Enhanced flatline thermo pvmt mrkng (6IN dotted line) unit price, Tennessee
Low bidders on TDOT contracts carried a median of $2.10 per LF for item 716-12.05, enhanced flatline thermo pvmt mrkng (6in dotted line), over the 24 months to 02 OCT 2026, across 137 low bids. Half of all 342 bids fell between $1.58 and $3.00.
- Owner
- Tennessee DOT
- Item
- 716-12.05
- Unit
- LF
- Latest letting
- 02 OCT 2026
By year of letting
| Year | Contracts | Low bids | Low-bid median | All bids | Median, all bids |
|---|---|---|---|---|---|
| 2018 | 19 | 19 | $1.50 | 38 | $1.93 |
| 2020 | 19 | 19 | $2.00 | 40 | $1.82 |
| 2023 | 11 | 11 | $2.60 | 20 | $2.50 |
| 2024 | 62 | 62 | $2.57 | 143 | $2.50 |
| 2025 | 73 | 73 | $2.10 | 181 | $2.11 |
| 2026 | 44 | 44 | $2.07 | 116 | $2.00 |
Bid prices as published, not adjusted for inflation.
By county
| County | Low bids | Low-bid median | All bids | Median, all bids |
|---|---|---|---|---|
| Davidson County | 10 | $2.00 | 33 | $2.00 |
| Rutherford County | 6 | $1.50 | 26 | $1.75 |
| Shelby County | 7 | $4.00 | 19 | $4.00 |
| Williamson County | 4 | $2.32 | 16 | $2.00 |
| Cannon County | 3 | $2.04 | 12 | $2.06 |
| Marion County | 6 | $2.10 | 12 | $2.30 |
| Cumberland County | 7 | $2.10 | 11 | $2.00 |
| Hamilton County | 5 | $1.45 | 11 | $1.65 |
| Sumner County | 3 | $2.10 | 11 | $2.50 |
| Wilson County | 3 | $2.00 | 11 | $2.25 |
| Henderson County | 3 | $2.00 | 9 | $3.00 |
| Knox County | 3 | $2.15 | 9 | $2.50 |
Countys with at least three low bids, over the last 24 months.
By quantity
| Quantity (LF) | Low bids | Low-bid median |
|---|---|---|
| 9 to 370 | 34 | $2.10 |
| 375 to 1,025 | 34 | $2.10 |
| 1,084 to 2,670 | 34 | $2.00 |
| 2,677 to 23,700 | 35 | $2.00 |
The low bids split into four bands of equal count by the quantity on the contract. Larger quantities usually carry lower unit prices.
Latest contracts with this item
| Let | Contract | County | Quantity | Low bidder's price | Median | Bids | Low bidder | Source |
|---|---|---|---|---|---|---|---|---|
| 02 OCT 2026 | CN264061 | Henry And Stewart Counties | 490 | $3.00 | $3.00 | 3 | Delta Contracting Company, LLC | TDOT |
| 14 AUG 2026 | CN262056 | Grundy County | 5,307 | $1.35 | $1.40 | 5 | Mack Construction, LLC | TDOT |
| 26 JUN 2026 | CN263048 | Bedford County | 570 | $1.00 | $1.68 | 4 | Hawkins Asphalt Paving, LLC | TDOT |
| 26 JUN 2026 | CN263059 | Dickson And Hickman Counties | 1,281 | $2.00 | $2.35 | 3 | Jones Bros. Contractors, LLC | TDOT |
| 26 JUN 2026 | CN262047 | Fentress County | 370 | $2.10 | $2.05 | 2 | Rogers Group, Inc. | TDOT |
| 26 JUN 2026 | CN262054 | Franklin County | 5,500 | $3.21 | $3.21 | 1 | Tinsley Asphalt, LLC | TDOT |
| 26 JUN 2026 | CN261057 | Hawkins County | 2,213 | $1.38 | $1.44 | 4 | Whaley Construction, LLC | TDOT |
| 26 JUN 2026 | CN264051 | Mcnairy County | 769 | $4.20 | $4.20 | 2 | Asphalt Paving Systems, Inc. | TDOT |
| 26 JUN 2026 | CN262052 | Sequatchie County | 320 | $2.14 | $2.14 | 1 | Tinsley Asphalt, LLC | TDOT |
| 26 JUN 2026 | CN263054 | Williamson County | 4,431 | $3.00 | $2.05 | 4 | Volunteer Paving, LLC | TDOT |
| 08 MAY 2026 | CN264033 | Gibson County | 515 | $4.00 | $5.96 | 2 | Delta Contracting Company, LLC | TDOT |
| 08 MAY 2026 | CN262043 | Hamilton County | 97 | $0.80 | $0.83 | 2 | Wright Brothers Construction Company, Inc. | TDOT |
| 08 MAY 2026 | CN264039 | Henderson County | 1,300 | $2.00 | $3.70 | 3 | Jones Bros. Contractors, LLC | TDOT |
| 08 MAY 2026 | CN262044 | Putnam County | 43 | $1.60 | $1.80 | 2 | Rogers Group, Inc. | TDOT |
| 08 MAY 2026 | CN262045 | White County | 250 | $2.10 | $2.05 | 2 | Rogers Group, Inc. | TDOT |
Filter this item by your own quantity, county and period, or check your price against it, in the TDOT explorer.
How these prices were read
TDOT Summary of Bids PDFs: every letting posted for February 2024 to October 2026, and nine lettings of 2018 to 2023 recovered from archived copies of the tn.gov files. Cost-plus-time bids, and bids that did not match their published total, are left out.
- Statistics leave out bids over three times the low bid, zero or negative prices and token prices under 5% of the median.
- Item codes and units are TDOT's own: this item is compared with TDOT contracts only.
- Prices are bid prices, not paid prices, and are not adjusted for inflation. Use them as a reference range, never as a quote.
Your own bid history, read the same way
Mirage deploys AI agents for heavy civil estimating teams: quantities from the plan set, specs and addenda read, and bid tabs compared, inside your systems and your rules.