Approach slab (hpc) unit price, Texas
Low bidders on TxDOT contracts carried a median of $825.00 per CY for item 422-7014, approach slab (hpc), over the 24 months to 19 NOV 2026, across 48 low bids. Half of all 316 bids fell between $700.00 and $1,037.25.
- Owner
- Texas DOT
- Item
- 422-7014
- Unit
- CY
- Latest letting
- 04 NOV 2026
By year of letting
| Year | Contracts | Low bids | Low-bid median | All bids | Median, all bids |
|---|---|---|---|---|---|
| 2024 | 2 | 2 | $656.83 | 10 | $896.50 |
| 2025 | 26 | 25 | $850.00 | 169 | $872.00 |
| 2026 | 22 | 22 | $800.00 | 143 | $825.00 |
Bid prices as published, not adjusted for inflation.
By district
| District | Low bids | Low-bid median | All bids | Median, all bids |
|---|---|---|---|---|
| Dallas District | 17 | $750.00 | 138 | $800.00 |
| Fort Worth District | 12 | $800.00 | 82 | $855.50 |
| Abilene District | 4 | $950.00 | 29 | $1,000.00 |
| Odessa District | 6 | $878.75 | 23 | $1,000.00 |
| El Paso District | 3 | $525.00 | 16 | $675.00 |
Districts with at least three low bids, over the last 24 months.
By quantity
| Quantity (CY) | Low bids | Low-bid median |
|---|---|---|
| 5 to 82 | 12 | $855.00 |
| 82 to 122 | 12 | $890.00 |
| 124.60 to 324.70 | 12 | $878.75 |
| 377 to 1,619 | 12 | $634.25 |
The low bids split into four bands of equal count by the quantity on the contract. Larger quantities usually carry lower unit prices.
Latest contracts with this item
| Let | Contract | District | Quantity | Low bidder's price | Median | Estimate | Bids | Low bidder | Source |
|---|---|---|---|---|---|---|---|---|---|
| 04 NOV 2026 | A00212892 | Dallas District | 1,213 | $675.00 | $640.33 | $700.00 | 6 | INDUS ROAD & BRIDGE, INC. | TxDOT |
| 07 OCT 2026 | A00191892 | Odessa District | 124.60 | $1,148.00 | $1,200.00 | $935.00 | 7 | RELMCO, INC. | TxDOT |
| 06 AUG 2026 | A00199843 | Odessa District | 91.50 | $850.00 | $1,000.00 | $1,075.00 | 5 | DAN WILLIAMS COMPANY | TxDOT |
| 06 AUG 2026 | A00214454 | Fort Worth District | 38.50 | $1,000.00 | $1,000.00 | $810.00 | 8 | HODGES AND SON CONSTRUCTION COMPANY, INC. | TxDOT |
| 06 AUG 2026 | A00193283 | Fort Worth District | 60 | $678.00 | $939.00 | $780.00 | 2 | RAGLE CONSTRUCTION, INC. | TxDOT |
| 05 AUG 2026 | A00007222 | Fort Worth District | 510.80 | $680.00 | $700.00 | n/a | 11 | INDUS ROAD & BRIDGE, INC. | TxDOT |
| 05 AUG 2026 | A00065091 | Fort Worth District | 82 | $800.00 | $825.00 | $785.00 | 10 | HODGES AND SON CONSTRUCTION COMPANY, INC. | TxDOT |
| 02 JUL 2026 | A00064472 | Fort Worth District | 98.20 | $650.00 | $650.00 | $700.00 | 1 | CASTILLO ARANDA LLC | TxDOT |
| 01 JUL 2026 | A00080576 | Odessa District | 122 | $731.00 | $731.00 | $935.00 | 5 | JONES BROS. DIRT & PAVING CONTRACTORS, INC. | TxDOT |
| 01 JUL 2026 | A00008199 | Fort Worth District | 552.30 | $765.00 | $728.95 | $800.00 | 6 | INDUS ROAD & BRIDGE, INC. | TxDOT |
| 03 JUN 2026 | A00185405 | Dallas District | 130.40 | $926.50 | $926.50 | $750.00 | 5 | TUCAN CONTRACTING, LLC | TxDOT |
| 03 JUN 2026 | A00132662 | Abilene District | 1,254.10 | $1,000.00 | $1,000.00 | $800.00 | 1 | FNF CONSTRUCTION, INC. | TxDOT |
| 03 JUN 2026 | A00209326 | Dallas District | 194 | $1,787.69 | $1,890.90 | $1,200.00 | 7 | ALTUS CONSTRUCTION LLC | TxDOT |
| 03 JUN 2026 | A00063871 | El Paso District | 712.60 | $525.00 | $562.50 | $800.00 | 4 | JORDAN FOSTER CONSTRUCTION, LLC | TxDOT |
| 07 MAY 2026 | A00132253 | Corpus Christi District | 101.20 | $1,400.00 | $1,375.00 | $1,300.00 | 4 | RUSSELL MARINE, LLC | TxDOT |
Filter this item by your own quantity, district and period, or check your price against it, in the TxDOT explorer.
How these prices were read
TxDOT Bid Tabulations open-data export (data.texas.gov) from September 2024, read 21 November 2026, and TxDOT's legacy Tabulation of Bids pages for January 2020 to August 2024. The legacy pages are a large sample, not every contract: their file names were reused from year to year. Their district is the one TxDOT gives the county. Bids that did not match their published total are left out.
- Statistics leave out bids over three times the low bid, zero or negative prices and token prices under 5% of the median.
- Item codes and units are TxDOT's own: this item is compared with TxDOT contracts only.
- Prices are bid prices, not paid prices, and are not adjusted for inflation. Use them as a reference range, never as a quote.
Your own bid history, read the same way
Mirage deploys AI agents for heavy civil estimating teams: quantities from the plan set, specs and addenda read, and bid tabs compared, inside your systems and your rules.