Plastic pavement marking (stop line) unit price, Tennessee
Low bidders on TDOT contracts carried a median of $18.00 per LF for item 716-02.05, plastic pavement marking (stop line), over the 24 months to 02 OCT 2026, across 434 low bids. Half of all 1,109 bids fell between $13.25 and $25.00.
- Owner
- Tennessee DOT
- Item
- 716-02.05
- Unit
- LF
- Latest letting
- 02 OCT 2026
By year of letting
| Year | Contracts | Low bids | Low-bid median | All bids | Median, all bids |
|---|---|---|---|---|---|
| 2018 | 95 | 95 | $14.70 | 194 | $15.00 |
| 2020 | 70 | 70 | $14.00 | 162 | $15.00 |
| 2023 | 19 | 19 | $15.75 | 43 | $16.00 |
| 2024 | 169 | 169 | $19.00 | 437 | $20.00 |
| 2025 | 206 | 206 | $18.02 | 521 | $20.00 |
| 2026 | 168 | 168 | $16.43 | 426 | $18.00 |
Bid prices as published, not adjusted for inflation.
By county
| County | Low bids | Low-bid median | All bids | Median, all bids |
|---|---|---|---|---|
| Rutherford County | 14 | $20.02 | 61 | $20.00 |
| Davidson County | 18 | $25.00 | 57 | $22.00 |
| Williamson County | 9 | $24.04 | 41 | $25.00 |
| Knox County | 12 | $11.50 | 40 | $12.00 |
| Maury County | 9 | $25.00 | 36 | $24.15 |
| Sumner County | 9 | $21.00 | 29 | $21.19 |
| Anderson County | 8 | $13.78 | 27 | $16.00 |
| Shelby County | 10 | $30.62 | 26 | $30.45 |
| Hamilton County | 12 | $11.30 | 24 | $11.50 |
| Cumberland County | 9 | $12.40 | 19 | $12.40 |
| Gibson County | 9 | $25.00 | 19 | $26.84 |
| Sullivan County | 9 | $10.80 | 19 | $11.25 |
Countys with at least three low bids, over the last 24 months.
By quantity
| Quantity (LF) | Low bids | Low-bid median |
|---|---|---|
| 11 to 106 | 108 | $21.00 |
| 112 to 250 | 109 | $19.00 |
| 251 to 540 | 108 | $15.85 |
| 540 to 4,148 | 109 | $15.00 |
The low bids split into four bands of equal count by the quantity on the contract. Larger quantities usually carry lower unit prices.
Latest contracts with this item
| Let | Contract | County | Quantity | Low bidder's price | Median | Bids | Low bidder | Source |
|---|---|---|---|---|---|---|---|---|
| 02 OCT 2026 | CN261076 | Anderson County | 20 | $15.05 | $17.00 | 4 | Rogers Group, Inc. | TDOT |
| 02 OCT 2026 | CN261065 | Campbell And Morgan Counties | 101 | $10.00 | $10.05 | 4 | Mountain Home Construction LLC | TDOT |
| 02 OCT 2026 | CN261074 | Claiborne County | 15 | $17.00 | $17.00 | 5 | Southern Constructors, Inc. | TDOT |
| 02 OCT 2026 | CN261075 | Counties Cocke, Hawkins, Jefferson, Monroe, Scott, And Washington | 75 | $15.00 | $21.15 | 3 | Stansell Electric Company, Inc. | TDOT |
| 02 OCT 2026 | CN264057 | Hardin County | 66 | $35.00 | $38.00 | 5 | Delta Contracting Company, LLC | TDOT |
| 02 OCT 2026 | CN264061 | Henry And Stewart Counties | 400 | $21.00 | $21.00 | 3 | Delta Contracting Company, LLC | TDOT |
| 02 OCT 2026 | CN261072 | Johnson County | 35 | $22.29 | $22.29 | 1 | Baker's Construction Services, Inc. | TDOT |
| 02 OCT 2026 | CN263066 | Smith County | 60 | $20.00 | $28.15 | 4 | Rock Supremacy, LLC | TDOT |
| 02 OCT 2026 | CN261064 | Sullivan County | 200 | $14.56 | $14.56 | 1 | Summers-Taylor, Inc. | TDOT |
| 14 AUG 2026 | CN261063 | Campbell County | 75 | $15.50 | $15.50 | 5 | Rogers Group, Inc. | TDOT |
| 14 AUG 2026 | CN262058 | Cumberland County | 1,295 | $12.86 | $13.23 | 6 | Charles Blalock & Sons, Inc. | TDOT |
| 14 AUG 2026 | CN264048 | Dyer County | 142 | $35.00 | $35.00 | 1 | Ford Construction Company | TDOT |
| 14 AUG 2026 | CN262056 | Grundy County | 54 | $14.00 | $13.90 | 5 | Mack Construction, LLC | TDOT |
| 14 AUG 2026 | CN261061 | Knox County | 230 | $10.50 | $11.62 | 4 | Charles Blalock & Sons, Inc. | TDOT |
| 14 AUG 2026 | CN263060 | Counties Lawrence, Lewis, Perry, And Wayne | 969 | $15.00 | $20.00 | 3 | Superior Traffic Control, LLC | TDOT |
Filter this item by your own quantity, county and period, or check your price against it, in the TDOT explorer.
How these prices were read
TDOT Summary of Bids PDFs: every letting posted for February 2024 to October 2026, and nine lettings of 2018 to 2023 recovered from archived copies of the tn.gov files. Cost-plus-time bids, and bids that did not match their published total, are left out.
- Statistics leave out bids over three times the low bid, zero or negative prices and token prices under 5% of the median.
- Item codes and units are TDOT's own: this item is compared with TDOT contracts only.
- Prices are bid prices, not paid prices, and are not adjusted for inflation. Use them as a reference range, never as a quote.