Bituminous material for prime coat (pc) unit price, Tennessee
Low bidders on TDOT contracts carried a median of $1,167.50 per TON for item 402-01, bituminous material for prime coat (pc), over the 24 months to 02 OCT 2026, across 108 low bids. Half of all 348 bids fell between $999.50 and $1,607.91.
- Owner
- Tennessee DOT
- Item
- 402-01
- Unit
- TON
- Latest letting
- 02 OCT 2026
By year of letting
| Year | Contracts | Low bids | Low-bid median | All bids | Median, all bids |
|---|---|---|---|---|---|
| 2018 | 12 | 11 | $1,000.00 | 39 | $893.00 |
| 2020 | 15 | 15 | $900.00 | 48 | $910.31 |
| 2023 | 6 | 6 | $1,140.00 | 16 | $1,140.00 |
| 2024 | 58 | 57 | $1,100.00 | 184 | $1,164.45 |
| 2025 | 50 | 50 | $1,405.00 | 160 | $1,352.71 |
| 2026 | 29 | 29 | $800.00 | 99 | $1,200.00 |
Bid prices as published, not adjusted for inflation.
By county
| County | Low bids | Low-bid median | All bids | Median, all bids |
|---|---|---|---|---|
| Rutherford County | 4 | $1,080.00 | 19 | $1,050.00 |
| Sumner County | 3 | $1,200.00 | 16 | $1,275.00 |
| Williamson County | 4 | $1,202.50 | 16 | $1,422.50 |
| Cumberland County | 5 | $1,265.00 | 14 | $1,252.20 |
| Anderson County | 3 | $1,435.00 | 12 | $1,397.50 |
| Bradley County | 3 | $1,300.00 | 12 | $1,631.99 |
| Coffee County | 3 | $1,080.60 | 11 | $1,184.46 |
| Monroe County | 3 | $945.00 | 11 | $505.00 |
| Shelby County | 3 | $1,488.27 | 9 | $1,466.00 |
| Sullivan County | 3 | $2,000.00 | 9 | $2,130.00 |
| Chester County | 3 | $450.00 | 8 | $450.00 |
| Hamilton County | 3 | $2,200.00 | 7 | $1,500.00 |
Countys with at least three low bids, over the last 24 months.
By quantity
| Quantity (TON) | Low bids | Low-bid median |
|---|---|---|
| 0.20 to 3 | 27 | $1,655.00 |
| 3 to 8 | 27 | $1,350.00 |
| 8 to 27 | 27 | $1,080.00 |
| 28 to 387 | 27 | $1,000.00 |
The low bids split into four bands of equal count by the quantity on the contract. Larger quantities usually carry lower unit prices.
Latest contracts with this item
| Let | Contract | County | Quantity | Low bidder's price | Median | Bids | Low bidder | Source |
|---|---|---|---|---|---|---|---|---|
| 02 OCT 2026 | CN263064 | Bedford County | 1.40 | $850.00 | $2,615.00 | 6 | Jones Bros. Contractors, LLC | TDOT |
| 02 OCT 2026 | CN263065 | Humphreys County | 2 | $100.00 | $510.00 | 6 | Dement Construction Group, LLC | TDOT |
| 14 AUG 2026 | CN264048 | Dyer County | 27 | $500.00 | $500.00 | 1 | Ford Construction Company | TDOT |
| 14 AUG 2026 | CN261061 | Knox County | 8 | $142.00 | $1,212.73 | 4 | Charles Blalock & Sons, Inc. | TDOT |
| 14 AUG 2026 | CN264052 | Tipton County | 11 | $1,375.00 | $1,375.00 | 2 | Delta Contracting Company, LLC | TDOT |
| 26 JUN 2026 | CN264041 | Chester County | 4 | $150.00 | $325.00 | 2 | Delta Contracting Company, LLC | TDOT |
| 26 JUN 2026 | CN263059 | Dickson And Hickman Counties | 29 | $800.00 | $800.00 | 3 | Jones Bros. Contractors, LLC | TDOT |
| 26 JUN 2026 | CN264049 | Dyer County | 11 | $500.00 | $500.00 | 3 | Ford Construction Company | TDOT |
| 26 JUN 2026 | CN261057 | Hawkins County | 27 | $315.00 | $317.50 | 4 | Whaley Construction, LLC | TDOT |
| 26 JUN 2026 | CN261901 | Johnson County | 1.10 | $800.00 | $955.19 | 2 | Southern Constructors, Inc. | TDOT |
| 26 JUN 2026 | CN264037 | Lake County | 32 | $300.00 | $300.00 | 1 | Ford Construction Company | TDOT |
| 26 JUN 2026 | CN263052 | Maury County | 14 | $200.00 | $1,200.00 | 8 | Eubank Asphalt Paving & Sealing, LLC | TDOT |
| 26 JUN 2026 | CN261044 | Monroe County | 136 | $128.10 | $328.00 | 6 | Charles Blalock & Sons, Inc. | TDOT |
| 26 JUN 2026 | CN263057 | Rutherford County | 387 | $1,260.00 | $1,155.00 | 4 | Civil Constructors, LLC | TDOT |
| 26 JUN 2026 | CN264042 | Tipton County | 8 | $1,365.00 | $1,365.00 | 3 | Ford Construction Company | TDOT |
Filter this item by your own quantity, county and period, or check your price against it, in the TDOT explorer.
How these prices were read
TDOT Summary of Bids PDFs: every letting posted for February 2024 to October 2026, and nine lettings of 2018 to 2023 recovered from archived copies of the tn.gov files. Cost-plus-time bids, and bids that did not match their published total, are left out.
- Statistics leave out bids over three times the low bid, zero or negative prices and token prices under 5% of the median.
- Item codes and units are TDOT's own: this item is compared with TDOT contracts only.
- Prices are bid prices, not paid prices, and are not adjusted for inflation. Use them as a reference range, never as a quote.