Fiber optic fusion splice unit price, Texas
Low bidders on TxDOT contracts carried a median of $71.66 per EACH for item 6027-7004, fiber optic fusion splice, over the 24 months to 19 NOV 2026, across 45 low bids. Half of all 247 bids fell between $50.00 and $125.00.
- Owner
- Texas DOT
- Item
- 6027-7004
- Unit
- EACH
- Latest letting
- 04 NOV 2026
By year of letting
| Year | Contracts | Low bids | Low-bid median | All bids | Median, all bids |
|---|---|---|---|---|---|
| 2024 | 2 | 2 | $61.77 | 17 | $56.00 |
| 2025 | 25 | 25 | $90.65 | 127 | $80.44 |
| 2026 | 18 | 18 | $67.95 | 103 | $67.41 |
Bid prices as published, not adjusted for inflation.
By district
| District | Low bids | Low-bid median | All bids | Median, all bids |
|---|---|---|---|---|
| Houston District | 19 | $68.64 | 115 | $61.00 |
| Dallas District | 9 | $80.00 | 58 | $79.70 |
| San Antonio District | 5 | $150.00 | 29 | $140.00 |
| El Paso District | 4 | $132.50 | 14 | $132.50 |
Districts with at least three low bids, over the last 24 months.
By quantity
| Quantity (EACH) | Low bids | Low-bid median |
|---|---|---|
| 4 to 72 | 11 | $166.76 |
| 78 to 144 | 11 | $69.00 |
| 150 to 270 | 11 | $71.66 |
| 276 to 3,012 | 12 | $53.60 |
The low bids split into four bands of equal count by the quantity on the contract. Larger quantities usually carry lower unit prices.
Latest contracts with this item
| Let | Contract | District | Quantity | Low bidder's price | Median | Estimate | Bids | Low bidder | Source |
|---|---|---|---|---|---|---|---|---|---|
| 04 NOV 2026 | A00212892 | Dallas District | 48 | $94.00 | $92.05 | $69.00 | 6 | INDUS ROAD & BRIDGE, INC. | TxDOT |
| 07 OCT 2026 | A00192619 | Dallas District | 1,116 | $28.30 | $49.48 | n/a | 6 | SICE, INC. | TxDOT |
| 06 OCT 2026 | A00186301 | Waco District | 576 | $71.00 | $67.22 | $67.00 | 6 | BIG CREEK CONSTRUCTION, LTD. | TxDOT |
| 03 SEP 2026 | A00208481 | Dallas District | 144 | $27.76 | $65.00 | $235.00 | 7 | SICE, INC. | TxDOT |
| 06 AUG 2026 | A00218304 | San Antonio District | 1,406 | $24.13 | $54.30 | $90.00 | 7 | SICE, INC. | TxDOT |
| 05 AUG 2026 | A00206808 | Houston District | 270 | $29.12 | $30.27 | $75.00 | 7 | ALBATROSS CONSTRUCTION LLC | TxDOT |
| 02 JUL 2026 | A00124174 | Lubbock District | 15 | $50.00 | $124.19 | $85.00 | 4 | WILLIAMS BROTHERS CONSTRUCTION CO., INC. | TxDOT |
| 02 JUL 2026 | A00064320 | Fort Worth District | 192 | $71.66 | $65.55 | $100.00 | 6 | SICE, INC. | TxDOT |
| 03 JUN 2026 | A00063871 | El Paso District | 120 | $130.00 | $127.50 | $131.00 | 4 | JORDAN FOSTER CONSTRUCTION, LLC | TxDOT |
| 07 MAY 2026 | A00031457 | San Antonio District | 6 | $500.00 | $90.00 | $90.00 | 3 | WEBBER, LLC | TxDOT |
| 06 MAY 2026 | A00123433 | Houston District | 156 | $67.26 | $71.89 | $100.00 | 7 | THIRD COAST SERVICES LLC | TxDOT |
| 07 APR 2026 | A00123513 | Houston District | 156 | $172.33 | $57.24 | $75.00 | 5 | ALLSTATE SIGNAL & CONSTRUCTION, LLC | TxDOT |
| 05 MAR 2026 | A00193765 | Dallas District | 16 | $80.00 | $90.00 | $80.00 | 8 | ELECNOR BELCO ELECTRIC, INC. | TxDOT |
| 04 MAR 2026 | A00132533 | Dallas District | 300 | $325.00 | $89.00 | $90.00 | 9 | HIGHWAY 19 CONSTRUCTION LLC | TxDOT |
| 05 FEB 2026 | A00132314 | Houston District | 576 | $12.42 | $37.00 | $63.98 | 7 | CREACOM, INC. | TxDOT |
Filter this item by your own quantity, district and period, or check your price against it, in the TxDOT explorer.
How these prices were read
TxDOT Bid Tabulations open-data export (data.texas.gov) from September 2024, read 21 November 2026, and TxDOT's legacy Tabulation of Bids pages for January 2020 to August 2024. The legacy pages are a large sample, not every contract: their file names were reused from year to year. Their district is the one TxDOT gives the county. Bids that did not match their published total are left out.
- Statistics leave out bids over three times the low bid, zero or negative prices and token prices under 5% of the median.
- Item codes and units are TxDOT's own: this item is compared with TxDOT contracts only.
- Prices are bid prices, not paid prices, and are not adjusted for inflation. Use them as a reference range, never as a quote.
Your own bid history, read the same way