4 | Charles Blalock & Sons, Inc. | TDOT |
| 14 AUG 2026 | CN264054 | Shelby County | 914 | $178.00 | $189.00 | 2 | Dement Construction Group, LLC | TDOT |
Filter this item by your own quantity, county and period, or check your price against it, in the TDOT explorer.
How these prices were read
TDOT Summary of Bids PDFs: every letting posted for February 2024 to October 2026, and nine lettings of 2018 to 2023 recovered from archived copies of the tn.gov files. Cost-plus-time bids, and bids that did not match their published total, are left out.
- Statistics leave out bids over three times the low bid, zero or negative prices and token prices under 5% of the median.
- Item codes and units are TDOT's own: this item is compared with TDOT contracts only.
- Prices are bid prices, not paid prices, and are not adjusted for inflation. Use them as a reference range, never as a quote.
Your own bid history, read the same way