Low bidders on TxDOT contracts carried a median of $85.00 per TON for item 8011-7055, d-gr hma ty d pg 64-22 (pickup), over the 24 months to 19 NOV 2026, across 145 low bids. Half of all 351 bids fell between $76.00 and $100.00.
- Owner
- Texas DOT
- Item
- 8011-7055
- Unit
- TON
- Latest letting
- 18 NOV 2026
By year of letting
| Year | Contracts | Low bids | Low-bid median | All bids | Median, all bids |
|---|---|---|---|---|---|
| 2024 | 8 | 8 | $104.50 | 13 | $109.00 |
| 2025 | 77 | 77 | $88.00 | 176 | $85.00 |
| 2026 | 65 | 65 | $84.42 | 170 | $86.12 |
Bid prices as published, not adjusted for inflation.
By district
| District | Low bids | Low-bid median | All bids | Median, all bids |
|---|---|---|---|---|
| Bryan District | 19 | $75.75 | 55 | $82.00 |
| Waco District | 16 | $67.00 | 55 | $73.15 |
| Wichita Falls District | 16 | $74.97 | 51 | $76.64 |
| Paris District | 19 | $82.00 | 50 | $88.50 |
| Corpus Christi District | 15 | $87.00 | 33 | $95.00 |
| Atlanta District | 18 | $115.90 | 30 | $115.45 |
| Fort Worth District | 5 | $80.00 | 15 | $85.45 |
| Dallas District | 6 | $89.00 | 13 | $90.00 |
| Amarillo District | 7 | $115.00 | 11 | $115.00 |
| Lufkin District | 8 | $115.00 | 11 | $115.00 |
| Odessa District | 6 | $121.50 | 8 | $130.00 |
| Beaumont District | 3 | $105.00 | 5 | $105.00 |
Districts with at least three low bids, over the last 24 months.
By quantity
| Quantity (TON) | Low bids | Low-bid median |
|---|---|---|
| 50 to 400 | 36 | $75.88 |
| 400 to 1,000 | 36 | $90.00 |
| 1,000 to 1,500 | 36 | $114.35 |
| 1,500 to 5,500 | 37 | $77.18 |
The low bids split into four bands of equal count by the quantity on the contract. Larger quantities usually carry lower unit prices.
Latest contracts with this item
| Let | Contract | District | Quantity | Low bidder's price | Median | Estimate | Bids | Low bidder | Source |
|---|---|---|---|---|---|---|---|---|---|
| 18 NOV 2026 | A00224407 | Bryan District | 2,000 | $75.00 | $76.00 | $90.00 | 3 | BIG CREEK CONSTRUCTION, LTD. | TxDOT |
| 17 NOV 2026 | A00223978 | Corpus Christi District | 1,000 | $85.00 | $85.50 | $95.00 | 4 | CK NEWBERRY, LLC | TxDOT |
| 17 NOV 2026 | A00223979 | Corpus Christi District | 2,000 | $85.00 | $92.00 | $90.00 | 3 | CK NEWBERRY, LLC | TxDOT |
| 17 NOV 2026 | A00224405 | Bryan District | 400 | $76.00 | $87.75 | $90.00 | 3 | KNIFE RIVER CORPORATION - SOUTH | TxDOT |
| 17 NOV 2026 | A00224406 | Bryan District | 2,000 | $75.00 | $82.50 | $90.00 | 3 | BIG CREEK CONSTRUCTION, LTD. | TxDOT |
| 12 NOV 2026 | A00223366 | Dallas District | 500 | $86.00 | $91.25 | $94.35 | 4 | AUSTIN ASPHALT, INC. | TxDOT |
| 22 OCT 2026 | A00224074 | Atlanta District | 1,100 | $118.90 | $121.95 | $115.90 | 2 | LONGVIEW ASPHALT, INC. | TxDOT |
| 22 OCT 2026 | A00224075 | Atlanta District | 1,100 | $90.00 | $92.50 | $115.00 | 2 | C-RAE MATERIALS LLC | TxDOT |
| 22 OCT 2026 | A00224076 | Atlanta District | 1,100 | $118.90 | $118.90 | $114.00 | 1 | LONGVIEW ASPHALT, INC. | TxDOT |
| 22 OCT 2026 | A00224077 | Atlanta District | 1,100 | $118.90 | $118.90 | $115.90 | 1 | LONGVIEW ASPHALT, INC. | TxDOT |
| 22 OCT 2026 | A00224078 | Atlanta District | 1,100 | $90.00 | $91.50 | $119.00 | 2 | C-RAE MATERIALS LLC | TxDOT |
| 22 OCT 2026 | A00224079 | Atlanta District | 1,100 | $118.90 | $118.90 | $115.90 | 1 | LONGVIEW ASPHALT, INC. | TxDOT |
| 22 OCT 2026 | A00224080 | Atlanta District | 1,100 | $90.00 | $92.50 | $114.00 | 2 | C-RAE MATERIALS LLC | TxDOT |
| 22 OCT 2026 | A00224081 | Atlanta District | 1,100 | $90.00 | $91.50 | $118.00 | 2 | C-RAE MATERIALS LLC | TxDOT |
| 22 OCT 2026 | A00224082 | Atlanta District | 1,100 | $90.00 | $91.50 | $118.00 | 2 | C-RAE MATERIALS LLC | TxDOT |
Filter this item by your own quantity, district and period, or check your price against it, in the TxDOT explorer.
How these prices were read
TxDOT Bid Tabulations open-data export (data.texas.gov) from September 2024, read 21 November 2026, and TxDOT's legacy Tabulation of Bids pages for January 2020 to August 2024. The legacy pages are a large sample, not every contract: their file names were reused from year to year. Their district is the one TxDOT gives the county. Bids that did not match their published total are left out.
- Statistics leave out bids over three times the low bid, zero or negative prices and token prices under 5% of the median.
- Item codes and units are TxDOT's own: this item is compared with TxDOT contracts only.
- Prices are bid prices, not paid prices, and are not adjusted for inflation. Use them as a reference range, never as a quote.