Low bidders on TxDOT contracts carried a median of $806.63 per CY for item 422-7013, approach slab, over the 24 months to 19 NOV 2026, across 103 low bids. Half of all 737 bids fell between $710.00 and $1,000.00.

Owner
Texas DOT
Item
422-7013
Unit
CY
Latest letting
04 NOV 2026
$806.63Low bidder's median, per CY
$850.00Median of all bids, per CY
103Contracts in the window
$810.00Engineer's estimate, median per CY

By year of letting

Approach slab, TxDOT: unit prices by year
YearContractsLow bidsLow-bid medianAll bidsMedian, all bids
202433$750.0019$771.50
20254747$870.00312$880.03
20265656$800.00425$840.00
Approach slab, TxDOT: unit prices by year

Bid prices as published, not adjusted for inflation.

By district

Approach slab, TxDOT: unit prices by district, last 24 months
DistrictLow bidsLow-bid medianAll bidsMedian, all bids
Corpus Christi District9$750.0073$875.00
Houston District8$752.6669$800.00
San Antonio District8$725.0052$733.33
Tyler District7$755.0052$790.00
Austin District6$769.8249$733.00
Fort Worth District6$812.5047$850.00
Bryan District5$875.0045$900.00
Amarillo District8$909.5544$1,080.55
Paris District5$795.0044$800.00
Lufkin District6$815.0042$815.00
Laredo District5$927.6833$905.00
Beaumont District5$840.0024$831.62
Approach slab, TxDOT: unit prices by district, last 24 months

Districts with at least three low bids, over the last 24 months.

By quantity

Approach slab, TxDOT: low bidder's median by quantity band
Quantity (CY)Low bidsLow-bid median
8.40 to 53.4025$840.00
56 to 9226$934.50
92.20 to 175.3026$807.50
208 to 1,779.7026$716.50
Approach slab, TxDOT: low bidder's median by quantity band

The low bids split into four bands of equal count by the quantity on the contract. Larger quantities usually carry lower unit prices.

Latest contracts with this item

Latest TxDOT contracts carrying Approach slab
LetContractDistrictQuantityLow bidder's priceMedianEstimateBidsLow bidderSource
04 NOV 2026A00124162Bryan District405$648.00$811.00$800.0012FLUOR ENTERPRISES, INC.TxDOT
04 NOV 2026A00209149Laredo District108$901.17$901.17$900.007STX CIVILTxDOT
03 NOV 2026A00184974Austin District1,185.90$825.57$850.68$806.006AUSTIN BRIDGE & ROAD SERVICES, LPTxDOT
07 OCT 2026A00132124Lufkin District314.40$830.00$800.00$750.007LONGVIEW BRIDGE AND ROAD, LTD.TxDOT
06 OCT 2026A00134683Houston District96.40$800.00$800.00$660.529GARRET SHIELDS INFRASTRUCTURETxDOT
03 SEP 2026A00184830Amarillo District156$1,500.00$1,013.90$900.007GILVIN-TERRILL, LTD.TxDOT
03 SEP 2026A00139727Paris District61$950.00$800.00$600.008LONGVIEW BRIDGE AND ROAD, LTD.TxDOT
03 SEP 2026A00207389Childress District61.20$1,005.00$1,005.00$850.007COPPELL CONSTRUCTION CO., INC.TxDOT
02 SEP 2026A00192185Houston District114.90$800.00$758.00$1,000.0011R CONSTRUCTION CIVIL, LLCTxDOT
02 SEP 2026A00195348Paris District56$700.00$800.00$800.007HIGHWAY 19 CONSTRUCTION LLCTxDOT
02 SEP 2026A00184856San Antonio District51.40$800.00$725.63$500.008DELGADO'S CONTRACTORS, LLCTxDOT
06 AUG 2026A00192187Beaumont District41.20$650.00$773.89$800.006CASTILLO ARANDA LLCTxDOT
06 AUG 2026A00119935Laredo District988$927.68$889.27$650.004PULICE CONSTRUCTION, INC.TxDOT
06 AUG 2026A00136986San Antonio District112.30$650.00$678.62$600.008HUNTER INDUSTRIES, LTD.TxDOT
05 AUG 2026A00128458Amarillo District170$860.00$916.40$925.004J. LEE MILLIGAN, INC.TxDOT
Latest TxDOT contracts carrying Approach slab

Filter this item by your own quantity, district and period, or check your price against it, in the TxDOT explorer.

How these prices were read

TxDOT Bid Tabulations open-data export (data.texas.gov) from September 2024, read 21 November 2026, and TxDOT's legacy Tabulation of Bids pages for January 2020 to August 2024. The legacy pages are a large sample, not every contract: their file names were reused from year to year. Their district is the one TxDOT gives the county. Bids that did not match their published total are left out.

  • Statistics leave out bids over three times the low bid, zero or negative prices and token prices under 5% of the median.
  • Item codes and units are TxDOT's own: this item is compared with TxDOT contracts only.
  • Prices are bid prices, not paid prices, and are not adjusted for inflation. Use them as a reference range, never as a quote.

Your own bid history, read the same way

Mirage deploys AI agents for heavy civil estimating teams: quantities from the plan set, specs and addenda read, and bid tabs compared, inside your systems and your rules.

We use your email to reply to you and, now and then, to tell you about Mirage. You can opt out at any time. Privacy policy