Trackless tack coat unit price, Tennessee
Low bidders on TDOT contracts carried a median of $939.55 per TON for item 403-02.01, trackless tack coat, over the 24 months to 02 OCT 2026, across 161 low bids. Half of all 340 bids fell between $855.00 and $1,080.04.
- Owner
- Tennessee DOT
- Item
- 403-02.01
- Unit
- TON
- Latest letting
- 02 OCT 2026
By year of letting
| Year | Contracts | Low bids | Low-bid median | All bids | Median, all bids |
|---|---|---|---|---|---|
| 2018 | 2 | 2 | $897.50 | 3 | $995.00 |
| 2020 | 2 | 2 | $837.50 | 2 | $837.50 |
| 2023 | 12 | 12 | $925.00 | 21 | $875.00 |
| 2024 | 53 | 53 | $870.00 | 115 | $950.00 |
| 2025 | 78 | 79 | $904.00 | 163 | $950.00 |
| 2026 | 63 | 60 | $972.50 | 125 | $960.00 |
Bid prices as published, not adjusted for inflation.
By county
| County | Low bids | Low-bid median | All bids | Median, all bids |
|---|---|---|---|---|
| Shelby County | 10 | $1,006.00 | 27 | $1,250.00 |
| Hamilton County | 11 | $905.00 | 22 | $900.00 |
| Henderson County | 7 | $350.00 | 20 | $810.00 |
| Cumberland County | 8 | $955.00 | 13 | $1,000.00 |
| Hardin County | 5 | $250.00 | 10 | $580.00 |
| Gibson County | 5 | $350.00 | 9 | $754.35 |
| Decatur County | 3 | $300.00 | 8 | $857.00 |
| Tipton County | 4 | $1,305.00 | 8 | $1,318.95 |
| Fayette County | 3 | $1,215.50 | 8 | $1,207.75 |
| Coffee County | 3 | $855.82 | 7 | $904.00 |
| Madison County | 3 | $500.00 | 7 | $500.00 |
| Mcminn County | 6 | $925.00 | 7 | $905.00 |
Countys with at least three low bids, over the last 24 months.
By quantity
| Quantity (TON) | Low bids | Low-bid median |
|---|---|---|
| 1 to 34 | 40 | $950.00 |
| 35 to 63 | 40 | $925.00 |
| 64 to 112 | 40 | $907.50 |
| 112 to 352 | 41 | $905.00 |
The low bids split into four bands of equal count by the quantity on the contract. Larger quantities usually carry lower unit prices.
Latest contracts with this item
| Let | Contract | County | Quantity | Low bidder's price | Median | Bids | Low bidder | Source |
|---|---|---|---|---|---|---|---|---|
| 02 OCT 2026 | CN264061 | Henry And Stewart Counties | 62 | $250.00 | $800.00 | 3 | Delta Contracting Company, LLC | TDOT |
| 14 AUG 2026 | CN262060 | Meigs County | 2 | $1,095.16 | $1,095.16 | 5 | Mid-State Construction Company, Inc. | TDOT |
| 26 JUN 2026 | CN264043 | Dyer County | 77 | $500.00 | $500.00 | 1 | Ford Construction Company | TDOT |
| 26 JUN 2026 | CN262047 | Fentress County | 52.40 | $1,025.00 | $1,037.50 | 2 | Rogers Group, Inc. | TDOT |
| 26 JUN 2026 | CN262054 | Franklin County | 115 | $1,200.00 | $1,200.00 | 1 | Tinsley Asphalt, LLC | TDOT |
| 26 JUN 2026 | CN264045 | Haywood County | 184 | $200.00 | $350.00 | 2 | Delta Contracting Company, LLC | TDOT |
| 26 JUN 2026 | CN264047 | Henderson County | 54 | $200.00 | $560.00 | 2 | Delta Contracting Company, LLC | TDOT |
| 26 JUN 2026 | CN264050 | Henry County | 79 | $250.00 | $474.62 | 2 | Delta Contracting Company, LLC | TDOT |
| 26 JUN 2026 | CN262049 | Marion County | 32 | $1,200.00 | $1,150.00 | 2 | Tinsley Asphalt, LLC | TDOT |
| 26 JUN 2026 | CN262050 | Mcminn County | 62 | $950.00 | $950.00 | 1 | Rogers Group, Inc. | TDOT |
| 26 JUN 2026 | CN264051 | Mcnairy County | 38 | n/a | $1,500.00 | 1 | Asphalt Paving Systems, Inc. | TDOT |
| 26 JUN 2026 | CN262053 | Sequatchie County | 50 | $985.00 | $985.00 | 1 | Rogers Group, Inc. | TDOT |
| 26 JUN 2026 | CN262052 | Sequatchie County | 88 | $1,110.00 | $1,110.00 | 1 | Tinsley Asphalt, LLC | TDOT |
| 26 JUN 2026 | CN264042 | Tipton County | 11 | $1,365.00 | $1,365.00 | 3 | Ford Construction Company | TDOT |
| 26 JUN 2026 | CN264904 | Gibson County | 150 | $200.00 | $575.00 | 2 | Delta Contracting Company, LLC | TDOT |
Filter this item by your own quantity, county and period, or check your price against it, in the TDOT explorer.
How these prices were read
TDOT Summary of Bids PDFs: every letting posted for February 2024 to October 2026, and nine lettings of 2018 to 2023 recovered from archived copies of the tn.gov files. Cost-plus-time bids, and bids that did not match their published total, are left out.
- Statistics leave out bids over three times the low bid, zero or negative prices and token prices under 5% of the median.
- Item codes and units are TDOT's own: this item is compared with TDOT contracts only.
- Prices are bid prices, not paid prices, and are not adjusted for inflation. Use them as a reference range, never as a quote.
Your own bid history, read the same way
Mirage deploys AI agents for heavy civil estimating teams: quantities from the plan set, specs and addenda read, and bid tabs compared, inside your systems and your rules.