Bonding course unit price, Texas
Low bidders on TxDOT contracts carried a median of $4.00 per GAL for item 3007-7001, bonding course, over the 24 months to 19 NOV 2026, across 213 low bids. Half of all 1,134 bids fell between $3.50 and $5.51.
- Owner
- Texas DOT
- Item
- 3007-7001
- Unit
- GAL
- Latest letting
- 04 NOV 2026
By year of letting
| Year | Contracts | Low bids | Low-bid median | All bids | Median, all bids |
|---|---|---|---|---|---|
| 2024 | 7 | 7 | $5.00 | 29 | $4.50 |
| 2025 | 112 | 111 | $4.00 | 551 | $4.25 |
| 2026 | 105 | 101 | $3.65 | 577 | $4.15 |
Bid prices as published, not adjusted for inflation.
By district
| District | Low bids | Low-bid median | All bids | Median, all bids |
|---|---|---|---|---|
| Austin District | 56 | $3.52 | 357 | $4.00 |
| San Antonio District | 26 | $3.52 | 157 | $4.00 |
| Pharr District | 27 | $3.00 | 128 | $4.11 |
| Lufkin District | 21 | $6.00 | 111 | $6.04 |
| Bryan District | 11 | $4.20 | 79 | $5.00 |
| Odessa District | 28 | $3.50 | 75 | $4.50 |
| Laredo District | 14 | $3.36 | 66 | $4.00 |
| Wichita Falls District | 11 | $4.64 | 59 | $4.25 |
| Brownwood District | 6 | $4.12 | 37 | $4.00 |
| Paris District | 6 | $5.05 | 32 | $5.80 |
Districts with at least three low bids, over the last 24 months.
By quantity
| Quantity (GAL) | Low bids | Low-bid median |
|---|---|---|
| 3 to 2,746 | 53 | $5.00 |
| 2,823 to 8,621 | 53 | $4.00 |
| 8,736 to 23,555 | 53 | $3.35 |
| 23,679 to 203,597 | 54 | $3.02 |
The low bids split into four bands of equal count by the quantity on the contract. Larger quantities usually carry lower unit prices.
Latest contracts with this item
| Let | Contract | District | Quantity | Low bidder's price | Median | Estimate | Bids | Low bidder | Source |
|---|---|---|---|---|---|---|---|---|---|
| 04 NOV 2026 | A00206976 | Austin District | 58 | $30.00 | $26.00 | $4.00 | 9 | LONE STAR SITEWORK, LLC | TxDOT |
| 04 NOV 2026 | A00124162 | Bryan District | 24,419 | $4.20 | $4.32 | $5.50 | 12 | FLUOR ENTERPRISES, INC. | TxDOT |
| 04 NOV 2026 | A00209149 | Laredo District | 315 | $12.94 | $6.00 | $5.00 | 7 | STX CIVIL | TxDOT |
| 04 NOV 2026 | A00196925 | Paris District | 2,877 | $5.00 | $5.60 | $4.50 | 9 | HIGHWAY 19 CONSTRUCTION LLC | TxDOT |
| 04 NOV 2026 | A00188206 | Austin District | 21,627 | $4.20 | $3.88 | $3.25 | 6 | BOBCAT SERVICES, INC. | TxDOT |
| 03 NOV 2026 | A00197970 | Pharr District | 29,518 | $2.83 | $2.92 | $3.20 | 2 | FOREMOST PAVING, INC. | TxDOT |
| 03 NOV 2026 | A00184974 | Austin District | 54,084 | $5.00 | $4.44 | $2.97 | 6 | AUSTIN BRIDGE & ROAD SERVICES, LP | TxDOT |
| 07 OCT 2026 | A00132124 | Lufkin District | 19,394 | $5.00 | $6.00 | $6.00 | 7 | LONGVIEW BRIDGE AND ROAD, LTD. | TxDOT |
| 07 OCT 2026 | A00064192 | San Antonio District | 19,376 | $2.87 | $3.80 | $4.00 | 8 | HUNTER INDUSTRIES, LTD. | TxDOT |
| 30 SEP 2026 | A00223227 | Lufkin District | 1,819 | $4.12 | $4.56 | $5.00 | 2 | TEXAS MATERIALS GROUP, INC. | TxDOT |
| 03 SEP 2026 | A00123454 | Pharr District | 6,840 | $4.95 | $4.95 | $3.50 | 5 | REIM CONSTRUCTION, INC. | TxDOT |
| 03 SEP 2026 | A00206794 | San Antonio District | 14,585 | $3.43 | $3.00 | $3.42 | 3 | HUNTER INDUSTRIES, LTD. | TxDOT |
| 03 SEP 2026 | A00061184 | Austin District | 15,724 | $3.37 | $4.12 | $3.25 | 8 | HUNTER INDUSTRIES, LTD. | TxDOT |
| 03 SEP 2026 | A00212859 | Fort Worth District | 539 | $4.40 | $4.75 | $6.00 | 7 | JAY MILLS CONTRACTING, INCORPORATED | TxDOT |
| 02 SEP 2026 | A00121174 | Pharr District | 40,353 | $1.00 | $4.00 | $3.50 | 7 | IOC COMPANY LLC | TxDOT |
Filter this item by your own quantity, district and period, or check your price against it, in the TxDOT explorer.
How these prices were read
TxDOT Bid Tabulations open-data export (data.texas.gov) from September 2024, read 21 November 2026, and TxDOT's legacy Tabulation of Bids pages for January 2020 to August 2024. The legacy pages are a large sample, not every contract: their file names were reused from year to year. Their district is the one TxDOT gives the county. Bids that did not match their published total are left out.
- Statistics leave out bids over three times the low bid, zero or negative prices and token prices under 5% of the median.
- Item codes and units are TxDOT's own: this item is compared with TxDOT contracts only.
- Prices are bid prices, not paid prices, and are not adjusted for inflation. Use them as a reference range, never as a quote.
Your own bid history, read the same way
Mirage deploys AI agents for heavy civil estimating teams: quantities from the plan set, specs and addenda read, and bid tabs compared, inside your systems and your rules.