Bituminous material for tack coat (tc) unit price, Tennessee
Low bidders on TDOT contracts carried a median of $967.40 per TON for item 403-01, bituminous material for tack coat (tc), over the 24 months to 02 OCT 2026, across 314 low bids. Half of all 920 bids fell between $875.00 and $1,200.00.
- Owner
- Tennessee DOT
- Item
- 403-01
- Unit
- TON
- Latest letting
- 02 OCT 2026
By year of letting
| Year | Contracts | Low bids | Low-bid median | All bids | Median, all bids |
|---|---|---|---|---|---|
| 2018 | 86 | 84 | $672.49 | 188 | $695.51 |
| 2020 | 50 | 50 | $692.50 | 125 | $712.00 |
| 2023 | 18 | 18 | $1,037.50 | 47 | $1,170.00 |
| 2024 | 143 | 142 | $1,000.00 | 419 | $1,050.00 |
| 2025 | 147 | 147 | $975.00 | 409 | $1,000.00 |
| 2026 | 115 | 112 | $950.00 | 354 | $989.55 |
Bid prices as published, not adjusted for inflation.
By county
| County | Low bids | Low-bid median | All bids | Median, all bids |
|---|---|---|---|---|
| Rutherford County | 14 | $925.00 | 63 | $975.00 |
| Davidson County | 18 | $900.00 | 57 | $900.00 |
| Williamson County | 11 | $900.00 | 49 | $925.00 |
| Knox County | 13 | $925.00 | 44 | $925.00 |
| Maury County | 11 | $860.00 | 42 | $961.42 |
| Sumner County | 9 | $950.79 | 29 | $987.83 |
| Anderson County | 8 | $960.00 | 28 | $980.00 |
| Sullivan County | 12 | $1,175.00 | 26 | $1,200.00 |
| Bedford County | 5 | $950.00 | 22 | $986.73 |
| Hawkins County | 8 | $1,123.15 | 19 | $1,312.50 |
| Shelby County | 6 | $1,382.24 | 19 | $1,390.00 |
| Humphreys County | 5 | $300.00 | 18 | $847.50 |
Countys with at least three low bids, over the last 24 months.
By quantity
| Quantity (TON) | Low bids | Low-bid median |
|---|---|---|
| 0.03 to 5.90 | 78 | $1,250.00 |
| 5.90 to 39 | 79 | $950.00 |
| 40 to 90 | 78 | $915.30 |
| 90 to 343 | 79 | $900.00 |
The low bids split into four bands of equal count by the quantity on the contract. Larger quantities usually carry lower unit prices.
Latest contracts with this item
| Let | Contract | County | Quantity | Low bidder's price | Median | Bids | Low bidder | Source |
|---|---|---|---|---|---|---|---|---|
| 02 OCT 2026 | CN261076 | Anderson County | 2.10 | $940.00 | $1,193.50 | 4 | Rogers Group, Inc. | TDOT |
| 02 OCT 2026 | CN263064 | Bedford County | 0.30 | $850.00 | $2,550.00 | 6 | Jones Bros. Contractors, LLC | TDOT |
| 02 OCT 2026 | CN261070 | Carter County | 1 | $1,719.04 | $1,600.00 | 3 | Baker's Construction Services, Inc. | TDOT |
| 02 OCT 2026 | CN261067 | Carter County | 0.03 | $1,458.00 | $1,588.50 | 4 | Eclipse Companies,LLC | TDOT |
| 02 OCT 2026 | CN261074 | Claiborne County | 1 | $1,250.00 | $1,210.00 | 5 | Southern Constructors, Inc. | TDOT |
| 02 OCT 2026 | CN264057 | Hardin County | 11 | $225.00 | $248.00 | 5 | Delta Contracting Company, LLC | TDOT |
| 02 OCT 2026 | CN261079 | Hawkins County | 2 | $1,450.00 | $1,425.00 | 3 | Southern Constructors, Inc. | TDOT |
| 02 OCT 2026 | CN263065 | Humphreys County | 0.50 | $100.00 | $510.00 | 6 | Dement Construction Group, LLC | TDOT |
| 02 OCT 2026 | CN261072 | Johnson County | 2 | $3,183.40 | $3,183.40 | 1 | Baker's Construction Services, Inc. | TDOT |
| 02 OCT 2026 | CN261073 | Knox County | 2 | $1,400.00 | $1,400.00 | 4 | Bluegrass Contracting Corporation | TDOT |
| 02 OCT 2026 | CN263066 | Smith County | 3 | $1,500.00 | $1,365.00 | 4 | Rock Supremacy, LLC | TDOT |
| 02 OCT 2026 | CN261064 | Sullivan County | 30 | $1,350.00 | $1,350.00 | 1 | Summers-Taylor, Inc. | TDOT |
| 14 AUG 2026 | CN261063 | Campbell County | 4 | $1,120.00 | $1,176.00 | 5 | Rogers Group, Inc. | TDOT |
| 14 AUG 2026 | CN262059 | Coffee County | 3 | $1,050.00 | $1,100.00 | 5 | Jones Bros. Contractors, LLC | TDOT |
| 14 AUG 2026 | CN262058 | Cumberland County | 142 | $1,050.00 | $1,075.00 | 6 | Charles Blalock & Sons, Inc. | TDOT |
Filter this item by your own quantity, county and period, or check your price against it, in the TDOT explorer.
How these prices were read
TDOT Summary of Bids PDFs: every letting posted for February 2024 to October 2026, and nine lettings of 2018 to 2023 recovered from archived copies of the tn.gov files. Cost-plus-time bids, and bids that did not match their published total, are left out.
- Statistics leave out bids over three times the low bid, zero or negative prices and token prices under 5% of the median.
- Item codes and units are TDOT's own: this item is compared with TDOT contracts only.
- Prices are bid prices, not paid prices, and are not adjusted for inflation. Use them as a reference range, never as a quote.