Embankment (final) (dens cont) (ty C1) unit price, Texas
Low bidders on TxDOT contracts carried a median of $14.32 per CY for item 1326025, embankment (final) (dens cont) (ty c1), from 07 MAY 2020 to 10 JUL 2024, across 50 low bids. Half of all 264 bids fell between $10.35 and $30.00.
- Owner
- Texas DOT
- Item
- 1326025
- Unit
- CY
- Latest letting
- 10 JUL 2024
By year of letting
| Year | Contracts | Low bids | Low-bid median | All bids | Median, all bids |
|---|---|---|---|---|---|
| 2020 | 5 | 5 | $9.10 | 55 | $10.00 |
| 2021 | 10 | 10 | $12.73 | 57 | $15.35 |
| 2022 | 12 | 12 | $14.32 | 59 | $14.39 |
| 2023 | 12 | 12 | $36.83 | 39 | $40.00 |
| 2024 | 11 | 11 | $13.19 | 54 | $22.00 |
Bid prices as published, not adjusted for inflation.
By district
| District | Low bids | Low-bid median | All bids | Median, all bids |
|---|---|---|---|---|
| Dallas District | 33 | $13.87 | 196 | $15.00 |
| Waco District | 4 | $18.50 | 16 | $19.82 |
Districts with at least three low bids, over all lettings.
By quantity
| Quantity (CY) | Low bids | Low-bid median |
|---|---|---|
| 245 to 8,007 | 12 | $35.00 |
| 8,007 to 45,892 | 13 | $14.25 |
| 46,774 to 180,653 | 12 | $8.79 |
| 217,311 to 1,143,237 | 13 | $11.79 |
The low bids split into four bands of equal count by the quantity on the contract. Larger quantities usually carry lower unit prices.
Latest contracts with this item
| Let | Contract | District | Quantity | Low bidder's price | Median | Estimate | Bids | Low bidder | Source |
|---|---|---|---|---|---|---|---|---|---|
| 10 JUL 2024 | 07243201 | Dallas District | 501,648 | $13.19 | $15.04 | $18.00 | 2 | AUSTIN BRIDGE & ROAD SERVICES, LP | TxDOT |
| 10 JUL 2024 | 07243207 | Dallas District | 31,077 | $7.00 | $24.52 | $25.00 | 6 | HARPER BROTHERS CONSTRUCTION LLC | TxDOT |
| 02 MAY 2024 | 05243003 | Waco District | 299,871 | $17.00 | $19.90 | $10.00 | 4 | BIG CREEK CONSTRUCTION, LTD. | TxDOT |
| 04 APR 2024 | 04243001 | Dallas District | 1,143,237 | $1.63 | $6.31 | $15.00 | 2 | SEMA CONSTRUCTION, INC. | TxDOT |
| 06 MAR 2024 | 03243210 | Dallas District | 1,219.80 | $40.00 | $40.00 | $50.00 | 5 | HODGES AND SON CONSTRUCTION COMPANY, INC. | TxDOT |
| 05 MAR 2024 | 03243004 | Dallas District | 45,892 | $10.00 | $19.00 | $24.00 | 7 | INDUS ROAD & BRIDGE, INC. | TxDOT |
| 05 MAR 2024 | 03243017 | San Antonio District | 2,616 | $55.00 | $41.50 | $16.00 | 6 | J3 COMPANY, LLC | TxDOT |
| 02 FEB 2024 | 02243201 | Waco District | 718,050 | $22.00 | $22.00 | $23.00 | 3 | JAMES CONSTRUCTION GROUP, LLC | TxDOT |
| 02 FEB 2024 | 02243217 | Dallas District | 9,659 | $30.00 | $29.55 | $35.00 | 10 | HIGHWAY 19 CONSTRUCTION LLC | TxDOT |
| 01 FEB 2024 | 02243001 | Dallas District | 180,653 | $8.28 | $19.10 | $15.00 | 3 | FLATIRON CONSTRUCTORS, INC. | TxDOT |
| 04 JAN 2024 | 01243001 | Dallas District | 345,820 | $11.00 | $10.60 | $18.00 | 6 | MARIO SINACOLA & SONS EXCAVATING, INC. | TxDOT |
| 06 DEC 2023 | 12233201 | Yoakum District | 89,813 | $125.00 | $100.00 | $17.50 | 3 | WILLIAMS BROTHERS CONSTRUCTION CO., INC. | TxDOT |
| 07 SEP 2023 | 09233208 | Waco District | 48,062.83 | $20.00 | $19.50 | $13.00 | 4 | BIG CREEK CONSTRUCTION, LTD. | TxDOT |
| 03 AUG 2023 | 08233201 | Paris District | 373,706 | $11.79 | $20.50 | $13.00 | 4 | SEMA CONSTRUCTION, INC. | TxDOT |
| 03 AUG 2023 | 08233274 | Tyler District | 44,690 | $50.00 | $50.00 | $15.00 | 3 | EAST TEXAS BRIDGE, INC. | TxDOT |
Filter this item by your own quantity, district and period, or check your price against it, in the TxDOT explorer.
How these prices were read
TxDOT Bid Tabulations open-data export (data.texas.gov) from September 2024, read 21 November 2026, and TxDOT's legacy Tabulation of Bids pages for January 2020 to August 2024. The legacy pages are a large sample, not every contract: their file names were reused from year to year. Their district is the one TxDOT gives the county. Bids that did not match their published total are left out.
- Statistics leave out bids over three times the low bid, zero or negative prices and token prices under 5% of the median.
- Item codes and units are TxDOT's own: this item is compared with TxDOT contracts only.
- Prices are bid prices, not paid prices, and are not adjusted for inflation. Use them as a reference range, never as a quote.