Cctv field equip (digital) (instl only) unit price, Texas

Low bidders on TxDOT contracts carried a median of $1,275.00 per EACH for item 6018-7001, cctv field equip (digital) (instl only), over the 24 months to 19 NOV 2026, across 44 low bids. Half of all 229 bids fell between $810.00 and $2,453.45.

Owner
Texas DOT
Item
6018-7001
Unit
EACH
Latest letting
03 NOV 2026
$1,275.00Low bidder's median, per EACH
$1,330.00Median of all bids, per EACH
44Contracts in the window
$2,100.00Engineer's estimate, median per EACH

By year of letting

Cctv field equip (digital) (instl only), TxDOT: unit prices by year
YearContractsLow bidsLow-bid medianAll bidsMedian, all bids
20252121$2,000.00101$1,800.00
20262323$850.00128$1,023.50
Cctv field equip (digital) (instl only), TxDOT: unit prices by year

Bid prices as published, not adjusted for inflation.

By district

Cctv field equip (digital) (instl only), TxDOT: unit prices by district, last 24 months
DistrictLow bidsLow-bid medianAll bidsMedian, all bids
San Antonio District11$770.0060$955.00
Dallas District7$1,000.0046$1,150.00
Austin District7$1,100.0044$1,746.04
Corpus Christi District4$1,417.5022$1,140.10
Odessa District3$10,21313$3,000.00
Lubbock District3$3,290.0012$3,395.00
El Paso District3$2,200.0010$2,250.00
Cctv field equip (digital) (instl only), TxDOT: unit prices by district, last 24 months

Districts with at least three low bids, over the last 24 months.

By quantity

Cctv field equip (digital) (instl only), TxDOT: low bidder's median by quantity band
Quantity (EACH)Low bidsLow-bid median
1 to 111$1,330.00
1 to 311$2,000.00
3 to 511$1,300.00
6 to 20011$884.00
Cctv field equip (digital) (instl only), TxDOT: low bidder's median by quantity band

The low bids split into four bands of equal count by the quantity on the contract. Larger quantities usually carry lower unit prices.

Latest contracts with this item

Latest TxDOT contracts carrying Cctv field equip (digital) (instl only)
LetContractDistrictQuantityLow bidder's priceMedianEstimateBidsLow bidderSource
03 NOV 2026A00184974Austin District13$371.88$590.87$1,000.006AUSTIN BRIDGE & ROAD SERVICES, LPTxDOT
07 OCT 2026A00135746Dallas District1$2,250.00$1,377.20$3,000.009GARRET SHIELDS INFRASTRUCTURETxDOT
07 OCT 2026A00064192San Antonio District2$670.00$726.77$800.008HUNTER INDUSTRIES, LTD.TxDOT
03 SEP 2026A00208481Dallas District1$846.43$846.43$1,500.007SICE, INC.TxDOT
03 SEP 2026A00198323Dallas District1$750.00$1,472.75$2,000.008AMERICAN LIGHTING AND SIGNALIZATION, LLCTxDOT
02 JUL 2026A00124174Lubbock District5$1,500.00$1,062.57$24,0004WILLIAMS BROTHERS CONSTRUCTION CO., INC.TxDOT
02 JUL 2026A00193863Dallas District11$745.55$850.00n/a5SICE, INC.TxDOT
02 JUL 2026A00187816Odessa District1$2,996.30$2,996.30$7,612.573JASCOTxDOT
01 JUL 2026A00080576Odessa District1$10,213$2,500.00$3,500.005JONES BROS. DIRT & PAVING CONTRACTORS, INC.TxDOT
01 JUL 2026A00193476San Antonio District4$450.00$810.00$1,000.007E-Z BEL CONSTRUCTION, LLCTxDOT
03 JUN 2026A00206735Austin District1$1,000.00$1,000.00$1,000.007E-Z BEL CONSTRUCTION, LLCTxDOT
03 JUN 2026A00062698San Antonio District3$770.00$503.50$1,500.006JORDAN FOSTER CONSTRUCTION, LLCTxDOT
03 JUN 2026A00063871El Paso District8$2,300.00$2,275.00$2,000.004JORDAN FOSTER CONSTRUCTION, LLCTxDOT
07 MAY 2026A00184602Austin District1$1,330.00$1,330.00$2,500.005ELECNOR BELCO ELECTRIC, INC.TxDOT
07 MAY 2026A00031457San Antonio District6$500.00$1,800.00$2,200.003WEBBER, LLCTxDOT
Latest TxDOT contracts carrying Cctv field equip (digital) (instl only)

Filter this item by your own quantity, district and period, or check your price against it, in the TxDOT explorer.

How these prices were read

TxDOT Bid Tabulations open-data export (data.texas.gov) from September 2024, read 21 November 2026, and TxDOT's legacy Tabulation of Bids pages for January 2020 to August 2024. The legacy pages are a large sample, not every contract: their file names were reused from year to year. Their district is the one TxDOT gives the county. Bids that did not match their published total are left out.

  • Statistics leave out bids over three times the low bid, zero or negative prices and token prices under 5% of the median.
  • Item codes and units are TxDOT's own: this item is compared with TxDOT contracts only.
  • Prices are bid prices, not paid prices, and are not adjusted for inflation. Use them as a reference range, never as a quote.

Your own bid history, read the same way