Enhanced flat line thermo (8IN line) unit price, Tennessee

Low bidders on TDOT contracts carried a median of $2.75 per LF for item 716-12.06, enhanced flat line thermo (8in line), over the 24 months to 02 OCT 2026, across 40 low bids. Half of all 113 bids fell between $2.10 and $4.00.

Owner
Tennessee DOT
Item
716-12.06
Unit
LF
Latest letting
26 JUN 2026
$2.75Low bidder's median, per LF
$2.75Median of all bids, per LF
40Contracts in the window

By year of letting

Enhanced flat line thermo (8IN line), TDOT: unit prices by year
YearContractsLow bidsLow-bid medianAll bidsMedian, all bids
201877$2.0018$2.02
202033$2.0010$2.00
20242323$2.6559$3.00
20251919$3.0044$3.00
20261616$2.1550$2.17
Enhanced flat line thermo (8IN line), TDOT: unit prices by year

Bid prices as published, not adjusted for inflation.

By quantity

Enhanced flat line thermo (8IN line), TDOT: low bidder's median by quantity band
Quantity (LF)Low bidsLow-bid median
50 to 37810$2.62
491 to 1,299.9910$2.35
1,330 to 3,28310$2.74
3,880 to 9,42910$3.08
Enhanced flat line thermo (8IN line), TDOT: low bidder's median by quantity band

The low bids split into four bands of equal count by the quantity on the contract. Larger quantities usually carry lower unit prices.

Latest contracts with this item

Latest TDOT contracts carrying Enhanced flat line thermo (8IN line)
LetContractCountyQuantityLow bidder's priceMedianBidsLow bidderSource
26 JUN 2026CN262054Franklin County1,100$4.28$4.281Tinsley Asphalt, LLCTDOT
26 JUN 2026CN264045Haywood County3,880$4.00$4.002Delta Contracting Company, LLCTDOT
26 JUN 2026CN263052Maury County1,299.99$4.00$2.108Eubank Asphalt Paving & Sealing, LLCTDOT
26 JUN 2026CN263055Williamson County491$2.20$2.205Bell & Associates Construction, LLCTDOT
08 MAY 2026CN261039Knox County378$3.00$3.805The Truesdell CorporationTDOT
08 MAY 2026CN263044Sumner County4,475$1.60$1.603Rogers Group, Inc.TDOT
20 MAR 2026CN263036Williamson County1,563$2.00$2.123Vulcan Construction Materials, LLCTDOT
20 MAR 2026CN263025Davidson County950$2.00$2.003Vulcan Construction Materials, LLCTDOT
06 FEB 2026CN261007Counties Anderson, Blount, Campbell, Carter, Claiborne, Cocke, Grainger, Greene, Hamblen, Hancock, Hawkins, Jefferson, Johnson, Knox, Loudon, Monroe, Morgan, Roane, Scott, Sevier, Sullivan, Unicoi, Union, And Washington50$1.90$2.153Mullen's Markings, IncTDOT
06 FEB 2026CN263004Counties Bedford, Cheatham, Davidson, Dickson, Giles, Hickman, Houston, Humphreys, Lawrence, Lewis, Lincoln, Macon, Marshall, Maury, Montgomery, Moore, Perry, Robertson, Rutherford, Smith, Stewart, Sumner, Trousdale, Wayne, Williamson, And Wilson3,000$3.00$3.502Reynolds Sealing & Striping, Inc.TDOT
06 FEB 2026CN264001Counties Benton, Carroll, Chester, Crockett, Decatur, Dyer, Fayette, Gibson, Hardeman, Hardin, Haywood, Henderson, Henry, Lake, Lauderdale, Madison, Mcnairy, Obion, Shelby, Tipton, And Weakley100$3.00$3.001Traf-Mark Industries, L.L.C.TDOT
06 FEB 2026CN262003Counties Bledsoe, Bradley, Cannon, Clay, Coffee, Cumberland, Dekalb, Fentress, Franklin, Grundy, Hamilton, Jackson, Marion, Mcminn, Meigs, Overton, Pickett, Polk, Putnam, Rhea, Sequatchie, Van Buren, Warren, And White4,000$1.75$1.753Mullen's Markings, IncTDOT
06 FEB 2026CN262004Cannon County130$2.04$2.052Asphalt Paving Systems, Inc.TDOT
06 FEB 2026CN263017Montgomery County275$4.00$4.003Eubank Asphalt Paving & Sealing, LLCTDOT
06 FEB 2026CN262010Overton County120$2.10$2.103Asphalt Paving Systems, Inc.TDOT
Latest TDOT contracts carrying Enhanced flat line thermo (8IN line)

Filter this item by your own quantity, county and period, or check your price against it, in the TDOT explorer.

How these prices were read

TDOT Summary of Bids PDFs: every letting posted for February 2024 to October 2026, and nine lettings of 2018 to 2023 recovered from archived copies of the tn.gov files. Cost-plus-time bids, and bids that did not match their published total, are left out.

  • Statistics leave out bids over three times the low bid, zero or negative prices and token prices under 5% of the median.
  • Item codes and units are TDOT's own: this item is compared with TDOT contracts only.
  • Prices are bid prices, not paid prices, and are not adjusted for inflation. Use them as a reference range, never as a quote.

Your own bid history, read the same way

Mirage deploys AI agents for heavy civil estimating teams: quantities from the plan set, specs and addenda read, and bid tabs compared, inside your systems and your rules.

We use your email to reply to you and, now and then, to tell you about Mirage. You can opt out at any time. Privacy policy