Longitudinal joint sealant unit price, Tennessee
Low bidders on TDOT contracts carried a median of $2,900.00 per LM for item 411-01.21, longitudinal joint sealant, over the 24 months to 02 OCT 2026, across 124 low bids. Half of all 264 bids fell between $2,750.00 and $3,190.00.
- Owner
- Tennessee DOT
- Item
- 411-01.21
- Unit
- LM
- Latest letting
- 26 JUN 2026
By year of letting
| Year | Contracts | Low bids | Low-bid median | All bids | Median, all bids |
|---|---|---|---|---|---|
| 2020 | 3 | 3 | $3,100.00 | 4 | $3,000.00 |
| 2023 | 7 | 7 | $3,050.00 | 13 | $3,050.00 |
| 2024 | 31 | 31 | $2,940.00 | 62 | $3,080.00 |
| 2025 | 69 | 69 | $2,900.00 | 155 | $2,900.00 |
| 2026 | 53 | 50 | $2,900.00 | 99 | $2,900.00 |
Bid prices as published, not adjusted for inflation.
By county
| County | Low bids | Low-bid median | All bids | Median, all bids |
|---|---|---|---|---|
| Shelby County | 10 | $2,010.00 | 27 | $3,250.00 |
| Hamilton County | 10 | $3,174.25 | 20 | $3,209.50 |
| Davidson County | 5 | $2,950.00 | 15 | $2,800.00 |
| Henderson County | 5 | $2,800.00 | 14 | $2,875.00 |
| Cumberland County | 6 | $2,957.00 | 9 | $2,850.00 |
| Hardin County | 3 | $2,900.00 | 7 | $2,900.00 |
| Marion County | 3 | $3,049.50 | 6 | $3,097.50 |
| Putnam County | 3 | $2,692.00 | 6 | $2,671.00 |
| Fentress County | 3 | $2,877.00 | 5 | $2,750.00 |
| Mcnairy County | 3 | $2,856.00 | 5 | $2,856.00 |
| Haywood County | 3 | $3,200.00 | 5 | $3,200.00 |
| Sequatchie County | 3 | $2,940.00 | 5 | $2,940.00 |
Countys with at least three low bids, over the last 24 months.
By quantity
| Quantity (LM) | Low bids | Low-bid median |
|---|---|---|
| 0.10 to 6 | 31 | $3,010.00 |
| 6.20 to 11.40 | 31 | $2,992.50 |
| 11.90 to 20 | 31 | $2,800.00 |
| 20.20 to 63.34 | 31 | $2,800.00 |
The low bids split into four bands of equal count by the quantity on the contract. Larger quantities usually carry lower unit prices.
Latest contracts with this item
| Let | Contract | County | Quantity | Low bidder's price | Median | Bids | Low bidder | Source |
|---|---|---|---|---|---|---|---|---|
| 26 JUN 2026 | CN264043 | Dyer County | 8 | $3,190.00 | $3,190.00 | 1 | Ford Construction Company | TDOT |
| 26 JUN 2026 | CN262047 | Fentress County | 12 | $2,510.00 | $2,605.00 | 2 | Rogers Group, Inc. | TDOT |
| 26 JUN 2026 | CN262054 | Franklin County | 20 | $2,996.00 | $2,996.00 | 1 | Tinsley Asphalt, LLC | TDOT |
| 26 JUN 2026 | CN264045 | Haywood County | 16 | $2,800.00 | $2,800.00 | 2 | Delta Contracting Company, LLC | TDOT |
| 26 JUN 2026 | CN264047 | Henderson County | 15 | $2,800.00 | $2,850.00 | 2 | Delta Contracting Company, LLC | TDOT |
| 26 JUN 2026 | CN264050 | Henry County | 7 | $3,000.00 | $3,000.00 | 2 | Delta Contracting Company, LLC | TDOT |
| 26 JUN 2026 | CN262049 | Marion County | 6.20 | $3,049.50 | $3,424.75 | 2 | Tinsley Asphalt, LLC | TDOT |
| 26 JUN 2026 | CN262050 | Mcminn County | 17 | $2,800.00 | $2,800.00 | 1 | Rogers Group, Inc. | TDOT |
| 26 JUN 2026 | CN264051 | Mcnairy County | 11.69 | n/a | $2,730.00 | 1 | Asphalt Paving Systems, Inc. | TDOT |
| 26 JUN 2026 | CN262053 | Sequatchie County | 13 | $2,589.00 | $2,589.00 | 1 | Rogers Group, Inc. | TDOT |
| 26 JUN 2026 | CN262052 | Sequatchie County | 17 | $2,940.00 | $2,940.00 | 1 | Tinsley Asphalt, LLC | TDOT |
| 08 MAY 2026 | CN262040 | Cumberland County | 5.30 | $2,745.50 | $2,672.75 | 2 | Rogers Group, Inc. | TDOT |
| 08 MAY 2026 | CN262046 | Cumberland And Fentress Counties | 1.60 | $2,745.00 | $2,747.50 | 2 | Rogers Group, Inc. | TDOT |
| 08 MAY 2026 | CN262042 | Hamilton County | 7 | $3,162.50 | $3,106.25 | 2 | APAC-Atlantic, Inc. | TDOT |
| 08 MAY 2026 | CN262043 | Hamilton County | 16 | $3,050.00 | $3,106.25 | 2 | Wright Brothers Construction Company, Inc. | TDOT |
Filter this item by your own quantity, county and period, or check your price against it, in the TDOT explorer.
How these prices were read
TDOT Summary of Bids PDFs: every letting posted for February 2024 to October 2026, and nine lettings of 2018 to 2023 recovered from archived copies of the tn.gov files. Cost-plus-time bids, and bids that did not match their published total, are left out.
- Statistics leave out bids over three times the low bid, zero or negative prices and token prices under 5% of the median.
- Item codes and units are TDOT's own: this item is compared with TDOT contracts only.
- Prices are bid prices, not paid prices, and are not adjusted for inflation. Use them as a reference range, never as a quote.