D-gr hma ty b pg 64-22 (pickup) unit price, Texas

Low bidders on TxDOT contracts carried a median of $70.00 per TON for item 8011-7001, d-gr hma ty b pg 64-22 (pickup), over the 24 months to 19 NOV 2026, across 53 low bids. Half of all 150 bids fell between $65.07 and $82.26.

Owner
Texas DOT
Item
8011-7001
Unit
TON
Latest letting
20 AUG 2026
$70.00Low bidder's median, per TON
$70.00Median of all bids, per TON
53Contracts in the window
$73.16Engineer's estimate, median per TON

By year of letting

D-gr hma ty b pg 64-22 (pickup), TxDOT: unit prices by year
YearContractsLow bidsLow-bid medianAll bidsMedian, all bids
202444$107.507$90.00
20253232$69.6284$70.00
20262020$68.5663$70.24
D-gr hma ty b pg 64-22 (pickup), TxDOT: unit prices by year

Bid prices as published, not adjusted for inflation.

By district

D-gr hma ty b pg 64-22 (pickup), TxDOT: unit prices by district, last 24 months
DistrictLow bidsLow-bid medianAll bidsMedian, all bids
Waco District16$61.0055$65.07
Wichita Falls District16$69.5251$72.00
Fort Worth District4$69.0212$70.00
Corpus Christi District3$85.007$88.00
Paris District3$80.007$80.00
Lufkin District4$111.005$110.00
Beaumont District3$90.005$90.00
D-gr hma ty b pg 64-22 (pickup), TxDOT: unit prices by district, last 24 months

Districts with at least three low bids, over the last 24 months.

By quantity

D-gr hma ty b pg 64-22 (pickup), TxDOT: low bidder's median by quantity band
Quantity (TON)Low bidsLow-bid median
50 to 10013$72.00
100 to 25013$73.75
250 to 1,00013$68.79
1,000 to 3,00014$64.83
D-gr hma ty b pg 64-22 (pickup), TxDOT: low bidder's median by quantity band

The low bids split into four bands of equal count by the quantity on the contract. Larger quantities usually carry lower unit prices.

Latest contracts with this item

Latest TxDOT contracts carrying D-gr hma ty b pg 64-22 (pickup)
LetContractDistrictQuantityLow bidder's priceMedianEstimateBidsLow bidderSource
20 AUG 2026A00223409Paris District250$80.00$79.70$68.004RK HALL, LLCTxDOT
02 JUL 2026A00219895Waco District550$61.00$65.00$60.003BIG CREEK CONSTRUCTION, LTD.TxDOT
02 JUL 2026A00219896Waco District1,750$61.00$65.00$57.503BIG CREEK CONSTRUCTION, LTD.TxDOT
01 JUL 2026A00220051Waco District2,000$66.89$65.94$67.164TEXAS MATERIALS GROUP, INC.TxDOT
01 JUL 2026A00220053Waco District1,000$61.75$66.20$68.194BIG CREEK CONSTRUCTION, LTD.TxDOT
17 JUN 2026A00221758Wichita Falls District100$72.00$73.00$69.535JAGOE-PUBLIC COMPANYTxDOT
17 JUN 2026A00221759Wichita Falls District100$62.14$76.00$69.535OVERLAND MATERIALS & MANUFACTURING, INC.TxDOT
17 JUN 2026A00221760Wichita Falls District100$70.24$72.88$69.534ZACK BURKETT CO.TxDOT
17 JUN 2026A00221761Wichita Falls District100$73.75$73.00$69.535AUSTIN ASPHALT, INC.TxDOT
17 JUN 2026A00221762Wichita Falls District100$70.24$70.24$69.531ZACK BURKETT CO.TxDOT
17 JUN 2026A00221763Wichita Falls District100$77.59$89.34$69.532OVERLAND MATERIALS & MANUFACTURING, INC.TxDOT
17 JUN 2026A00221764Wichita Falls District100$62.90$72.00$69.533OVERLAND MATERIALS & MANUFACTURING, INC.TxDOT
12 MAY 2026A00218685Houston District200$95.00$102.50$90.002AMERICAN MATERIALS, INC.TxDOT
23 APR 2026A00220893Wichita Falls District100$70.24$73.87$70.532ZACK BURKETT CO.TxDOT
23 APR 2026A00220894Wichita Falls District100$70.24$70.24$70.531ZACK BURKETT CO.TxDOT
Latest TxDOT contracts carrying D-gr hma ty b pg 64-22 (pickup)

Filter this item by your own quantity, district and period, or check your price against it, in the TxDOT explorer.

How these prices were read

TxDOT Bid Tabulations open-data export (data.texas.gov) from September 2024, read 21 November 2026, and TxDOT's legacy Tabulation of Bids pages for January 2020 to August 2024. The legacy pages are a large sample, not every contract: their file names were reused from year to year. Their district is the one TxDOT gives the county. Bids that did not match their published total are left out.

  • Statistics leave out bids over three times the low bid, zero or negative prices and token prices under 5% of the median.
  • Item codes and units are TxDOT's own: this item is compared with TxDOT contracts only.
  • Prices are bid prices, not paid prices, and are not adjusted for inflation. Use them as a reference range, never as a quote.

Your own bid history, read the same way

Mirage deploys AI agents for heavy civil estimating teams: quantities from the plan set, specs and addenda read, and bid tabs compared, inside your systems and your rules.