Plastic pavement marking (turn lane arrow) unit price, Tennessee
Low bidders on TDOT contracts carried a median of $211.57 per EACH for item 716-02.06, plastic pavement marking (turn lane arrow), over the 24 months to 02 OCT 2026, across 294 low bids. Half of all 780 bids fell between $184.75 and $250.00.
- Owner
- Tennessee DOT
- Item
- 716-02.06
- Unit
- EACH
- Latest letting
- 02 OCT 2026
By year of letting
| Year | Contracts | Low bids | Low-bid median | All bids | Median, all bids |
|---|---|---|---|---|---|
| 2018 | 65 | 65 | $150.00 | 136 | $150.00 |
| 2020 | 38 | 38 | $155.50 | 90 | $157.25 |
| 2023 | 9 | 9 | $210.00 | 21 | $210.00 |
| 2024 | 117 | 117 | $205.00 | 309 | $205.00 |
| 2025 | 144 | 144 | $215.00 | 377 | $225.00 |
| 2026 | 111 | 111 | $211.20 | 293 | $210.00 |
Bid prices as published, not adjusted for inflation.
By county
| County | Low bids | Low-bid median | All bids | Median, all bids |
|---|---|---|---|---|
| Rutherford County | 12 | $194.50 | 51 | $200.00 |
| Williamson County | 10 | $245.19 | 46 | $247.50 |
| Davidson County | 14 | $220.00 | 45 | $200.00 |
| Knox County | 12 | $192.50 | 42 | $205.00 |
| Sumner County | 9 | $215.00 | 29 | $215.00 |
| Maury County | 7 | $225.00 | 29 | $225.00 |
| Shelby County | 10 | $311.77 | 27 | $306.00 |
| Hamilton County | 10 | $173.75 | 20 | $177.50 |
| Anderson County | 6 | $240.50 | 19 | $251.00 |
| Monroe County | 5 | $205.00 | 17 | $180.00 |
| Sullivan County | 8 | $164.65 | 17 | $165.00 |
| Bedford County | 3 | $183.75 | 13 | $200.00 |
Countys with at least three low bids, over the last 24 months.
By quantity
| Quantity (EACH) | Low bids | Low-bid median |
|---|---|---|
| 1 to 6 | 73 | $225.00 |
| 6 to 14 | 74 | $211.60 |
| 14 to 34 | 73 | $224.40 |
| 34 to 350 | 74 | $200.00 |
The low bids split into four bands of equal count by the quantity on the contract. Larger quantities usually carry lower unit prices.
Latest contracts with this item
| Let | Contract | County | Quantity | Low bidder's price | Median | Bids | Low bidder | Source |
|---|---|---|---|---|---|---|---|---|
| 02 OCT 2026 | CN261076 | Anderson County | 3 | $251.00 | $271.50 | 4 | Rogers Group, Inc. | TDOT |
| 02 OCT 2026 | CN261075 | Counties Cocke, Hawkins, Jefferson, Monroe, Scott, And Washington | 1 | $180.00 | $289.00 | 3 | Stansell Electric Company, Inc. | TDOT |
| 02 OCT 2026 | CN264057 | Hardin County | 8 | $250.00 | $273.00 | 5 | Delta Contracting Company, LLC | TDOT |
| 02 OCT 2026 | CN264061 | Henry And Stewart Counties | 12 | $185.00 | $185.00 | 3 | Delta Contracting Company, LLC | TDOT |
| 02 OCT 2026 | CN261064 | Sullivan County | 14 | $234.23 | $234.23 | 1 | Summers-Taylor, Inc. | TDOT |
| 14 AUG 2026 | CN261063 | Campbell County | 1 | $258.00 | $258.00 | 5 | Rogers Group, Inc. | TDOT |
| 14 AUG 2026 | CN262058 | Cumberland County | 3 | $194.25 | $199.62 | 6 | Charles Blalock & Sons, Inc. | TDOT |
| 14 AUG 2026 | CN262056 | Grundy County | 2 | $190.00 | $190.00 | 5 | Mack Construction, LLC | TDOT |
| 14 AUG 2026 | CN261061 | Knox County | 6 | $131.25 | $142.75 | 4 | Charles Blalock & Sons, Inc. | TDOT |
| 14 AUG 2026 | CN264052 | Tipton County | 13 | $300.00 | $300.00 | 2 | Delta Contracting Company, LLC | TDOT |
| 26 JUN 2026 | CN263048 | Bedford County | 3 | $160.00 | $200.00 | 4 | Hawkins Asphalt Paving, LLC | TDOT |
| 26 JUN 2026 | CN264041 | Chester County | 2 | $225.00 | $225.00 | 2 | Delta Contracting Company, LLC | TDOT |
| 26 JUN 2026 | CN263059 | Dickson And Hickman Counties | 4 | $200.00 | $236.00 | 3 | Jones Bros. Contractors, LLC | TDOT |
| 26 JUN 2026 | CN262047 | Fentress County | 11 | $237.60 | $231.30 | 2 | Rogers Group, Inc. | TDOT |
| 26 JUN 2026 | CN262054 | Franklin County | 15 | $240.75 | $240.75 | 1 | Tinsley Asphalt, LLC | TDOT |
Filter this item by your own quantity, county and period, or check your price against it, in the TDOT explorer.
How these prices were read
TDOT Summary of Bids PDFs: every letting posted for February 2024 to October 2026, and nine lettings of 2018 to 2023 recovered from archived copies of the tn.gov files. Cost-plus-time bids, and bids that did not match their published total, are left out.
- Statistics leave out bids over three times the low bid, zero or negative prices and token prices under 5% of the median.
- Item codes and units are TDOT's own: this item is compared with TDOT contracts only.
- Prices are bid prices, not paid prices, and are not adjusted for inflation. Use them as a reference range, never as a quote.
Your own bid history, read the same way