Cement treat(exist matl)(8") unit price, Texas

Low bidders on TxDOT contracts carried a median of $3.25 per SY for item 2756011, cement treat(exist matl)(8"), from 09 JAN 2020 to 10 JUL 2024, across 66 low bids. Half of all 306 bids fell between $2.50 and $6.00.

Owner
Texas DOT
Item
2756011
Unit
SY
Latest letting
10 JUL 2024
$3.25Low bidder's median, per SY
$4.00Median of all bids, per SY
66Contracts in the window
$4.00Engineer's estimate, median per SY

By year of letting

Cement treat(exist matl)(8"), TxDOT: unit prices by year
YearContractsLow bidsLow-bid medianAll bidsMedian, all bids
20201212$1.9759$2.50
20211717$3.2597$3.59
20221212$2.7752$3.50
20231313$4.6350$5.20
20241212$5.2548$5.00
Cement treat(exist matl)(8"), TxDOT: unit prices by year

Bid prices as published, not adjusted for inflation.

By district

Cement treat(exist matl)(8"), TxDOT: unit prices by district, all lettings
DistrictLow bidsLow-bid medianAll bidsMedian, all bids
Tyler District17$5.0086$5.78
Yoakum District15$3.0061$3.00
Corpus Christi District5$1.5032$2.00
Fort Worth District5$3.7522$4.00
Waco District5$2.5019$2.75
Bryan District4$3.6218$2.90
Dallas District3$1.8415$2.10
Wichita Falls District3$3.0015$3.15
Cement treat(exist matl)(8"), TxDOT: unit prices by district, all lettings

Districts with at least three low bids, over all lettings.

By quantity

Cement treat(exist matl)(8"), TxDOT: low bidder's median by quantity band
Quantity (SY)Low bidsLow-bid median
100 to 6,08616$5.38
6,825 to 24,27817$3.00
25,264 to 71,75716$3.06
74,356 to 345,98717$2.50
Cement treat(exist matl)(8"), TxDOT: low bidder's median by quantity band

The low bids split into four bands of equal count by the quantity on the contract. Larger quantities usually carry lower unit prices.

Latest contracts with this item

Latest TxDOT contracts carrying Cement treat(exist matl)(8")
LetContractDistrictQuantityLow bidder's priceMedianEstimateBidsLow bidderSource
10 JUL 202407243204Yoakum District64,930$3.12$3.01$4.006HUNTER INDUSTRIES, LTD.TxDOT
10 JUL 202407243212Bryan District28,920$5.00$5.00$4.505LARRY YOUNG PAVING, INC.TxDOT
06 JUN 202406243228Fort Worth District739$10.00$16.50$4.502RAGLE CONSTRUCTION, INC.TxDOT
03 MAY 202405243207Tyler District101,501$4.00$4.88$5.104BAKER & COMPANY CONSTRUCTION, LLCTxDOT
02 MAY 202405243003Waco District93,373$2.50$2.88$4.704BIG CREEK CONSTRUCTION, LTD.TxDOT
04 APR 202404243008Yoakum District11,315$6.00$4.95$3.505E-Z BEL CONSTRUCTION, LLCTxDOT
06 MAR 202403243204Yoakum District23,859$3.00$3.61$4.902HUNTER INDUSTRIES, LTD.TxDOT
06 MAR 202403243227Tyler District1,437$11.00$14.50$16.004REYNOLDS & KAY, LTD.TxDOT
05 MAR 202403243009Yoakum District6,086$5.50$5.19$7.004E-Z BEL CONSTRUCTION, LLCTxDOT
02 FEB 202402243239Lubbock District48,810$7.50$7.50$10.003LONE STAR DIRT & PAVING, LTD.TxDOT
01 FEB 202402243005Atlanta District147,972$4.00$4.00$4.003LONGVIEW BRIDGE AND ROAD, LTD.TxDOT
04 JAN 202401243031Amarillo District10,832$6.40$8.32$7.006L A FULLER & SONS CONSTRUCTION, LTD.TxDOT
05 DEC 202312233002Yoakum District176,532$3.00$3.00$4.001HUNTER INDUSTRIES, LTD.TxDOT
01 NOV 202311233006Tyler District38,865$5.10$5.10$5.005MADDEN CONTRACTING COMPANY, LLC.TxDOT
07 SEP 202309233206Tyler District143,992$6.55$7.00$5.383REYNOLDS & KAY, LTD.TxDOT
Latest TxDOT contracts carrying Cement treat(exist matl)(8")

Filter this item by your own quantity, district and period, or check your price against it, in the TxDOT explorer.

How these prices were read

TxDOT Bid Tabulations open-data export (data.texas.gov) from September 2024, read 21 November 2026, and TxDOT's legacy Tabulation of Bids pages for January 2020 to August 2024. The legacy pages are a large sample, not every contract: their file names were reused from year to year. Their district is the one TxDOT gives the county. Bids that did not match their published total are left out.

  • Statistics leave out bids over three times the low bid, zero or negative prices and token prices under 5% of the median.
  • Item codes and units are TxDOT's own: this item is compared with TxDOT contracts only.
  • Prices are bid prices, not paid prices, and are not adjusted for inflation. Use them as a reference range, never as a quote.

Your own bid history, read the same way

Mirage deploys AI agents for heavy civil estimating teams: quantities from the plan set, specs and addenda read, and bid tabs compared, inside your systems and your rules.

We use your email to reply to you and, now and then, to tell you about Mirage. You can opt out at any time. Privacy policy