Fiber optic fusion splice unit price, Texas
Low bidders on TxDOT contracts carried a median of $56.35 per EACH for item 60076094, fiber optic fusion splice, from 04 MAR 2020 to 01 AUG 2024, across 79 low bids. Half of all 323 bids fell between $35.68 and $79.15.
- Owner
- Texas DOT
- Item
- 60076094
- Unit
- EACH
- Latest letting
- 01 AUG 2024
By year of letting
| Year | Contracts | Low bids | Low-bid median | All bids | Median, all bids |
|---|---|---|---|---|---|
| 2020 | 22 | 22 | $57.67 | 116 | $44.23 |
| 2021 | 20 | 20 | $35.94 | 80 | $39.38 |
| 2022 | 9 | 9 | $80.00 | 35 | $70.00 |
| 2023 | 17 | 17 | $54.00 | 62 | $60.00 |
| 2024 | 11 | 11 | $70.42 | 30 | $74.78 |
Bid prices as published, not adjusted for inflation.
By district
| District | Low bids | Low-bid median | All bids | Median, all bids |
|---|---|---|---|---|
| Houston District | 30 | $46.50 | 130 | $40.22 |
| Fort Worth District | 10 | $57.67 | 54 | $57.64 |
| Dallas District | 11 | $63.00 | 44 | $62.72 |
| El Paso District | 9 | $125.00 | 26 | $105.50 |
| San Antonio District | 5 | $36.00 | 20 | $63.17 |
| Laredo District | 4 | $40.50 | 16 | $33.00 |
| Austin District | 4 | $38.80 | 14 | $44.00 |
| Yoakum District | 3 | $70.42 | 8 | $83.71 |
Districts with at least three low bids, over all lettings.
By quantity
| Quantity (EACH) | Low bids | Low-bid median |
|---|---|---|
| 2 to 42 | 19 | $107.20 |
| 48 to 224 | 20 | $50.19 |
| 228 to 480 | 20 | $41.04 |
| 492 to 3,000 | 20 | $62.03 |
The low bids split into four bands of equal count by the quantity on the contract. Larger quantities usually carry lower unit prices.
Latest contracts with this item
| Let | Contract | District | Quantity | Low bidder's price | Median | Estimate | Bids | Low bidder | Source |
|---|---|---|---|---|---|---|---|---|---|
| 01 AUG 2024 | 08243001 | Houston District | 864 | $65.00 | $65.00 | $45.00 | 2 | WEBBER, LLC | TxDOT |
| 09 JUL 2024 | 07243001 | Fort Worth District | 444 | $79.15 | $79.20 | $45.00 | 2 | ZACHRY CONSTRUCTION CORPORATION | TxDOT |
| 09 JUL 2024 | 07243002 | El Paso District | 972 | $196.75 | $209.34 | $120.00 | 2 | SUNDT CONSTRUCTION, INC. | TxDOT |
| 06 JUN 2024 | 06243201 | San Antonio District | 156 | $130.00 | $137.00 | $190.00 | 5 | WEBBER, LLC | TxDOT |
| 06 JUN 2024 | 06243203 | Houston District | 174 | $50.00 | $41.00 | $53.85 | 2 | JAMES CONSTRUCTION GROUP, LLC | TxDOT |
| 03 MAY 2024 | 05243201 | Yoakum District | 864 | $70.42 | $64.00 | $70.00 | 3 | PULICE CONSTRUCTION, INC. | TxDOT |
| 03 MAY 2024 | 05243202 | Fort Worth District | 372 | $293.76 | $292.39 | $70.00 | 5 | ZACHRY CONSTRUCTION CORPORATION | TxDOT |
| 04 APR 2024 | 04243001 | Dallas District | 1,134 | $62.99 | $65.12 | $75.00 | 2 | SEMA CONSTRUCTION, INC. | TxDOT |
| 05 MAR 2024 | 03243035 | Austin District | 100 | $40.00 | $41.00 | $30.00 | 2 | ELECNOR BELCO ELECTRIC, INC. | TxDOT |
| 02 FEB 2024 | 02243224 | Dallas District | 6 | $500.00 | $291.88 | $150.00 | 2 | FNH CONSTRUCTION, LLC | TxDOT |
| 01 FEB 2024 | 02243001 | Dallas District | 72 | $50.38 | $50.50 | $69.28 | 3 | FLATIRON CONSTRUCTORS, INC. | TxDOT |
| 06 DEC 2023 | 12233201 | Yoakum District | 24 | $410.28 | $410.28 | $65.00 | 3 | WILLIAMS BROTHERS CONSTRUCTION CO., INC. | TxDOT |
| 02 NOV 2023 | 11233213 | El Paso District | 4 | $125.00 | $125.00 | $200.00 | 1 | TRI STATE ELECTRIC, LTD. | TxDOT |
| 06 SEP 2023 | 09233024 | Houston District | 384 | $50.00 | $38.83 | $52.74 | 3 | THIRD COAST SERVICES LLC | TxDOT |
| 03 AUG 2023 | 08233203 | Dallas District | 72 | $83.00 | $91.50 | $65.00 | 2 | WEBBER, LLC | TxDOT |
Filter this item by your own quantity, district and period, or check your price against it, in the TxDOT explorer.
How these prices were read
TxDOT Bid Tabulations open-data export (data.texas.gov) from September 2024, read 21 November 2026, and TxDOT's legacy Tabulation of Bids pages for January 2020 to August 2024. The legacy pages are a large sample, not every contract: their file names were reused from year to year. Their district is the one TxDOT gives the county. Bids that did not match their published total are left out.
- Statistics leave out bids over three times the low bid, zero or negative prices and token prices under 5% of the median.
- Item codes and units are TxDOT's own: this item is compared with TxDOT contracts only.
- Prices are bid prices, not paid prices, and are not adjusted for inflation. Use them as a reference range, never as a quote.