Scoring shoulders (continuous) (16IN width) unit price, Tennessee
Low bidders on TDOT contracts carried a median of $955.00 per LM for item 411-12.01, scoring shoulders (continuous) (16in width), over the 24 months to 02 OCT 2026, across 108 low bids. Half of all 292 bids fell between $713.42 and $2,000.00.
- Owner
- Tennessee DOT
- Item
- 411-12.01
- Unit
- LM
- Latest letting
- 02 OCT 2026
By year of letting
| Year | Contracts | Low bids | Low-bid median | All bids | Median, all bids |
|---|---|---|---|---|---|
| 2018 | 24 | 24 | $698.62 | 42 | $670.00 |
| 2020 | 9 | 9 | $775.00 | 21 | $1,485.00 |
| 2023 | 13 | 13 | $771.80 | 26 | $768.40 |
| 2024 | 53 | 53 | $1,000.00 | 135 | $1,035.00 |
| 2025 | 59 | 59 | $950.00 | 161 | $975.00 |
| 2026 | 22 | 22 | $967.12 | 65 | $1,207.50 |
Bid prices as published, not adjusted for inflation.
By county
| County | Low bids | Low-bid median | All bids | Median, all bids |
|---|---|---|---|---|
| Davidson County | 8 | $782.50 | 27 | $950.00 |
| Shelby County | 8 | $1,645.78 | 26 | $1,596.76 |
| Williamson County | 4 | $659.88 | 16 | $700.43 |
| Knox County | 4 | $922.50 | 13 | $825.00 |
| Cumberland County | 4 | $816.12 | 12 | $1,304.40 |
| Marion County | 5 | $1,050.00 | 11 | $1,335.50 |
| Sumner County | 3 | $775.00 | 10 | $850.26 |
| Henderson County | 3 | $825.00 | 9 | $905.00 |
| Sullivan County | 4 | $1,195.00 | 8 | $1,044.38 |
| Maury County | 3 | $634.38 | 8 | $629.69 |
| Madison County | 3 | $3,150.00 | 7 | $3,400.00 |
| Mcminn County | 3 | $795.00 | 4 | $775.00 |
Countys with at least three low bids, over the last 24 months.
By quantity
| Quantity (LM) | Low bids | Low-bid median |
|---|---|---|
| 0.16 to 2.70 | 27 | $4,658.00 |
| 4.40 to 10 | 27 | $950.00 |
| 10 to 18 | 27 | $845.00 |
| 18 to 33.80 | 27 | $750.00 |
The low bids split into four bands of equal count by the quantity on the contract. Larger quantities usually carry lower unit prices.
Latest contracts with this item
| Let | Contract | County | Quantity | Low bidder's price | Median | Bids | Low bidder | Source |
|---|---|---|---|---|---|---|---|---|
| 02 OCT 2026 | CN264061 | Henry And Stewart Counties | 4.40 | $1,200.00 | $1,200.00 | 3 | Delta Contracting Company, LLC | TDOT |
| 26 JUN 2026 | CN263059 | Dickson And Hickman Counties | 1.80 | $3,425.00 | $3,360.00 | 3 | Jones Bros. Contractors, LLC | TDOT |
| 26 JUN 2026 | CN261057 | Hawkins County | 1.60 | $4,702.50 | $3,725.42 | 4 | Whaley Construction, LLC | TDOT |
| 26 JUN 2026 | CN263054 | Williamson County | 14.60 | $764.25 | $702.12 | 4 | Volunteer Paving, LLC | TDOT |
| 08 MAY 2026 | CN262042 | Hamilton County | 5.10 | $1,207.50 | $1,353.75 | 2 | APAC-Atlantic, Inc. | TDOT |
| 08 MAY 2026 | CN264039 | Henderson County | 5 | $2,550.00 | $2,550.00 | 3 | Jones Bros. Contractors, LLC | TDOT |
| 08 MAY 2026 | CN264036 | Henry County | 0.30 | $5,500.00 | $5,500.00 | 4 | Delta Contracting Company, LLC | TDOT |
| 08 MAY 2026 | CN261041 | Knox County | 12 | $550.00 | $535.00 | 3 | APAC-Atlantic, Inc. | TDOT |
| 20 MAR 2026 | CN264025 | Fayette And Shelby Counties | 33.48 | $515.00 | $525.30 | 3 | APAC-Tennessee, Inc. | TDOT |
| 20 MAR 2026 | CN264022 | Obion County | 6.50 | $1,305.00 | $1,305.00 | 1 | Ford Construction Company | TDOT |
| 20 MAR 2026 | CN264027 | Shelby County | 14 | $600.00 | $606.00 | 3 | APAC-Tennessee, Inc. | TDOT |
| 20 MAR 2026 | CN264026 | Shelby County | 0.40 | $46,800 | $23,895 | 6 | Thomson & Thomson, Inc. | TDOT |
| 20 MAR 2026 | CN261025 | Sullivan County | 18 | $638.40 | $964.20 | 2 | W-L Construction & Paving, Inc. | TDOT |
| 20 MAR 2026 | CN263032 | Sumner County | 8.50 | $675.00 | $642.50 | 2 | Rogers Group, Inc. | TDOT |
| 20 MAR 2026 | CN261027 | Unicoi County | 31 | $1,170.00 | $1,170.00 | 1 | Summers-Taylor, Inc. | TDOT |
Filter this item by your own quantity, county and period, or check your price against it, in the TDOT explorer.
How these prices were read
TDOT Summary of Bids PDFs: every letting posted for February 2024 to October 2026, and nine lettings of 2018 to 2023 recovered from archived copies of the tn.gov files. Cost-plus-time bids, and bids that did not match their published total, are left out.
- Statistics leave out bids over three times the low bid, zero or negative prices and token prices under 5% of the median.
- Item codes and units are TDOT's own: this item is compared with TDOT contracts only.
- Prices are bid prices, not paid prices, and are not adjusted for inflation. Use them as a reference range, never as a quote.