D-gr hma ty-b PG64-22 unit price, Texas
Low bidders on TxDOT contracts carried a median of $95.96 per TON for item 30766001, d-gr hma ty-b pg64-22, from 06 FEB 2020 to 02 AUG 2024, across 251 low bids. Half of all 1,113 bids fell between $75.00 and $120.30.
- Owner
- Texas DOT
- Item
- 30766001
- Unit
- TON
- Latest letting
- 02 AUG 2024
By year of letting
| Year | Contracts | Low bids | Low-bid median | All bids | Median, all bids |
|---|---|---|---|---|---|
| 2020 | 49 | 49 | $74.00 | 270 | $75.60 |
| 2021 | 62 | 62 | $74.00 | 318 | $76.47 |
| 2022 | 29 | 29 | $105.63 | 119 | $110.00 |
| 2023 | 66 | 66 | $113.15 | 237 | $121.00 |
| 2024 | 45 | 45 | $120.00 | 169 | $120.00 |
Bid prices as published, not adjusted for inflation.
By district
| District | Low bids | Low-bid median | All bids | Median, all bids |
|---|---|---|---|---|
| San Antonio District | 45 | $76.80 | 258 | $77.02 |
| Austin District | 34 | $76.00 | 192 | $78.50 |
| Fort Worth District | 28 | $97.02 | 148 | $99.00 |
| Yoakum District | 27 | $102.00 | 99 | $109.70 |
| Wichita Falls District | 23 | $98.00 | 85 | $103.46 |
| Brownwood District | 15 | $110.00 | 51 | $115.00 |
| Corpus Christi District | 9 | $93.00 | 48 | $100.42 |
| Waco District | 11 | $71.00 | 44 | $78.00 |
| Amarillo District | 13 | $120.00 | 42 | $120.00 |
| Beaumont District | 9 | $150.00 | 25 | $133.50 |
| Abilene District | 6 | $162.75 | 25 | $190.00 |
| Lufkin District | 6 | $135.00 | 24 | $125.00 |
Districts with at least three low bids, over all lettings.
By quantity
| Quantity (TON) | Low bids | Low-bid median |
|---|---|---|
| 6 to 2,109 | 62 | $136.15 |
| 2,399 to 8,039 | 63 | $100.00 |
| 8,058 to 21,866 | 63 | $80.90 |
| 21,918 to 250,943 | 63 | $92.00 |
The low bids split into four bands of equal count by the quantity on the contract. Larger quantities usually carry lower unit prices.
Latest contracts with this item
| Let | Contract | District | Quantity | Low bidder's price | Median | Estimate | Bids | Low bidder | Source |
|---|---|---|---|---|---|---|---|---|---|
| 02 AUG 2024 | 08243202 | Houston District | 185 | $149.17 | $182.70 | $110.00 | 4 | JAMES CONSTRUCTION GROUP, LLC | TxDOT |
| 10 JUL 2024 | 07243204 | Yoakum District | 20,542 | $93.40 | $99.00 | $115.00 | 6 | HUNTER INDUSTRIES, LTD. | TxDOT |
| 10 JUL 2024 | 07243214 | Beaumont District | 6,010 | $150.00 | $165.12 | $160.00 | 3 | CORNERSTONE PAVING AND CONSTRUCTION, L.L.C. | TxDOT |
| 10 JUL 2024 | 07243215 | Wichita Falls District | 8,676 | $105.00 | $132.50 | $100.00 | 4 | ZACK BURKETT CO. | TxDOT |
| 09 JUL 2024 | 07243002 | El Paso District | 39,560 | $108.50 | $116.75 | $100.00 | 2 | SUNDT CONSTRUCTION, INC. | TxDOT |
| 09 JUL 2024 | 07243005 | Abilene District | 14,087 | $130.00 | $172.00 | $130.00 | 3 | FNF CONSTRUCTION, INC. | TxDOT |
| 09 JUL 2024 | 07243018 | Bryan District | 6 | $750.00 | $575.00 | $160.00 | 4 | LARRY YOUNG PAVING, INC. | TxDOT |
| 09 JUL 2024 | 07243020 | Beaumont District | 1,361 | $150.10 | $150.00 | $173.30 | 3 | CORNERSTONE PAVING AND CONSTRUCTION, L.L.C. | TxDOT |
| 06 JUN 2024 | 06243201 | San Antonio District | 108,426 | $81.82 | $88.00 | $105.00 | 5 | WEBBER, LLC | TxDOT |
| 06 JUN 2024 | 06243228 | Fort Worth District | 152 | $174.00 | $192.00 | $135.00 | 2 | RAGLE CONSTRUCTION, INC. | TxDOT |
| 05 JUN 2024 | 06243008 | Wichita Falls District | 52,123 | $116.00 | $130.09 | $110.00 | 4 | A. L. HELMCAMP, INC. | TxDOT |
| 05 JUN 2024 | 06243013 | Yoakum District | 209 | $225.00 | $287.50 | $165.00 | 2 | CEKRA INC. | TxDOT |
| 05 JUN 2024 | 06243014 | Amarillo District | 1,394 | $150.00 | $214.50 | $120.00 | 3 | L A FULLER & SONS CONSTRUCTION, LTD. | TxDOT |
| 05 JUN 2024 | 06243018 | Fort Worth District | 803 | $300.00 | $300.00 | $145.00 | 5 | GRATIOT CONSTRUCTION, LTD. | TxDOT |
| 05 JUN 2024 | 06243022 | Wichita Falls District | 6,731 | $123.00 | $142.25 | $100.00 | 4 | ZACK BURKETT CO. | TxDOT |
Filter this item by your own quantity, district and period, or check your price against it, in the TxDOT explorer.
How these prices were read
TxDOT Bid Tabulations open-data export (data.texas.gov) from September 2024, read 21 November 2026, and TxDOT's legacy Tabulation of Bids pages for January 2020 to August 2024. The legacy pages are a large sample, not every contract: their file names were reused from year to year. Their district is the one TxDOT gives the county. Bids that did not match their published total are left out.
- Statistics leave out bids over three times the low bid, zero or negative prices and token prices under 5% of the median.
- Item codes and units are TxDOT's own: this item is compared with TxDOT contracts only.
- Prices are bid prices, not paid prices, and are not adjusted for inflation. Use them as a reference range, never as a quote.