Cctv field equipment (analog) unit price, Texas
Low bidders on TxDOT contracts carried a median of $7,312.20 per EACH for item 60106001, cctv field equipment (analog), from 10 JAN 2020 to 06 JUN 2024, across 45 low bids. Half of all 180 bids fell between $6,201.86 and $9,040.00.
- Owner
- Texas DOT
- Item
- 60106001
- Unit
- EACH
- Latest letting
- 06 JUN 2024
By year of letting
| Year | Contracts | Low bids | Low-bid median | All bids | Median, all bids |
|---|---|---|---|---|---|
| 2020 | 15 | 15 | $7,335.00 | 67 | $8,396.89 |
| 2021 | 15 | 15 | $6,289.85 | 63 | $6,660.00 |
| 2022 | 3 | 3 | $8,000.00 | 11 | $7,565.00 |
| 2023 | 9 | 9 | $8,120.00 | 28 | $7,654.06 |
| 2024 | 3 | 3 | $9,720.97 | 11 | $8,140.00 |
Bid prices as published, not adjusted for inflation.
By district
| District | Low bids | Low-bid median | All bids | Median, all bids |
|---|---|---|---|---|
| Houston District | 15 | $6,778.00 | 66 | $6,895.00 |
| San Antonio District | 10 | $7,656.10 | 44 | $8,700.00 |
| Austin District | 8 | $7,952.06 | 32 | $8,500.00 |
| Yoakum District | 4 | $9,380.49 | 13 | $8,710.00 |
Districts with at least three low bids, over all lettings.
By quantity
| Quantity (EACH) | Low bids | Low-bid median |
|---|---|---|
| 1 to 2 | 11 | $8,943.63 |
| 2 to 5 | 11 | $8,700.00 |
| 5 to 10 | 11 | $7,085.00 |
| 10 to 31 | 12 | $7,074.81 |
The low bids split into four bands of equal count by the quantity on the contract. Larger quantities usually carry lower unit prices.
Latest contracts with this item
| Let | Contract | District | Quantity | Low bidder's price | Median | Estimate | Bids | Low bidder | Source |
|---|---|---|---|---|---|---|---|---|---|
| 06 JUN 2024 | 06243201 | San Antonio District | 2 | $3,500.00 | $3,684.00 | $4,000.00 | 5 | WEBBER, LLC | TxDOT |
| 03 MAY 2024 | 05243201 | Yoakum District | 10 | $9,720.97 | $8,850.00 | $10,000 | 3 | PULICE CONSTRUCTION, INC. | TxDOT |
| 04 APR 2024 | 04243002 | Corpus Christi District | 1 | $11,800 | $10,761 | $8,120.00 | 3 | BAY LTD. | TxDOT |
| 06 DEC 2023 | 12233201 | Yoakum District | 8 | $9,040.00 | $9,040.00 | $7,500.00 | 3 | WILLIAMS BROTHERS CONSTRUCTION CO., INC. | TxDOT |
| 06 DEC 2023 | 12233217 | Austin District | 11 | $7,404.13 | $7,904.00 | $8,641.39 | 3 | SICE, INC. | TxDOT |
| 01 NOV 2023 | 11233019 | San Antonio District | 4 | $5,000.00 | $5,000.00 | $7,045.41 | 1 | E-Z BEL CONSTRUCTION, LLC | TxDOT |
| 06 SEP 2023 | 09233001 | Beaumont District | 2 | $22,000 | $20,500 | $7,500.00 | 4 | PULICE CONSTRUCTION, INC. | TxDOT |
| 03 AUG 2023 | 08233219 | Austin District | 18 | $7,189.62 | $7,966.61 | $8,000.00 | 3 | SICE, INC. | TxDOT |
| 28 JUN 2023 | 06233602 | Yoakum District | 12 | $10,100 | $8,450.00 | $7,650.00 | 2 | WEBBER, LLC | TxDOT |
| 27 JUN 2023 | 06233402 | Lufkin District | 1 | $9,850.00 | $7,851.50 | $7,000.00 | 2 | WEBBER, LLC | TxDOT |
| 05 MAY 2023 | 05233201 | Houston District | 9 | $6,975.00 | $6,975.00 | $7,000.00 | 5 | JAMES CONSTRUCTION GROUP, LLC | TxDOT |
| 07 MAR 2023 | 03233001 | Houston District | 8 | $8,120.00 | $7,297.77 | $6,960.54 | 5 | WILLIAMS BROTHERS CONSTRUCTION CO., INC. | TxDOT |
| 03 AUG 2022 | 08223002 | Houston District | 13 | $6,960.00 | $7,038.75 | $5,900.00 | 4 | WEBBER, LLC | TxDOT |
| 29 JUN 2022 | 06223419 | San Antonio District | 1 | $8,000.00 | $4,500.00 | $7,229.09 | 2 | E-Z BEL CONSTRUCTION, LLC | TxDOT |
| 05 MAY 2022 | 05223202 | Austin District | 5 | $9,954.50 | $8,409.53 | $5,500.00 | 5 | FLUOR HEAVY CIVIL, LLC | TxDOT |
Filter this item by your own quantity, district and period, or check your price against it, in the TxDOT explorer.
How these prices were read
TxDOT Bid Tabulations open-data export (data.texas.gov) from September 2024, read 21 November 2026, and TxDOT's legacy Tabulation of Bids pages for January 2020 to August 2024. The legacy pages are a large sample, not every contract: their file names were reused from year to year. Their district is the one TxDOT gives the county. Bids that did not match their published total are left out.
- Statistics leave out bids over three times the low bid, zero or negative prices and token prices under 5% of the median.
- Item codes and units are TxDOT's own: this item is compared with TxDOT contracts only.
- Prices are bid prices, not paid prices, and are not adjusted for inflation. Use them as a reference range, never as a quote.
Your own bid history, read the same way
Mirage deploys AI agents for heavy civil estimating teams: quantities from the plan set, specs and addenda read, and bid tabs compared, inside your systems and your rules.