D-gr hma ty b pg 64-22 (pickup) unit price, Texas
Low bidders on TxDOT contracts carried a median of $70.00 per TON for item 8011-7001, d-gr hma ty b pg 64-22 (pickup), over the 24 months to 19 NOV 2026, across 53 low bids. Half of all 150 bids fell between $65.07 and $82.26.
- Owner
- Texas DOT
- Item
- 8011-7001
- Unit
- TON
- Latest letting
- 20 AUG 2026
By year of letting
| Year | Contracts | Low bids | Low-bid median | All bids | Median, all bids |
|---|---|---|---|---|---|
| 2024 | 4 | 4 | $107.50 | 7 | $90.00 |
| 2025 | 32 | 32 | $69.62 | 84 | $70.00 |
| 2026 | 20 | 20 | $68.56 | 63 | $70.24 |
Bid prices as published, not adjusted for inflation.
By district
| District | Low bids | Low-bid median | All bids | Median, all bids |
|---|---|---|---|---|
| Waco District | 16 | $61.00 | 55 | $65.07 |
| Wichita Falls District | 16 | $69.52 | 51 | $72.00 |
| Fort Worth District | 4 | $69.02 | 12 | $70.00 |
| Corpus Christi District | 3 | $85.00 | 7 | $88.00 |
| Paris District | 3 | $80.00 | 7 | $80.00 |
| Lufkin District | 4 | $111.00 | 5 | $110.00 |
| Beaumont District | 3 | $90.00 | 5 | $90.00 |
Districts with at least three low bids, over the last 24 months.
By quantity
| Quantity (TON) | Low bids | Low-bid median |
|---|---|---|
| 50 to 100 | 13 | $72.00 |
| 100 to 250 | 13 | $73.75 |
| 250 to 1,000 | 13 | $68.79 |
| 1,000 to 3,000 | 14 | $64.83 |
The low bids split into four bands of equal count by the quantity on the contract. Larger quantities usually carry lower unit prices.
Latest contracts with this item
| Let | Contract | District | Quantity | Low bidder's price | Median | Estimate | Bids | Low bidder | Source |
|---|---|---|---|---|---|---|---|---|---|
| 20 AUG 2026 | A00223409 | Paris District | 250 | $80.00 | $79.70 | $68.00 | 4 | RK HALL, LLC | TxDOT |
| 02 JUL 2026 | A00219895 | Waco District | 550 | $61.00 | $65.00 | $60.00 | 3 | BIG CREEK CONSTRUCTION, LTD. | TxDOT |
| 02 JUL 2026 | A00219896 | Waco District | 1,750 | $61.00 | $65.00 | $57.50 | 3 | BIG CREEK CONSTRUCTION, LTD. | TxDOT |
| 01 JUL 2026 | A00220051 | Waco District | 2,000 | $66.89 | $65.94 | $67.16 | 4 | TEXAS MATERIALS GROUP, INC. | TxDOT |
| 01 JUL 2026 | A00220053 | Waco District | 1,000 | $61.75 | $66.20 | $68.19 | 4 | BIG CREEK CONSTRUCTION, LTD. | TxDOT |
| 17 JUN 2026 | A00221758 | Wichita Falls District | 100 | $72.00 | $73.00 | $69.53 | 5 | JAGOE-PUBLIC COMPANY | TxDOT |
| 17 JUN 2026 | A00221759 | Wichita Falls District | 100 | $62.14 | $76.00 | $69.53 | 5 | OVERLAND MATERIALS & MANUFACTURING, INC. | TxDOT |
| 17 JUN 2026 | A00221760 | Wichita Falls District | 100 | $70.24 | $72.88 | $69.53 | 4 | ZACK BURKETT CO. | TxDOT |
| 17 JUN 2026 | A00221761 | Wichita Falls District | 100 | $73.75 | $73.00 | $69.53 | 5 | AUSTIN ASPHALT, INC. | TxDOT |
| 17 JUN 2026 | A00221762 | Wichita Falls District | 100 | $70.24 | $70.24 | $69.53 | 1 | ZACK BURKETT CO. | TxDOT |
| 17 JUN 2026 | A00221763 | Wichita Falls District | 100 | $77.59 | $89.34 | $69.53 | 2 | OVERLAND MATERIALS & MANUFACTURING, INC. | TxDOT |
| 17 JUN 2026 | A00221764 | Wichita Falls District | 100 | $62.90 | $72.00 | $69.53 | 3 | OVERLAND MATERIALS & MANUFACTURING, INC. | TxDOT |
| 12 MAY 2026 | A00218685 | Houston District | 200 | $95.00 | $102.50 | $90.00 | 2 | AMERICAN MATERIALS, INC. | TxDOT |
| 23 APR 2026 | A00220893 | Wichita Falls District | 100 | $70.24 | $73.87 | $70.53 | 2 | ZACK BURKETT CO. | TxDOT |
| 23 APR 2026 | A00220894 | Wichita Falls District | 100 | $70.24 | $70.24 | $70.53 | 1 | ZACK BURKETT CO. | TxDOT |
Filter this item by your own quantity, district and period, or check your price against it, in the TxDOT explorer.
How these prices were read
TxDOT Bid Tabulations open-data export (data.texas.gov) from September 2024, read 21 November 2026, and TxDOT's legacy Tabulation of Bids pages for January 2020 to August 2024. The legacy pages are a large sample, not every contract: their file names were reused from year to year. Their district is the one TxDOT gives the county. Bids that did not match their published total are left out.
- Statistics leave out bids over three times the low bid, zero or negative prices and token prices under 5% of the median.
- Item codes and units are TxDOT's own: this item is compared with TxDOT contracts only.
- Prices are bid prices, not paid prices, and are not adjusted for inflation. Use them as a reference range, never as a quote.
Your own bid history, read the same way