Cement treat (subgrade) (8") unit price, Texas
Low bidders on TxDOT contracts carried a median of $4.00 per SY for item 2756010, cement treat (subgrade) (8"), from 06 FEB 2020 to 10 JUL 2024, across 107 low bids. Half of all 457 bids fell between $3.00 and $7.25.
- Owner
- Texas DOT
- Item
- 2756010
- Unit
- SY
- Latest letting
- 10 JUL 2024
By year of letting
| Year | Contracts | Low bids | Low-bid median | All bids | Median, all bids |
|---|---|---|---|---|---|
| 2020 | 16 | 16 | $2.88 | 90 | $4.00 |
| 2021 | 29 | 29 | $3.50 | 143 | $3.50 |
| 2022 | 19 | 19 | $3.41 | 72 | $4.00 |
| 2023 | 24 | 24 | $5.00 | 80 | $6.65 |
| 2024 | 19 | 19 | $5.75 | 72 | $6.00 |
Bid prices as published, not adjusted for inflation.
By district
| District | Low bids | Low-bid median | All bids | Median, all bids |
|---|---|---|---|---|
| Wichita Falls District | 23 | $4.35 | 83 | $4.75 |
| Bryan District | 13 | $4.25 | 70 | $3.95 |
| Amarillo District | 18 | $4.71 | 66 | $5.36 |
| Atlanta District | 14 | $2.50 | 63 | $3.50 |
| Fort Worth District | 11 | $5.25 | 49 | $5.60 |
| Yoakum District | 8 | $3.38 | 33 | $3.00 |
| Tyler District | 5 | $4.00 | 20 | $4.00 |
| Corpus Christi District | 3 | $4.00 | 10 | $4.60 |
Districts with at least three low bids, over all lettings.
By quantity
| Quantity (SY) | Low bids | Low-bid median |
|---|---|---|
| 50 to 4,391 | 26 | $5.78 |
| 4,438 to 30,592 | 27 | $5.00 |
| 31,558 to 70,917 | 27 | $3.00 |
| 71,680 to 496,590 | 27 | $2.75 |
The low bids split into four bands of equal count by the quantity on the contract. Larger quantities usually carry lower unit prices.
Latest contracts with this item
| Let | Contract | District | Quantity | Low bidder's price | Median | Estimate | Bids | Low bidder | Source |
|---|---|---|---|---|---|---|---|---|---|
| 10 JUL 2024 | 07243215 | Wichita Falls District | 41,536 | $8.00 | $7.17 | $6.50 | 4 | ZACK BURKETT CO. | TxDOT |
| 06 JUN 2024 | 06243205 | Wichita Falls District | 120,350 | $5.50 | $3.00 | $4.00 | 3 | A. L. HELMCAMP, INC. | TxDOT |
| 05 JUN 2024 | 06243005 | Amarillo District | 39,803 | $11.15 | $16.07 | $7.00 | 2 | J. LEE MILLIGAN, INC. | TxDOT |
| 05 JUN 2024 | 06243008 | Wichita Falls District | 165,531 | $2.75 | $4.42 | $3.00 | 4 | A. L. HELMCAMP, INC. | TxDOT |
| 05 JUN 2024 | 06243009 | Bryan District | 68,269 | $1.30 | $2.59 | $4.46 | 6 | KNIFE RIVER CORPORATION - SOUTH | TxDOT |
| 05 JUN 2024 | 06243012 | Amarillo District | 2,357 | $5.68 | $8.38 | $10.00 | 4 | KIEWIT INFRASTRUCTURE SOUTH CO. | TxDOT |
| 05 JUN 2024 | 06243019 | Abilene District | 4,438 | $25.00 | $25.00 | $10.00 | 1 | HODGES AND SON CONSTRUCTION COMPANY, INC. | TxDOT |
| 05 JUN 2024 | 06243022 | Wichita Falls District | 30,592 | $10.00 | $8.85 | $3.50 | 4 | ZACK BURKETT CO. | TxDOT |
| 03 MAY 2024 | 05243236 | Atlanta District | 4,391 | $5.00 | $5.00 | $8.25 | 4 | EAST TEXAS BRIDGE, INC. | TxDOT |
| 05 APR 2024 | 04243202 | Wichita Falls District | 496,590 | $2.39 | $2.27 | $2.50 | 2 | AUSTIN BRIDGE & ROAD SERVICES, LP ZACHRY CONSTRUCTION CORPORATION | TxDOT |
| 06 MAR 2024 | 03243222 | Atlanta District | 3,319 | $5.75 | $5.88 | $6.75 | 4 | THK CONSTRUCTION LLC | TxDOT |
| 05 MAR 2024 | 03243001 | Tyler District | 76,615 | $4.00 | $4.00 | $4.50 | 5 | LAMAR COMPANIES LLC | TxDOT |
| 05 MAR 2024 | 03243003 | Amarillo District | 147,866 | $16.45 | $16.45 | $5.50 | 1 | WEBBER, LLC | TxDOT |
| 05 MAR 2024 | 03243018 | Wichita Falls District | 4,046 | $13.00 | $15.50 | $6.00 | 2 | A. L. HELMCAMP, INC. | TxDOT |
| 02 FEB 2024 | 02243242 | Bryan District | 1,670 | $6.24 | $12.00 | $6.00 | 9 | KNIFE RIVER CORPORATION - SOUTH | TxDOT |
Filter this item by your own quantity, district and period, or check your price against it, in the TxDOT explorer.
How these prices were read
TxDOT Bid Tabulations open-data export (data.texas.gov) from September 2024, read 21 November 2026, and TxDOT's legacy Tabulation of Bids pages for January 2020 to August 2024. The legacy pages are a large sample, not every contract: their file names were reused from year to year. Their district is the one TxDOT gives the county. Bids that did not match their published total are left out.
- Statistics leave out bids over three times the low bid, zero or negative prices and token prices under 5% of the median.
- Item codes and units are TxDOT's own: this item is compared with TxDOT contracts only.
- Prices are bid prices, not paid prices, and are not adjusted for inflation. Use them as a reference range, never as a quote.
Your own bid history, read the same way
Mirage deploys AI agents for heavy civil estimating teams: quantities from the plan set, specs and addenda read, and bid tabs compared, inside your systems and your rules.