Cctv field equip (digital) (instl only) unit price, Texas

Low bidders on TxDOT contracts carried a median of $1,995.00 per EACH for item 60106011, cctv field equip (digital) (instl only), from 06 FEB 2020 to 09 JUL 2024, across 56 low bids. Half of all 178 bids fell between $1,200.00 and $5,300.00.

Owner
Texas DOT
Item
60106011
Unit
EACH
Latest letting
09 JUL 2024
$1,995.00Low bidder's median, per EACH
$2,167.23Median of all bids, per EACH
56Contracts in the window
$2,500.00Engineer's estimate, median per EACH

By year of letting

Cctv field equip (digital) (instl only), TxDOT: unit prices by year
YearContractsLow bidsLow-bid medianAll bidsMedian, all bids
202088$1,422.9727$1,540.00
20211010$4,047.5046$4,680.15
202277$1,250.0020$1,525.06
20231111$2,040.0028$2,040.00
20242020$2,406.5057$2,313.00
Cctv field equip (digital) (instl only), TxDOT: unit prices by year

Bid prices as published, not adjusted for inflation.

By district

Cctv field equip (digital) (instl only), TxDOT: unit prices by district, all lettings
DistrictLow bidsLow-bid medianAll bidsMedian, all bids
El Paso District26$2,060.0068$2,306.50
San Antonio District8$1,200.0026$1,200.00
Odessa District6$7,200.0026$7,750.00
Pharr District3$1,532.9412$1,025.00
Dallas District3$1,250.009$2,395.20
Cctv field equip (digital) (instl only), TxDOT: unit prices by district, all lettings

Districts with at least three low bids, over all lettings.

By quantity

Cctv field equip (digital) (instl only), TxDOT: low bidder's median by quantity band
Quantity (EACH)Low bidsLow-bid median
1 to 214$1,422.97
2 to 314$3,397.50
3 to 514$1,584.89
5 to 1914$2,594.00
Cctv field equip (digital) (instl only), TxDOT: low bidder's median by quantity band

The low bids split into four bands of equal count by the quantity on the contract. Larger quantities usually carry lower unit prices.

Latest contracts with this item

Latest TxDOT contracts carrying Cctv field equip (digital) (instl only)
LetContractDistrictQuantityLow bidder's priceMedianEstimateBidsLow bidderSource
09 JUL 202407243002El Paso District15$987.00$1,050.18$5,500.002SUNDT CONSTRUCTION, INC.TxDOT
06 JUN 202406243204Abilene District2$10,000$11,028$1,850.002WEBBER, LLCTxDOT
06 JUN 202406243222Dallas District4$500.00$2,110.60$15,0004DURABLE SPECIALTIES, INC.TxDOT
06 JUN 202406243248Beaumont District3$1,658.00$2,110.00$4,000.005TRAF-TEX, INC.TxDOT
06 JUN 202406243250Yoakum District2$1,703.55$1,703.55$2,000.007THIRD COAST SERVICES LLCTxDOT
05 JUN 202406243043San Antonio District4$2,500.00$1,705.00$3,000.004E-Z BEL CONSTRUCTION, LLCTxDOT
05 JUN 202406243052San Angelo District2$6,000.00$5,852.50$4,000.002LIGHT IT UP ELECTRICTxDOT
05 JUN 202406243053Odessa District2$3,500.00$4,602.50$5,500.002LIGHT IT UP ELECTRICTxDOT
03 MAY 202405243203El Paso District3$5,484.00$5,484.00$5,500.003SUNDT CONSTRUCTION, INC.TxDOT
02 MAY 202405243006El Paso District1$2,313.00$2,300.00$1,500.003JAMES HAMILTON CONSTRUCTION CO.TxDOT
02 MAY 202405243008El Paso District3$1,511.78$1,511.78$3,200.001VEMAC, LLCTxDOT
02 MAY 202405243032San Antonio District1$650.00$825.00$900.004E-Z BEL CONSTRUCTION, LLCTxDOT
04 APR 202404243001Dallas District1$4,660.08$2,786.54$5,400.002SEMA CONSTRUCTION, INC.TxDOT
06 MAR 202403243201Odessa District3$6,000.00$6,000.00$9,000.003SUNDT CONSTRUCTION, INC.TxDOT
06 MAR 202403243208Fort Worth District2$14,500$12,250$1,800.002NORTHEASTERN PAVERS, LLCTxDOT
Latest TxDOT contracts carrying Cctv field equip (digital) (instl only)

Filter this item by your own quantity, district and period, or check your price against it, in the TxDOT explorer.

How these prices were read

TxDOT Bid Tabulations open-data export (data.texas.gov) from September 2024, read 21 November 2026, and TxDOT's legacy Tabulation of Bids pages for January 2020 to August 2024. The legacy pages are a large sample, not every contract: their file names were reused from year to year. Their district is the one TxDOT gives the county. Bids that did not match their published total are left out.

  • Statistics leave out bids over three times the low bid, zero or negative prices and token prices under 5% of the median.
  • Item codes and units are TxDOT's own: this item is compared with TxDOT contracts only.
  • Prices are bid prices, not paid prices, and are not adjusted for inflation. Use them as a reference range, never as a quote.

Your own bid history, read the same way

Mirage deploys AI agents for heavy civil estimating teams: quantities from the plan set, specs and addenda read, and bid tabs compared, inside your systems and your rules.

We use your email to reply to you and, now and then, to tell you about Mirage. You can opt out at any time. Privacy policy