Backfill (ty b) unit price, Texas
Low bidders on TxDOT contracts carried a median of $200.00 per STA for item 134-7002, backfill (ty b), over the 24 months to 19 NOV 2026, across 107 low bids. Half of all 508 bids fell between $153.87 and $370.88.
- Owner
- Texas DOT
- Item
- 134-7002
- Unit
- STA
- Latest letting
- 07 OCT 2026
By year of letting
| Year | Contracts | Low bids | Low-bid median | All bids | Median, all bids |
|---|---|---|---|---|---|
| 2024 | 5 | 5 | $200.00 | 24 | $300.00 |
| 2025 | 56 | 56 | $203.00 | 252 | $250.00 |
| 2026 | 49 | 49 | $200.00 | 244 | $247.50 |
Bid prices as published, not adjusted for inflation.
By district
| District | Low bids | Low-bid median | All bids | Median, all bids |
|---|---|---|---|---|
| Lubbock District | 14 | $172.50 | 70 | $154.66 |
| Lufkin District | 8 | $201.99 | 49 | $260.00 |
| Atlanta District | 7 | $200.00 | 44 | $255.00 |
| Wichita Falls District | 10 | $180.00 | 44 | $234.58 |
| Paris District | 10 | $198.38 | 43 | $250.00 |
| Abilene District | 7 | $216.00 | 40 | $220.00 |
| Fort Worth District | 6 | $342.50 | 31 | $438.00 |
| Odessa District | 11 | $300.00 | 31 | $281.00 |
| Austin District | 5 | $146.00 | 23 | $148.40 |
| Beaumont District | 4 | $402.50 | 23 | $342.00 |
| Laredo District | 5 | $264.60 | 21 | $263.00 |
| Waco District | 4 | $237.50 | 18 | $241.58 |
Districts with at least three low bids, over the last 24 months.
By quantity
| Quantity (STA) | Low bids | Low-bid median |
|---|---|---|
| 1 to 76 | 26 | $406.94 |
| 78 to 216 | 27 | $200.00 |
| 225.69 to 379.15 | 27 | $188.00 |
| 400 to 1,604 | 27 | $160.00 |
The low bids split into four bands of equal count by the quantity on the contract. Larger quantities usually carry lower unit prices.
Latest contracts with this item
| Let | Contract | District | Quantity | Low bidder's price | Median | Estimate | Bids | Low bidder | Source |
|---|---|---|---|---|---|---|---|---|---|
| 07 OCT 2026 | A00132124 | Lufkin District | 305.45 | $325.00 | $325.00 | $200.00 | 7 | LONGVIEW BRIDGE AND ROAD, LTD. | TxDOT |
| 07 OCT 2026 | A00187431 | Paris District | 320.20 | $200.00 | $220.00 | $125.00 | 6 | A. K. GILLIS & SONS, LLC | TxDOT |
| 06 OCT 2026 | A00195499 | Wichita Falls District | 235 | $140.00 | $290.00 | $215.00 | 5 | OVERLAND CORPORATION | TxDOT |
| 06 OCT 2026 | A00207050 | Lubbock District | 379.15 | $22.00 | $69.03 | $200.00 | 6 | GRATIOT CONSTRUCTION, LTD. | TxDOT |
| 03 SEP 2026 | A00184246 | Lubbock District | 642.95 | $100.00 | $100.00 | $85.00 | 5 | GRATIOT CONSTRUCTION, LTD. | TxDOT |
| 06 AUG 2026 | A00199843 | Odessa District | 313.30 | $75.00 | $150.00 | $400.00 | 5 | DAN WILLIAMS COMPANY | TxDOT |
| 06 AUG 2026 | A00209034 | Corpus Christi District | 51 | $704.54 | $359.50 | $163.00 | 8 | STX CIVIL | TxDOT |
| 06 AUG 2026 | A00195300 | Wichita Falls District | 165 | $170.00 | $220.00 | $212.00 | 5 | A. L. HELMCAMP, INC. | TxDOT |
| 06 AUG 2026 | A00120927 | Lubbock District | 23 | $350.00 | $365.00 | n/a | 5 | A. L. HELMCAMP, INC. | TxDOT |
| 06 AUG 2026 | A00193246 | San Angelo District | 23 | $316.30 | $406.65 | $300.00 | 2 | REECE ALBERT, INC. | TxDOT |
| 05 AUG 2026 | A00196231 | Atlanta District | 364 | $200.00 | $200.00 | $210.00 | 7 | H. H. HOWARD & SONS, INC. | TxDOT |
| 05 AUG 2026 | A00198027 | Laredo District | 147 | $500.00 | $210.00 | $200.00 | 3 | LUCANIA CONTRACTORS LLC | TxDOT |
| 02 JUL 2026 | A00221480 | Paris District | 663.52 | $24.00 | $27.00 | $60.00 | 4 | D. L. LENNON INCORPORATED - CONTRACTOR | TxDOT |
| 02 JUL 2026 | A00064356 | Lufkin District | 369 | $200.00 | $280.00 | $200.00 | 6 | POSILLICO CIVIL, INC. | TxDOT |
| 01 JUL 2026 | A00206568 | Lufkin District | 134.45 | $195.00 | $191.70 | $200.00 | 5 | L. S. EQUIPMENT CO., INC. | TxDOT |
Filter this item by your own quantity, district and period, or check your price against it, in the TxDOT explorer.
How these prices were read
TxDOT Bid Tabulations open-data export (data.texas.gov) from September 2024, read 21 November 2026, and TxDOT's legacy Tabulation of Bids pages for January 2020 to August 2024. The legacy pages are a large sample, not every contract: their file names were reused from year to year. Their district is the one TxDOT gives the county. Bids that did not match their published total are left out.
- Statistics leave out bids over three times the low bid, zero or negative prices and token prices under 5% of the median.
- Item codes and units are TxDOT's own: this item is compared with TxDOT contracts only.
- Prices are bid prices, not paid prices, and are not adjusted for inflation. Use them as a reference range, never as a quote.
Your own bid history, read the same way
Mirage deploys AI agents for heavy civil estimating teams: quantities from the plan set, specs and addenda read, and bid tabs compared, inside your systems and your rules.