Additional lane closure item(type 21) unit price, Texas
Low bidders on TxDOT contracts carried a median of $60.00 per HR for item 790-7059, additional lane closure item(type 21), over the 24 months to 19 NOV 2026, across 59 low bids. Half of all 143 bids fell between $50.00 and $82.50.
- Owner
- Texas DOT
- Item
- 790-7059
- Unit
- HR
- Latest letting
- 05 NOV 2026
By year of letting
| Year | Contracts | Low bids | Low-bid median | All bids | Median, all bids |
|---|---|---|---|---|---|
| 2024 | 5 | 5 | $60.00 | 11 | $60.00 |
| 2025 | 25 | 24 | $52.50 | 53 | $60.00 |
| 2026 | 33 | 32 | $65.00 | 82 | $65.00 |
Bid prices as published, not adjusted for inflation.
By district
| District | Low bids | Low-bid median | All bids | Median, all bids |
|---|---|---|---|---|
| Lubbock District | 10 | $87.50 | 23 | $100.00 |
| Houston District | 5 | $50.00 | 19 | $55.00 |
| Dallas District | 6 | $76.25 | 16 | $75.00 |
| Tyler District | 5 | $52.00 | 16 | $60.00 |
| Lufkin District | 8 | $43.75 | 15 | $45.00 |
| Paris District | 5 | $50.00 | 14 | $50.00 |
| El Paso District | 4 | $67.00 | 8 | $87.00 |
| Abilene District | 4 | $51.00 | 8 | $51.00 |
| San Antonio District | 3 | $61.00 | 8 | $63.00 |
| Waco District | 3 | $60.00 | 7 | $60.00 |
| Odessa District | 3 | $150.00 | 3 | $150.00 |
Districts with at least three low bids, over the last 24 months.
By quantity
| Quantity (HR) | Low bids | Low-bid median |
|---|---|---|
| 5 to 75 | 14 | $77.50 |
| 100 to 741 | 15 | $50.00 |
| 750 to 3,000 | 15 | $60.00 |
| 3,125 to 12,800 | 15 | $52.00 |
The low bids split into four bands of equal count by the quantity on the contract. Larger quantities usually carry lower unit prices.
Latest contracts with this item
| Let | Contract | District | Quantity | Low bidder's price | Median | Estimate | Bids | Low bidder | Source |
|---|---|---|---|---|---|---|---|---|---|
| 05 NOV 2026 | A00224316 | Lubbock District | 75 | $135.00 | $120.00 | $125.00 | 3 | FC TRAFFIC CONTROL, LLC | TxDOT |
| 05 NOV 2026 | A00224318 | Lubbock District | 25 | n/a | $160.00 | $125.00 | 2 | FC TRAFFIC CONTROL, LLC | TxDOT |
| 04 NOV 2026 | A00223370 | Waco District | 3,000 | $60.00 | $67.50 | $67.50 | 2 | AWP SAFETY | TxDOT |
| 04 NOV 2026 | A00224031 | Waco District | 5,000 | $60.00 | $60.00 | $52.50 | 3 | AWP SAFETY | TxDOT |
| 04 NOV 2026 | A00224104 | Tyler District | 4,000 | $52.00 | $58.75 | $55.00 | 4 | HIGHWAY 19 CONSTRUCTION LLC | TxDOT |
| 03 NOV 2026 | A00223921 | Tyler District | 3,000 | $65.00 | $65.00 | $75.00 | 4 | HIGHWAY 19 CONSTRUCTION LLC | TxDOT |
| 03 NOV 2026 | A00224308 | San Antonio District | 4,500 | $65.00 | $65.00 | $75.00 | 4 | AUSTIN BARRICADE COMPANY, L.L.C. | TxDOT |
| 14 OCT 2026 | A00221875 | Dallas District | 650 | $77.50 | $77.50 | $50.00 | 3 | ROAD SOLUTIONS L.L.C. | TxDOT |
| 13 OCT 2026 | A00223813 | Tyler District | 500 | $45.00 | $55.00 | $55.00 | 3 | FLEX SUPPLY, LLC | TxDOT |
| 13 OCT 2026 | A00223818 | Tyler District | 100 | $45.00 | $55.00 | $55.00 | 3 | FLEX SUPPLY, LLC | TxDOT |
| 06 OCT 2026 | A00222877 | Tyler District | 7,500 | $75.00 | $65.00 | $55.00 | 2 | FC TRAFFIC CONTROL, LLC | TxDOT |
| 17 SEP 2026 | A00223663 | Paris District | 400 | $100.00 | $85.00 | $85.00 | 3 | FC TRAFFIC CONTROL, LLC | TxDOT |
| 09 SEP 2026 | A00221432 | Dallas District | 1,560 | $75.00 | $87.50 | $60.00 | 2 | AWP SAFETY | TxDOT |
| 09 SEP 2026 | A00221722 | Dallas District | 50 | $80.00 | $65.00 | $75.00 | 2 | AWP SAFETY | TxDOT |
| 08 SEP 2026 | A00218620 | Houston District | 5 | $75.00 | $75.00 | $30.00 | 2 | BLUE CHIP SERVICES, LLC | TxDOT |
Filter this item by your own quantity, district and period, or check your price against it, in the TxDOT explorer.
How these prices were read
TxDOT Bid Tabulations open-data export (data.texas.gov) from September 2024, read 21 November 2026, and TxDOT's legacy Tabulation of Bids pages for January 2020 to August 2024. The legacy pages are a large sample, not every contract: their file names were reused from year to year. Their district is the one TxDOT gives the county. Bids that did not match their published total are left out.
- Statistics leave out bids over three times the low bid, zero or negative prices and token prices under 5% of the median.
- Item codes and units are TxDOT's own: this item is compared with TxDOT contracts only.
- Prices are bid prices, not paid prices, and are not adjusted for inflation. Use them as a reference range, never as a quote.
Your own bid history, read the same way
Mirage deploys AI agents for heavy civil estimating teams: quantities from the plan set, specs and addenda read, and bid tabs compared, inside your systems and your rules.