Cement treat(exist matl)(8") unit price, Texas
Low bidders on TxDOT contracts carried a median of $3.25 per SY for item 2756011, cement treat(exist matl)(8"), from 09 JAN 2020 to 10 JUL 2024, across 66 low bids. Half of all 306 bids fell between $2.50 and $6.00.
- Owner
- Texas DOT
- Item
- 2756011
- Unit
- SY
- Latest letting
- 10 JUL 2024
By year of letting
| Year | Contracts | Low bids | Low-bid median | All bids | Median, all bids |
|---|---|---|---|---|---|
| 2020 | 12 | 12 | $1.97 | 59 | $2.50 |
| 2021 | 17 | 17 | $3.25 | 97 | $3.59 |
| 2022 | 12 | 12 | $2.77 | 52 | $3.50 |
| 2023 | 13 | 13 | $4.63 | 50 | $5.20 |
| 2024 | 12 | 12 | $5.25 | 48 | $5.00 |
Bid prices as published, not adjusted for inflation.
By district
| District | Low bids | Low-bid median | All bids | Median, all bids |
|---|---|---|---|---|
| Tyler District | 17 | $5.00 | 86 | $5.78 |
| Yoakum District | 15 | $3.00 | 61 | $3.00 |
| Corpus Christi District | 5 | $1.50 | 32 | $2.00 |
| Fort Worth District | 5 | $3.75 | 22 | $4.00 |
| Waco District | 5 | $2.50 | 19 | $2.75 |
| Bryan District | 4 | $3.62 | 18 | $2.90 |
| Dallas District | 3 | $1.84 | 15 | $2.10 |
| Wichita Falls District | 3 | $3.00 | 15 | $3.15 |
Districts with at least three low bids, over all lettings.
By quantity
| Quantity (SY) | Low bids | Low-bid median |
|---|---|---|
| 100 to 6,086 | 16 | $5.38 |
| 6,825 to 24,278 | 17 | $3.00 |
| 25,264 to 71,757 | 16 | $3.06 |
| 74,356 to 345,987 | 17 | $2.50 |
The low bids split into four bands of equal count by the quantity on the contract. Larger quantities usually carry lower unit prices.
Latest contracts with this item
| Let | Contract | District | Quantity | Low bidder's price | Median | Estimate | Bids | Low bidder | Source |
|---|---|---|---|---|---|---|---|---|---|
| 10 JUL 2024 | 07243204 | Yoakum District | 64,930 | $3.12 | $3.01 | $4.00 | 6 | HUNTER INDUSTRIES, LTD. | TxDOT |
| 10 JUL 2024 | 07243212 | Bryan District | 28,920 | $5.00 | $5.00 | $4.50 | 5 | LARRY YOUNG PAVING, INC. | TxDOT |
| 06 JUN 2024 | 06243228 | Fort Worth District | 739 | $10.00 | $16.50 | $4.50 | 2 | RAGLE CONSTRUCTION, INC. | TxDOT |
| 03 MAY 2024 | 05243207 | Tyler District | 101,501 | $4.00 | $4.88 | $5.10 | 4 | BAKER & COMPANY CONSTRUCTION, LLC | TxDOT |
| 02 MAY 2024 | 05243003 | Waco District | 93,373 | $2.50 | $2.88 | $4.70 | 4 | BIG CREEK CONSTRUCTION, LTD. | TxDOT |
| 04 APR 2024 | 04243008 | Yoakum District | 11,315 | $6.00 | $4.95 | $3.50 | 5 | E-Z BEL CONSTRUCTION, LLC | TxDOT |
| 06 MAR 2024 | 03243204 | Yoakum District | 23,859 | $3.00 | $3.61 | $4.90 | 2 | HUNTER INDUSTRIES, LTD. | TxDOT |
| 06 MAR 2024 | 03243227 | Tyler District | 1,437 | $11.00 | $14.50 | $16.00 | 4 | REYNOLDS & KAY, LTD. | TxDOT |
| 05 MAR 2024 | 03243009 | Yoakum District | 6,086 | $5.50 | $5.19 | $7.00 | 4 | E-Z BEL CONSTRUCTION, LLC | TxDOT |
| 02 FEB 2024 | 02243239 | Lubbock District | 48,810 | $7.50 | $7.50 | $10.00 | 3 | LONE STAR DIRT & PAVING, LTD. | TxDOT |
| 01 FEB 2024 | 02243005 | Atlanta District | 147,972 | $4.00 | $4.00 | $4.00 | 3 | LONGVIEW BRIDGE AND ROAD, LTD. | TxDOT |
| 04 JAN 2024 | 01243031 | Amarillo District | 10,832 | $6.40 | $8.32 | $7.00 | 6 | L A FULLER & SONS CONSTRUCTION, LTD. | TxDOT |
| 05 DEC 2023 | 12233002 | Yoakum District | 176,532 | $3.00 | $3.00 | $4.00 | 1 | HUNTER INDUSTRIES, LTD. | TxDOT |
| 01 NOV 2023 | 11233006 | Tyler District | 38,865 | $5.10 | $5.10 | $5.00 | 5 | MADDEN CONTRACTING COMPANY, LLC. | TxDOT |
| 07 SEP 2023 | 09233206 | Tyler District | 143,992 | $6.55 | $7.00 | $5.38 | 3 | REYNOLDS & KAY, LTD. | TxDOT |
Filter this item by your own quantity, district and period, or check your price against it, in the TxDOT explorer.
How these prices were read
TxDOT Bid Tabulations open-data export (data.texas.gov) from September 2024, read 21 November 2026, and TxDOT's legacy Tabulation of Bids pages for January 2020 to August 2024. The legacy pages are a large sample, not every contract: their file names were reused from year to year. Their district is the one TxDOT gives the county. Bids that did not match their published total are left out.
- Statistics leave out bids over three times the low bid, zero or negative prices and token prices under 5% of the median.
- Item codes and units are TxDOT's own: this item is compared with TxDOT contracts only.
- Prices are bid prices, not paid prices, and are not adjusted for inflation. Use them as a reference range, never as a quote.
Your own bid history, read the same way
Mirage deploys AI agents for heavy civil estimating teams: quantities from the plan set, specs and addenda read, and bid tabs compared, inside your systems and your rules.