Install dms (pole mtd cabinet) unit price, Texas
Low bidders on TxDOT contracts carried a median of $14,514 per EACH for item 60286001, install dms (pole mtd cabinet), from 09 APR 2020 to 09 JUL 2024, across 52 low bids. Half of all 178 bids fell between $11,136 and $24,750.
- Owner
- Texas DOT
- Item
- 60286001
- Unit
- EACH
- Latest letting
- 09 JUL 2024
By year of letting
| Year | Contracts | Low bids | Low-bid median | All bids | Median, all bids |
|---|---|---|---|---|---|
| 2020 | 6 | 6 | $19,478 | 34 | $19,755 |
| 2021 | 15 | 15 | $11,100 | 63 | $11,485 |
| 2022 | 7 | 7 | $22,755 | 23 | $16,000 |
| 2023 | 12 | 12 | $11,654 | 33 | $21,000 |
| 2024 | 12 | 12 | $16,821 | 25 | $25,777 |
Bid prices as published, not adjusted for inflation.
By district
| District | Low bids | Low-bid median | All bids | Median, all bids |
|---|---|---|---|---|
| Fort Worth District | 9 | $18,000 | 42 | $19,200 |
| San Antonio District | 7 | $12,713 | 36 | $11,517 |
| El Paso District | 11 | $38,500 | 23 | $35,000 |
| Lubbock District | 5 | $11,637 | 19 | $14,000 |
| Corpus Christi District | 3 | $15,500 | 14 | $14,483 |
| Austin District | 4 | $6,616.02 | 11 | $10,594 |
| Laredo District | 3 | $13,730 | 8 | $15,261 |
Districts with at least three low bids, over all lettings.
By quantity
| Quantity (EACH) | Low bids | Low-bid median |
|---|---|---|
| 1 to 1 | 13 | $12,713 |
| 2 to 2 | 13 | $15,618 |
| 2 to 3 | 13 | $13,600 |
| 3 to 31 | 13 | $15,641 |
The low bids split into four bands of equal count by the quantity on the contract. Larger quantities usually carry lower unit prices.
Latest contracts with this item
| Let | Contract | District | Quantity | Low bidder's price | Median | Estimate | Bids | Low bidder | Source |
|---|---|---|---|---|---|---|---|---|---|
| 09 JUL 2024 | 07243002 | El Paso District | 6 | $39,112 | $41,616 | $11,250 | 2 | SUNDT CONSTRUCTION, INC. | TxDOT |
| 09 JUL 2024 | 07243008 | Fort Worth District | 1 | $18,000 | $18,000 | $23,303 | 1 | LIGHT IT UP ELECTRIC | TxDOT |
| 05 JUN 2024 | 06243042 | Abilene District | 2 | $13,271 | $39,520 | $6,000.00 | 2 | FLORIDA TRAFFIC CONTROL DEVICES, INC. | TxDOT |
| 03 MAY 2024 | 05243202 | Fort Worth District | 2 | $25,898 | $25,777 | $22,000 | 5 | ZACHRY CONSTRUCTION CORPORATION | TxDOT |
| 02 MAY 2024 | 05243001 | Beaumont District | 3 | $14,027 | $14,027 | $20,000 | 1 | WILLIAMS BROTHERS CONSTRUCTION CO., INC. | TxDOT |
| 02 MAY 2024 | 05243002 | Laredo District | 4 | $13,730 | $13,615 | $21,700 | 2 | WEBBER, LLC | TxDOT |
| 02 MAY 2024 | 05243008 | El Paso District | 2 | $54,488 | $54,488 | $31,000 | 1 | VEMAC, LLC | TxDOT |
| 05 APR 2024 | 04243202 | Wichita Falls District | 3 | $15,641 | $27,274 | $20,000 | 2 | AUSTIN BRIDGE & ROAD SERVICES, LP ZACHRY CONSTRUCTION CORPORATION | TxDOT |
| 05 APR 2024 | 04243216 | San Antonio District | 8 | $13,405 | $21,169 | $15,000 | 4 | THE LEVY COMPANY, INC. | TxDOT |
| 05 MAR 2024 | 03243035 | Austin District | 1 | $1,300.00 | $7,650.00 | $14,800 | 2 | ELECNOR BELCO ELECTRIC, INC. | TxDOT |
| 01 FEB 2024 | 02243037 | El Paso District | 2 | $42,000 | $42,000 | $26,333 | 1 | TRI STATE ELECTRIC, LTD. | TxDOT |
| 05 JAN 2024 | 01243202 | El Paso District | 3 | $43,500 | $45,750 | $38,000 | 2 | DAN WILLIAMS COMPANY | TxDOT |
| 06 DEC 2023 | 12233210 | Odessa District | 6 | $31,810 | $31,810 | $15,000 | 1 | MICA CORPORATION | TxDOT |
| 06 DEC 2023 | 12233217 | Austin District | 1 | $5,232.04 | $8,972.80 | $15,562 | 3 | SICE, INC. | TxDOT |
| 07 SEP 2023 | 09233207 | El Paso District | 1 | $38,500 | $39,250 | $35,588 | 2 | DAN WILLIAMS COMPANY | TxDOT |
Filter this item by your own quantity, district and period, or check your price against it, in the TxDOT explorer.
How these prices were read
TxDOT Bid Tabulations open-data export (data.texas.gov) from September 2024, read 21 November 2026, and TxDOT's legacy Tabulation of Bids pages for January 2020 to August 2024. The legacy pages are a large sample, not every contract: their file names were reused from year to year. Their district is the one TxDOT gives the county. Bids that did not match their published total are left out.
- Statistics leave out bids over three times the low bid, zero or negative prices and token prices under 5% of the median.
- Item codes and units are TxDOT's own: this item is compared with TxDOT contracts only.
- Prices are bid prices, not paid prices, and are not adjusted for inflation. Use them as a reference range, never as a quote.